Re: Construction Diary Of 8units Of 2/3brds Flat Structure By ARBO CONTRACTOR LTD by rotecch77(m): 4:53pm On Nov 21, 2021 |
More update pics loading |
Re: Construction Diary Of 8units Of 2/3brds Flat Structure By ARBO CONTRACTOR LTD by rotecch77(m): 7:23am On Nov 23, 2021 |
Do you know that without adequate ventilation in a building it can cause “SICK BUILDING SYNDROME” Not only this Dust Heavy smoke Old working computer Chemicals All these can lead to sick building syndrome Let’s follow professional advise in most of our construction work. Reach out to us today for your Building drawing Building construction Mini flexible and rigid road Maintenance work Service work Finishing work @ Arbo Contractor Ltd We care 08066619493 |
Re: Construction Diary Of 8units Of 2/3brds Flat Structure By ARBO CONTRACTOR LTD by rotecch77(m): 9:01pm On Nov 23, 2021 |
Casting of the slab is going on here
|
Re: Construction Diary Of 8units Of 2/3brds Flat Structure By ARBO CONTRACTOR LTD by rotecch77(m): 8:51am On Nov 24, 2021 |
Casting done |
Re: Construction Diary Of 8units Of 2/3brds Flat Structure By ARBO CONTRACTOR LTD by rotecch77(m): 7:35pm On Nov 25, 2021 |
More pics loading Material used are as follow 320 bags of cement 4 lorries of 30 tones sharp sand 90 tones of granite Labour cost 320k casting only oo |
Re: Construction Diary Of 8units Of 2/3brds Flat Structure By ARBO CONTRACTOR LTD by rotecch77(m): 6:49am On Nov 27, 2021 |
Upper floor block setting will comes up soon Watch out |
Re: Construction Diary Of 8units Of 2/3brds Flat Structure By ARBO CONTRACTOR LTD by rotecch77(m): 8:34am On Dec 04, 2021 |
Upper floor Blk settings loading |
Re: Construction Diary Of 8units Of 2/3brds Flat Structure By ARBO CONTRACTOR LTD by rotecch77(m): 3:28pm On Dec 06, 2021 |
New week quote” When a customer complains, he is doing you a special favor; he is giving you another chance to serve him to his satisfaction. You will appreciate the importance of this opportunity when you consider that the customer’s alternative option was to desert you for a competitor.” |
Re: Construction Diary Of 8units Of 2/3brds Flat Structure By ARBO CONTRACTOR LTD by rotecch77(m): 8:15pm On Dec 09, 2021 |
Loading |
Re: Construction Diary Of 8units Of 2/3brds Flat Structure By ARBO CONTRACTOR LTD by rotecch77(m): 12:10pm On Dec 11, 2021 |
“If people are doubting how far you can go, go so far that you can’t hear them anymore.” —-/ Fact |
Re: Construction Diary Of 8units Of 2/3brds Flat Structure By ARBO CONTRACTOR LTD by rotecch77(m): 3:38pm On Dec 18, 2021 |
More update pics as we are progressing
|
Re: Construction Diary Of 8units Of 2/3brds Flat Structure By ARBO CONTRACTOR LTD by rotecch77(m): 9:11am On Dec 22, 2021 |
Progress pics About 5,000 blocks gone for this upper floor Still counting…..:::: don’t be surprised this is 8 flats 1 Like
|
Re: Construction Diary Of 8units Of 2/3brds Flat Structure By ARBO CONTRACTOR LTD by rotecch77(m): 6:32pm On Dec 23, 2021 |
Progress update pics
|
Re: Construction Diary Of 8units Of 2/3brds Flat Structure By ARBO CONTRACTOR LTD by rotecch77(m): 10:10am On Jan 01, 2022 |
Happy new year to all our esteemed clients, readers, and guests may this new year 2022 be a fruitful one for all of us. Amen. Arbo contractor Ltd Rotech building concept We care |
Re: Construction Diary Of 8units Of 2/3brds Flat Structure By ARBO CONTRACTOR LTD by rotecch77(m): 3:01pm On Jan 02, 2022 |
New year 2022 post Update on the ongoing project
|
Re: Construction Diary Of 8units Of 2/3brds Flat Structure By ARBO CONTRACTOR LTD by rotecch77(m): 10:33am On Jan 03, 2022 |
Roofing and little little work is loading to complete the carcass work.
