BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by BITSWORKS: 7:52pm On Mar 30, 2017 |
BITSWORKS Nigeria is a multi-discipline construction company comprising of architects, builders, civil engineers and interior designers. We currently have a brief for a client to construct 4 units of 2 bedrooms flats on a plot of land in Mowo-Kekere, Ikorodu. There is an existing bungalow in the land already but it is a fairly flat terrain. We will share the floor plan, elevations and 3D views once we have finalized on the design and permission has been given by the client. Size of land - 640 sqm Total area of building - 168.4sqm Estimated budget for construction - currently unknown PROJECT timeline - 10 months We have started with the foundation work and work is moving at a steady pace. Excavation and blinding of the foundation has been completed.
|
Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by BITSWORKS: 8:00pm On Mar 30, 2017 |
Block setting of the foundation, we are using 9" vibrated blocks .
|
Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by chuksjuve(m): 8:23pm On Mar 30, 2017 |
Nice one...keep us updated.. for your landscape and beautification, kindly contact us by checking our profile for more details.. keep it up |
Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by BITSWORKS: 5:57am On Mar 31, 2017 |
More block setting work pictures.
|
Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by BITSWORKS: 6:03am On Mar 31, 2017 |
chuksjuve: Noted sir. Thanks for the kind words. |
Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by BITSWORKS: 6:06am On Mar 31, 2017 |
Four coach of block setting was achieved and the foundation was high enough. Work on the short columns in progress.
|
Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by Onuokwu: 4:57pm On Mar 31, 2017 |
Can you share the plan of this house please? |
Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by BITSWORKS: 10:26am On Apr 01, 2017 |
Backfilling of the foundation trenches in progress.
|
Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by mufutau55(m): 12:47am On Apr 02, 2017 |
Very good straight line block laying work. Keep it up. Hajji M. |
Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by BITSWORKS: 1:16pm On Apr 02, 2017 |
Reinforcement mat work on the backfilled foundation. We are using 10mm rebars and spacing at 300mm (1foot) CC.
|
Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by BITSWORKS: 5:51am On Apr 08, 2017 |
mufutau55: Thank you Hajji M. |
Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by BITSWORKS: 6:04am On Apr 08, 2017 |
Casting of the german floor after the reinforcement mat was completed. Manual mixing was used and it was completed in 2 days.
|
Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by BITSWORKS: 6:24am On Apr 08, 2017 |
More casting pictures of the oversite concrete (german floor).
|
Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by BITSWORKS: 12:17pm On Apr 09, 2017 |
Block setting in progress once the german floor was completed. We are using 9" and 6" blocks.
|
Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by BITSWORKS: 4:29pm On Apr 09, 2017 |
More block setting pictures.
|
Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by BITSWORKS: 6:15am On May 13, 2017 |
Lintel and columns work in progress.
|
Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by BITSWORKS: 6:27am On May 13, 2017 |
Carpentry formwork for the suspended slab (decking) ongoing.
|
Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by BITSWORKS: 6:42am On May 13, 2017 |
After completion of the decking platform, reinforcement work started.
|
Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by BITSWORKS: 6:55am On May 13, 2017 |
Reinforcement work almost complete, staircase formwork and labourer stairs for casting.
|
Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by TenPassfour(m): 7:22am On May 13, 2017 |
Goodjob |
Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by BITSWORKS: 7:50am On May 13, 2017 |
All set for casting of the suspended floor slab (decking) and we did the casting on Friday May 12th 2017.
|
Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by BITSWORKS: 9:04am On May 13, 2017 |
TenPassfour: Thank you. |
Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by BITSWORKS: 9:06am On May 13, 2017 |
More pictures of the suspended floor slab casting.
|
Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by BITSWORKS: 12:22pm On May 13, 2017 |
Suspended floor slab casting concluded.
|
Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by Nobody: 8:27am On May 16, 2017 |
Nice job.
|
Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by BITSWORKS: 8:12am On May 20, 2017 |
StainlessH: Thank you. BR |
Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by adewaleID: 8:24am On May 20, 2017 |
Look good, well done |
Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by wazobiaman: 8:32am On May 26, 2017 |
Buddy, can u give me a rough estimate of list of materials including no of planks to use for roofing of, L= 50ft B= 30ft I will really appreciate The roof style is Hip Roof |
Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by BITSWORKS: 7:30am On May 29, 2017 |
The decking has been left to cure for 14 days plus now and we will be starting the first floor block setting soon.
|
(1) (Reply)
Urgent Sale Of New Bedroom Detached Duplex At Lekki County Homes Estate For N70m / Uncompleted Duplex For Sale On Odili Road,portharcourt (with Picture) / 2,3 Bedroom Flat,terrace House For Sell @new Wiltop Estate Omitoro Ikorodu Lagos
(Go Up)
Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health religion celebs tv-movies music-radio literature webmasters programming techmarket Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 18 |