A Nairanlander's Building Project by abdulwastecx(m): 1:06am On Jun 03, 2015 |
project location : chokocho, Port Harcourt, Rivers state. project description : construction of a sewage disposal system soak away/ septic tank, completion of ongoing 6 flat on self contain job duration : one month. |
Re: A Nairanlander's Building Project by amichaelz101(m): 1:07am On Jun 03, 2015 |
K |
Re: A Nairanlander's Building Project by abdulwastecx(m): 1:11am On Jun 03, 2015 |
the soakaway/septic tank system Due to land constrain the septic tank has a dimension of 7ft x 15ft x 10ft, the dimension of pit dug to accommodate this structure was 10ft x 186ft x 12ft. the extral dimension was to allow for ease of work and movement into the system. Material for the soak away/septic tank includes the following 1. 3/8 sharp sand as both the coarse and fine aggregates in the concrete 2. dangote portland cement 3. High yield bar of 12mm as main reinforcement and 10mm bar as links 4. soft plank as formwork |
Re: A Nairanlander's Building Project by abdulwastecx(m): 1:15am On Jun 03, 2015 |
procedure 1. the pit digging was done manually by 3 men for a period of three days at a cost of N35,000. we encountered some problem due to rainfall and the poor strength of the soil. 2. Due to anticipated poor bearing capacity of the soil, a raft beam was used as the foundation of the soak away, this cost was not allowed for during the planning process for the job 1 Share
|
Re: A Nairanlander's Building Project by abdulwastecx(m): 1:27am On Jun 03, 2015 |
Iron work for the raft beam : 12nr of Y12 was use @ N1,200/nr = N14,400 4nr of Y10 was use as links @ N1,000/nr = N4,000 Iron work For the six supporting column the height of the column is 3m 8Y12 was used as main reinforcement = N9,600 4Y10 was used as the link = N4,000 binding wire = N3,500 Total on material = N35,500 2 Likes |
Re: A Nairanlander's Building Project by HzRF(m): 1:28am On Jun 03, 2015 |
Gud one. Keep it up |
Re: A Nairanlander's Building Project by abdulwastecx(m): 1:34am On Jun 03, 2015 |
the making of the raft beam foundation for the soakaway foundation: 8bags of cement was used for the casting @ N2,100/nr = N 16,000 four plank of wood @ N1,000/nr = N4,000 total = N20,000 workmanship: 2 nr of iron bender @ N4,000/nr = N8,000 3 labour @ N2,000/nr = N6,000 1 Like
|
Re: A Nairanlander's Building Project by abdulwastecx(m): 1:45am On Jun 03, 2015 |
completion of the soakaway foundation
|
Re: A Nairanlander's Building Project by abdulwastecx(m): 1:49am On Jun 03, 2015 |
laying of block 1 Like
|
Re: A Nairanlander's Building Project by abdulwastecx(m): 1:51am On Jun 03, 2015 |
More block work
|
Re: A Nairanlander's Building Project by abdulwastecx(m): 2:01am On Jun 03, 2015 |
mid way beam to improve the strength
|
Re: A Nairanlander's Building Project by abdulwastecx(m): 2:03am On Jun 03, 2015 |
complete block wall of the soak away
|
Re: A Nairanlander's Building Project by mufutau55(m): 2:30am On Jun 03, 2015 |
Wow! Good work. I am following keenly. Some of this Clients are lucky to have you as their Builder.. You are a good teacher too.. Hajji M. 3 Likes |
Re: A Nairanlander's Building Project by abdulwastecx(m): 2:31am On Jun 03, 2015 |
mufutau55: thank you sir... 2 Likes |
Re: A Nairanlander's Building Project by Nobody: 3:21am On Jun 03, 2015 |
Nice one |
Re: A Nairanlander's Building Project by caesaraba(m): 8:06am On Jun 03, 2015 |
Nice. Following. |
Re: A Nairanlander's Building Project by iCool(m): 3:26pm On Jun 07, 2015 |
Very detailed with pictures, I LOVE the part where you give details of the pricing. Good Work! 2 Likes 1 Share |
Re: A Nairanlander's Building Project by abdulwastecx(m): 9:17am On Jun 13, 2015 |
here is the completion of the soak away/septic tank work
|
Re: A Nairanlander's Building Project by abdulwastecx(m): 9:25am On Jun 13, 2015 |
The second face of the job involve the completion of the six units of one room self contain each. A three dimension model was produce to guild the completion work 1 Like
|
Re: A Nairanlander's Building Project by abdulwastecx(m): 9:32am On Jun 13, 2015 |
we finally settled for the second one. The first activity involve the removal of the poorly done front arch. The following reasons necessitate for the removal 1. Heavy cracking of the block below the arch due to absence of supporting columns 2. poor workmanship
|
Re: A Nairanlander's Building Project by Nobody: 10:05am On Jun 13, 2015 |
abdulwastecx: @ abdulwastecx: Sorry, I missed the part where you did the cost of materials for casting the top part of the tank. Plus, can the reinforcement stand the weight of a vehicle? The steel rods there don't look like 12mm to me oh! Can you please enlighten me. |
Re: A Nairanlander's Building Project by MANGAM(m): 10:08am On Jun 13, 2015 |
Neat work, and I like ur detailed explanation |
Re: A Nairanlander's Building Project by abdulwastecx(m): 2:15pm On Jun 13, 2015 |
ijapa888: The main bar was 12mm spaced at 200mm center to center while the distribution bar was 10mm spaced at 250mm center to center. The aim of the job is not to allowed vehicle to pass over it but for the side of the wall to resist the overburden soil pressure which may result from moving vehicle adjacent to the wall. 2 Likes |
Re: A Nairanlander's Building Project by abdulwastecx(m): 2:28pm On Jun 16, 2015 |
continuation of the repair work...
|
Re: A Nairanlander's Building Project by abdulwastecx(m): 7:14pm On Jun 25, 2015 |
continuation of the work:The first task was the completion of the front arch
|
Re: A Nairanlander's Building Project by abdulwastecx(m): 12:28am On Jun 26, 2015 |
here is the roofing work wood type : 2 x 4 hard wood of 18ft length 2 x 4 hard wood of 12ft length 2 x 3 hard wood purline of 12ft length 1 x 10 facial board 0f 11ft lenth 4'' and 3'' nail Wood treatment chemical description of the roofing spacing wooden roof truss = 4ft center to center height of the king post = 10ft (3m)
|
Re: A Nairanlander's Building Project by abdulwastecx(m): 12:34am On Jun 26, 2015 |
more pics
|
Re: A Nairanlander's Building Project by mufutau55(m): 1:49am On Jun 26, 2015 |
Re: A Nairanlander's Building Project by princejones(m): 4:35am On Jun 26, 2015 |
Nice job my guy and pray for more jobs and contracts for we young contractors and building engineers |
Re: A Nairanlander's Building Project by abdulwastecx(m): 9:28am On Jun 27, 2015 |
princejones: amin sir |
Re: A Nairanlander's Building Project by abdulwastecx(m): 9:28am On Jun 27, 2015 |
mufutau55: yes sir..long time sir |
Re: A Nairanlander's Building Project by abdulwastecx(m): 10:58am On Jun 29, 2015 |
continuation of the roof
|
House Collapsed In Adeniji-Adele Street Lagos With People Trapped / My Father's House Was Sold Without My Consent / Construction Of A 10 Story Office Building
(Go Up)
Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health religion celebs tv-movies music-radio literature webmasters programming techmarket Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 43 |