|
Re: Construction Diary Of 8units Of 2/3brds Flat Structure By ARBO CONTRACTOR LTD by rotecch77(m): 9:28am On Jan 05, 2022 |
More pics
|
Re: Construction Diary Of 8units Of 2/3brds Flat Structure By ARBO CONTRACTOR LTD by rotecch77(m): 9:03am On Jan 14, 2022 |
Roofing carcass and roof covering preparation is in progress. Watch out. |
Re: Construction Diary Of 8units Of 2/3brds Flat Structure By ARBO CONTRACTOR LTD by rotecch77(m): 1:28pm On Jan 18, 2022 |
Watch out for the roof carcass and roof covering here soon |
Re: Construction Diary Of 8units Of 2/3brds Flat Structure By ARBO CONTRACTOR LTD by rotecch77(m): 8:58am On Jan 23, 2022 |
Watch out for the roof-work, pics loading |
Re: Construction Diary Of 8units Of 2/3brds Flat Structure By ARBO CONTRACTOR LTD by rotecch77(m): 8:52pm On Jan 25, 2022 |
More update pics Final roof parapet block work loading after roof carcass work
|
Re: Construction Diary Of 8units Of 2/3brds Flat Structure By ARBO CONTRACTOR LTD by rotecch77(m): 6:30pm On Jan 26, 2022 |
Roof carcass still in progress
|
Re: Construction Diary Of 8units Of 2/3brds Flat Structure By ARBO CONTRACTOR LTD by rotecch77(m): 6:38am On Jan 27, 2022 |
After this, finishings will follow Watch out ! |
Re: Construction Diary Of 8units Of 2/3brds Flat Structure By ARBO CONTRACTOR LTD by rotecch77(m): 3:42pm On Jan 29, 2022 |
Progress update
|
Re: Construction Diary Of 8units Of 2/3brds Flat Structure By ARBO CONTRACTOR LTD by rotecch77(m): 8:40am On Jan 30, 2022 |
Roof carcass done Roof covering in progress with long span Aluminum of 0.55m usage. We don’t use anything lesser than this gauge in all our projects Pics loading
|
Re: Construction Diary Of 8units Of 2/3brds Flat Structure By ARBO CONTRACTOR LTD by rotecch77(m): 9:20am On Jan 31, 2022 |
More
|
Re: Construction Diary Of 8units Of 2/3brds Flat Structure By ARBO CONTRACTOR LTD by rotecch77(m): 6:48am On Feb 06, 2022 |
Finishings stage loading Watch out |
Re: Construction Diary Of 8units Of 2/3brds Flat Structure By ARBO CONTRACTOR LTD by rotecch77(m): 8:42pm On Feb 08, 2022 |
Coming soon |
Re: Construction Diary Of 8units Of 2/3brds Flat Structure By ARBO CONTRACTOR LTD by rotecch77(m): 7:14am On Feb 15, 2022 |
Update loading |
Re: Construction Diary Of 8units Of 2/3brds Flat Structure By ARBO CONTRACTOR LTD by rotecch77(m): 7:43am On Mar 05, 2022 |
Watch out |
Re: Construction Diary Of 8units Of 2/3brds Flat Structure By ARBO CONTRACTOR LTD by Mukah1234(m): 12:44pm On Mar 08, 2022 |
Hello rotech. I sent an email to you. |
Re: Construction Diary Of 8units Of 2/3brds Flat Structure By ARBO CONTRACTOR LTD by rotecch77(m): 4:17pm On Mar 08, 2022 |
Mukah1234:Ok I will check |
(1) (2) (3) (4) (5) (6) (7) (8) (Reply)
Short Lets In Lagos, Nigeria / The Power Of Real Estate* / 4bedroom bungalow with 2bedroom flat In Gbetu,awoyaya for sale (with Pics)
(Go Up)
Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health religion celebs tv-movies music-radio literature webmasters programming techmarket Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 12 |