Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 10:21pm On Aug 18, 2015 |
Block work in progress!
|
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 1:08pm On Aug 19, 2015 |
segcymoor:
|
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by twinskenny(m): 1:14pm On Aug 19, 2015 |
[quote author=segcymoor post=37118190][/quote] weldone boss |
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by semitunde: 4:25pm On Aug 19, 2015 |
[quote author=segcymoor post=37118190][/quote] What you have here is like a process that I like. It makes a building look good and well done. Its about having your columns done first and then doing your blockwall after it, then do your lintels and next floor beams and slabs. With this system, you take control of the straightness of your walls from the bricklayers and this reduces errors. Its almost like doing a framed structure type of construction but just a little different. Its not as expensive as using a framed structure process.
|
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 10:31pm On Aug 19, 2015 |
semitunde:on point! 1 Like |
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by twinskenny(m): 9:11am On Aug 20, 2015 |
semitunde: I really want to contact you sir... hope u can provide me with your contact information. Thank you |
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 4:52pm On Aug 20, 2015 |
Men at Work!
|
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 8:31pm On Aug 20, 2015 |
segcymoor:
|
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by semitunde: 9:44pm On Aug 20, 2015 |
twinskenny: You do windows or roofs is it? I usually call those on here who I have their details or who are referred by others here. I'll call when the chance presents itself. I'm just the project manager, not the owner. Subcontracting can sometimes be like a cult thing, where the only way another gets in is if the first on fails on delivery or quality. You'll be kept in view for that time. Besides, I've knocked quite a few heads on politics section and I won't want my pics becoming a trending topic here |
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by twinskenny(m): 6:29am On Aug 21, 2015 |
semitunde:Lol.u are good sir.. Am into low voltage per say... and I.have various thread too. Cctv Access control Satellite tv distribution Voice.and data Multimedia Thank you sir 1 Like |
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 5:50pm On Aug 21, 2015 |
Still. ...........on block setting
|
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 6:52pm On Aug 22, 2015 |
Up next : casting to column |
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 2:12pm On Aug 23, 2015 |
Happy Sunday |
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 4:47pm On Aug 24, 2015 |
segcymoor:
|
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 7:07am On Aug 25, 2015 |
Formwork in progress!
|
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 12:12pm On Aug 26, 2015 |
Casting to column in progress! |
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 7:56pm On Aug 26, 2015 |
segcymoor: |
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 3:26pm On Aug 27, 2015 |
All things be equal. We should commence working on next slab by next week |
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 10:23pm On Aug 28, 2015 |
Completion of casting columns and lintel
|
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 9:14pm On Aug 29, 2015 |
Update : Taking level |
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by lucabrasi(m): 2:43am On Aug 30, 2015 |
segcymoor:pls what email can i reach you on for matters regarding business |
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by twinskenny(m): 7:40am On Aug 30, 2015 |
segcymoor:happy sunday my oga |
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 7:55am On Aug 30, 2015 |
lucabrasi:mooredesignbuild@gmail.com |
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by Dominionng(m): 8:34am On Aug 30, 2015 |
semitunde: Boss. Do go check my signature for ceiling works. Kind regards.... |
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 10:38pm On Aug 30, 2015 |
twinskenny:Same here. |
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 2:01pm On Sep 01, 2015 |
Formwork:Curing enough to remove ..we are able to achieve strong and neat concrete
|
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 4:12pm On Sep 02, 2015 |
Formwork in progress
|
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 10:11am On Sep 03, 2015 |
Target:we schedule to cast this slab less than weeks away |
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 9:23pm On Sep 04, 2015 |
segcymoor:Formwork almost completed. ...bending schedule in progress |
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 4:23pm On Sep 07, 2015 |
Reinforcement work in progress |
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by erico2k2(m): 5:22pm On Sep 07, 2015 |
segcymoor:Oga I site you ooh |
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 6:22pm On Sep 07, 2015 |
erico2k2:where? |
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) ... (43) (Reply)
Man Building A House Came Across Ant Hill And Preserved It / Lady Shares Video Of House An Agent Took Her To In Lagos For N300k / See The Tallest Building In Africa
Viewing this topic: 1 guest(s)
(Go Up)
Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health religion celebs tv-movies music-radio literature webmasters programming techmarket Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 29 |