Photo Speaks: Update on roof works. 1 Like
|
![]() |
Stage 12. FIXING OF LONG SPAN ALUMINIUM. Total Area: 340m2 Type of sheet: 0.55 foreign sheet. 1 Like
|
![]() |
Updates on the Perimeter fencing...
|
![]() |
More images
|
![]() |
Day 3
|
![]() |
Stage 11. CONSTRUCTION OF ROOF CARCASS. Expected roof height: 3.90m Day 1: Purchase and supply of timber for roof carcass. Materials; 2 x 6” Akputu wood 190 lenghts 2 x 4” Akputu wood 200 lenghts 2 x 3” Ebuni wood 290 lenghts 2 x 2” Ebuni wood 160 lenghts 4” nail 2cartons 3” nail 1carton 1 Like
|
![]() |
Casting of the Soakaway slab / Perimeter fencing 2 Likes
|
![]() |
More images
|
![]() |
Stage 10. Casting of the Concrete Fascia. Materials: Cement: 35 Bags Sharp Sand: 20 tons Granite 1/2": 20 tons Water: 1 Like
|
![]() |
More images 1 Like
|
![]() |
Stage 9. Construction of form work for the Concrete fascia (Carpentry works, Reinforcement works). CONCRETE FASCIA: Type: in-situ cast Materials: Wood: Ply wood 15 1 x 12” 95 lenghts 2 x 3” 90 lenghts 3” nails 2” nails 1.5”nails Machine works. Reinforcement. Y12 Iron rods: 33 lenghts Y10 Iron rods: 30 lenghts Y8 Iron rods: 22 lenghts Binding wire: I roll
|
![]() |
Hello everyone, sorry there had been no update on this particular project for a while now, that’s due to paucity in cash flow and colliding engagements. Henceforth, I will bring you up to date on how far we’ve gone and subsequently keep up with timely updates. Regards, Olabamijie. |
![]() |
NaijaFutbol: Thanks 1. If you look at the layout, you'll notice we implemented the interior changes after the dpc not at the initial digging/excavation stage; the reinforcement was to provide necessary and required support for the the internal walls so as to further prevent any case of settlement. Note: we ensured it is economical by using Y8 iron bars. 2. We plan to do Insitu cast for the Concrete facial though but to further answer your question, the four edge columns are functional; we'll adequately reinforce our head beam bearing in mind that the relative weight of our roof will be resting on those four ends, we ensured our lintel beam runs through the whole building thus linking the components (Beam/columns/foundation) adequately as you can see in the pictures. That's considerably efficient and cheaper compared to having columns at every here and there as you must have been used too. Once again, thanks for following and most importantly, your input. Regards Olabamijie 2 Likes |
![]() |
More block work images/ form work for Gate house Dpc
|
![]() |
More pictures.
|
![]() |
Images of: More Block work on the Main Building Block work for the Soakaway PreCast column finishes[b][/b]
|
![]() |
More pictures
|
![]() |
Stage 8: Casting of the connecting lintel and columns: Excavation for perimeter fence, and soak away (Completion) Details Beam Depth of lintel beam: 225mm Width of lintel beam: 225mm Columns 225mm x 225mm Materials: Cement: 25 bags Sharp sand: 10 tonns Granite: 10 tons 1 x 12" 60 length 2" Concrete nail Workmanship for Carpenter; N25,000 Casting: N50,000 Y12 iron bars: 20 lenghts. Y10 iron bars: 8 lenghts.
|
![]() |
More block works pictures. Thanks for following this thread; more so, stay tuned. 1 Share
|
![]() |
More Block work.
|
![]() |
MI
|
![]() |
More Images
|
![]() |
Stage 7. Block forming for the Superstructure. 6" Blocks for Interior. 9" Blocks for Exterior.
|
![]() |
abdulwastecx: Thanks Boss. |
![]() |
rulesman: Thank you Sir, We are AJIBSHELTER CONSTRUCTIONs, you can reach us through; Tel: 08078222578 Email: ajibshelter@gmail.com |
![]() |
More Images 1 Like
|
![]() |
Stage 6. Casting of the dpc. Specifications Mix Ratio: 1:3:6 Depth: 5” Materials: Cement: 70 Bags Sharp Sand: 20 tons Granite: 30 tons Mixer Water: Labour for Casting
|
![]() |
igbi: I really cant say if there's any free plot within the estate. If you are really interested, I can inquire for you. Kindly drop a contact through which I could give you the feedback. |
![]() |
Stage 5. Waste pipe plumbing work / steel reinforcement works for dpc/ formwork for dpc. Plumbing 4” over length pipe: 2” over length pipe: 4” original bend: 2” original bend: 2” tee: Tin of gum Steel reinforcement 120 Y8mm Binding wire Formwork for dpc 1 by 12” plank: 2 by 2”: cc Hajji M 1 Like
|
![]() |
More images
|
![]() |
Stage 4. Filling and Compaction. Soil compaction is a vital part of the construction process. It is used for support of structural entities such as building foundations, roadways, walkways, and earth retaining structures to name a few. In general, the pre selected soil should have adequate strength, be relatively in-compressible so that future settlement is not significant, be stable against volume change as water content or other factors vary, be durable and safe against deterioration. Materials/Expenditures Laterite 12 Tyres : 4 loads. cc lawyer
|
![]() |
MORE IMAGES 1 Like
|
(Go Up)
Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health religion celebs tv-movies music-radio literature webmasters programming techmarket Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 25 |