Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by spyder880(m): 10:30pm On Jun 15, 2021 |
More 1 Like
|
Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by spyder880(m): 10:33pm On Jun 15, 2021 |
More...... 1 Like
|
Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by spyder880(m): 7:57am On Jun 16, 2021 |
We have paid for a lot of materials needed for the first floor partitioning walls of this building, the blocks will be delivered today and my workers will start taking them upstairs for our use soon. 1 Like |
Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by Inception(m): 8:48am On Jun 21, 2021 |
Nice one sir What spacing did you use for the 12mm rod decking reinforcement (Longitudinal and transverse) It looks like 200mm (8 inches) from the pics posted though |
Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by spyder880(m): 9:12am On Jun 21, 2021 |
Inception: We used 150mm x 175mm (6"x7" ) 2 Likes |
Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by davle: 10:42pm On Jun 21, 2021 |
Weldone oga spyder, is it possible to tell us the cost of this decking, material and workmanship sir |
Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by spyder880(m): 7:47am On Jun 22, 2021 |
davle: I will give a list later today, already moving to site now. 2 Likes |
Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by Tiztonio(m): 7:57am On Jun 22, 2021 |
spyder880:Thanks, this will be helpful to us |
Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by spyder880(m): 8:00pm On Jun 22, 2021 |
We have started working on the block walls of this building, more pictures later. 2 Likes |
Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by spyder880(m): 10:59pm On Jun 22, 2021 |
List of Materials and workmanship for the construction of suspended slab for a double wing of 2 bedroom flats at Asaba. 1. 1x12x12 wood (345) x 1300 = N448,500 2. 2x2x12 wood (100) x 350 = N35,000 3. Long bamboo (178) x 400 = N71,200 4. 1x9x12 wood (10) 1,100 = N11,000 5. 1x6x12 wood (75) 650 = N48,750 6. Bag of 3" nails (2) 13,500 = N27,000 7. Half bag of 2" nails N8,500 8. Roll of nylon sheets (6) 7,000 = N42,000 9. 16mm rods (80) x 6,262 = N501,000 10. 12mm rods (245) x 3,522.24 = N862,950 11. 8mm rods (45) x 1733.33 = N78,000 12. Roll of binding wire N13,300 13. Electrical pipes, boxes,gum etc. N122,053.75 14. Bags of cement (181) x 3450 = N624,450 15. Trips of sharp sand (7) x 19,714.28 = N138,000 16. Trips of chippings (6) x 60,000 = N360,000 17. Carpentry N130,000 18. Iron fitters N120,000 19. Electricians N60,000 20. Concrete casters N250,000 21. Site foreman 20,000 22. Security man N20,000 23. Transportation and loading N47,950 Grand total N4,052,953.75 Promise kept, I will be around to entertain some questions. Thanks all. Edit: Cost prices in fractions indicate that we bought several quantities at different times and at different prices, so you are likely seeing average costs as unit prices in some materials. 4 Likes |
Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by davle: 6:08pm On Jun 23, 2021 |
spyder880: Thanks for this sir 1 Like |
Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by davle: 6:13pm On Jun 23, 2021 |
spyder880: Will I be correct to say you use the 1×6×12 for the deck surrounding. |
Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by spyder880(m): 11:09pm On Jun 23, 2021 |
davle: Yes, I also use it for the staircase risers. 1 Like |
Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by spyder880(m): 12:26am On Jun 26, 2021 |
We worked in this site on Friday, more pictures from our work here when day breaks. Good night my people. 2 Likes
|
Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by spyder880(m): 7:18am On Jun 26, 2021 |
Good morning this morning, More updates from this our building site yesterday......... 2 Likes
|
Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by spyder880(m): 7:22am On Jun 26, 2021 |
Upstairs wall partitioning........... 2 Likes
|
Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by spyder880(m): 7:27am On Jun 26, 2021 |
Looking at the house from the road as we work on the walls...... 2 Likes
|
Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by omanzo02: 8:28am On Jun 26, 2021 |
spyder880: Where are you buying 1x12x12 board for ₦1300? I got 1x12x16 for ₦4200 lol, what is actually the big difference? It really getting funny? |
Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by spyder880(m): 9:16am On Jun 26, 2021 |
omanzo02: I bought it from Asaba there, at that building materials market, Timber section at the express road. I will call to know what the cost is as at today. 1 Like |
Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by omanzo02: 9:28am On Jun 26, 2021 |
spyder880:Seem woods are cheaper in Asaba region compare to Warri, Sapele and Benin. I keep hearing hand vs machine saw wood, it's strange handsaw that requires more effort is cheaper than machinesaw, sometime they think everyone are mumu! Lol 1 Like |
Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by michlins(m): 9:52am On Jun 26, 2021 |
omanzo02:machine saw should be more straight than handsaw. It's not the efforts but quality of finished products 2 Likes |
Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by omanzo02: 11:56am On Jun 26, 2021 |
michlins:Dude, where I am, anything made by hand is 4 times costly than machine produced, that's the hard reality, mechanical finished product are standard while manual labour product are regarded as special product. |
Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by michlins(m): 12:00pm On Jun 26, 2021 |
omanzo02:I don't know where you are but am telling you market reality and how they charge here. 1 Like |
Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by omanzo02: 12:09pm On Jun 26, 2021 |
michlins:I am only emphasising the value for labour! Beside, the price discrepancies is way too high between 1x12x12 and 1x12x16 in the same Delta state |
Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by Badgers14: 12:49pm On Jun 26, 2021 |
omanzo02: I understand your point of view but you need to account for the tradesmen performing does job where you are "compa" to our tradesmen in Nigeria. I am sure where you are people take pride in their work, are meticulous, working with precision aimed at delivering a durable and professional product... Our 9ja people will just do the job jaga jaga... then when you complain they get angry.. turn to emotional blackmail.. ehn ehn because you are a big man now you think I will be here slaving for you... or they say oga na so they dem do am... or complains that the work is too difficult or worse yet abandon the work half way through. Some of our tradesmen lack the patience and the skill to do their jobs effectively. 1 Like |
Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by dongc(m): 1:22pm On Jun 26, 2021 |
omanzo02: I understand your emphasis..based on handmade and mass production...mass production are mostly cheaper due to lower overhead because of quantity....not sure it is same criteria with the machine cut and handcut with wood in Nigerian scenario |
Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by spyder880(m): 1:58pm On Jun 28, 2021 |
Offloading more iron rods here, we're going to use these for our columns and beams reinforcement works starting this afternoon, More pictures later. 2 Likes
|
Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by spyder880(m): 7:33am On Jul 07, 2021 |
More pictures from our work on this block of flats here.......... 1 Like
|
Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by spyder880(m): 7:40am On Jul 07, 2021 |
Places we had cast with concrete, we are removing the wood......... 1 Like
|
Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by spyder880(m): 7:55am On Jul 07, 2021 |
Beams, as seen from the top of the building....... 1 Like
|
Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by spyder880(m): 8:01am On Jul 07, 2021 |
The work done so far, more work is already underway in this site this morning........... 1 Like
|
Re: The Making Of The " Asaba Block Of 6 Flats Of 2 Bedrooms" by spyder880(m): 8:05am On Jul 07, 2021 |
We will head straight into the decking of the second floor as soon as we complete this first floor walls. 1 Like |
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) ... (16) (Reply)
Just Moved In Three Months Ago And Told To Pack Out Now. / Anambra Government Demolishes Brothel In Kara, Ogbaru (Photos) / Businesses And Houses Underwater In Lekki
(Go Up)
Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health religion celebs tv-movies music-radio literature webmasters programming techmarket Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) Nairaland - Copyright © 2005 - 2025 Oluwaseun Osewa. All rights reserved. See How To Advertise. 42 |