Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by Nobody: 1:18pm On Oct 23, 2017 |
Please kindly post the building plan. 2 Likes |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by saydfact(m): 1:18pm On Oct 23, 2017 |
Daboomb: I agree with you 100% but when u consider u're spending 8m on a building in Ilese - hmmm that been said, we brought the best quality WC for that type, we wld have changed the system inside if the client wanted to spend more.. |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by Daboomb: 1:21pm On Oct 23, 2017 |
saydfact: Too much cost savings, is not good in the long run. It is always, mostly "penny-wise, pound-foolish". I understand you are trying to manage cash-flow but there are BASIC thing sin building that you should not compromise! At least, get Concrete Pillars in the four corners of the building, (and maybe at some in-between Points. That wont kill you now? I like it that you did a german floor and did not try to save-save on that one too. Breaking walls for Pipes and Wiring (after erecting the building) really annoys me as l feel it weakens the whole structure. If you must do conduit then plan it from the onset 5 Likes 1 Share |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by Nwaoma198(f): 1:21pm On Oct 23, 2017 |
Weldone 2 Likes |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by japhethGold: 1:22pm On Oct 23, 2017 |
Great project. I will start mine next year in Jesus Name. Amen 6 Likes |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by Daboomb: 1:23pm On Oct 23, 2017 |
saydfact: Anyway, l am not here to criticize your work. I even thought it was your personal project. I am sure you will do better in the next project, having learned some lessons from this one. Once again, welldone. more grease to your elbow 3 Likes |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by gbolex(m): 1:24pm On Oct 23, 2017 |
I did a similar project, 10 rooms in total cost like 15m including cost of the land and other paper works. Cost of another 10 rooms foundation is inclusive. Find attached picture. Technically when you investing in such project, you need to confirm the cost of renting a self-contain hostel in that area. I doubt if the student there can pay 80K annually, i had to sell the land i bought there after completing 1st phase of this project. I will rather invest in TBills than building hostel for now. Its all about ROI, i dont think you need to use such expensive windows. Ileshe sch of health is not a high profile school (Sorry to say that but that is the truth). You really saved cost there, i made some mistakes while building mine but learnt my lesson. 6 Likes
|
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by Jonfort(m): 1:25pm On Oct 23, 2017 |
we d civil engineering student r so happy to c such post on this forum . thanks 2 Likes |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by haywire07(m): 1:26pm On Oct 23, 2017 |
Mrkumareze:I think Lintel only serves as a chain for the building when you choose to make it a perimeter beam. My only fear is, the entire length of the wall not having intermediate columns that would not only help give a break to the long wall but also help carry the roof load . I hope it's a stable land so cracks won't appear on the wall soonest 4 Likes |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by Bussydoll24(f): 1:27pm On Oct 23, 2017 |
We'll done.rejoice with those that merry. 3 Likes 1 Share |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by Daboomb: 1:30pm On Oct 23, 2017 |
saydfact: I love your sense of colour! The combination is really exquisite. BTW: Nigerians dont like to read at all or how come more than ten people keep asking the same question that has been asked and answered, over and over again? (How much did it cost to build this house?) 12 Likes 1 Share |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by madridguy(m): 1:31pm On Oct 23, 2017 |
This is a job well done. 2 Likes |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by haywire07(m): 1:32pm On Oct 23, 2017 |
Daboomb: It's even cheaper and safer when you carry out your plumbing works before laying blocks . 1 Like |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by oyoofong(m): 1:38pm On Oct 23, 2017 |
Great one there |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by Nobody: 1:38pm On Oct 23, 2017 |
I'm impressed with your level of expertise. I shall contact you soon for a house project. God bless you! |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by shakol91(m): 1:40pm On Oct 23, 2017 |
saydfact:my question is how did you carry those lintel bars up, if it was done manually,2 things must have been involved either the bars are too light or you employed at least 5 strong men to do that/used something else. 3 Likes |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by sonety2k(m): 1:42pm On Oct 23, 2017 |
gbolex: Pls which area area is your hostel located |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by gbolex(m): 1:45pm On Oct 23, 2017 |
Tai Solarin University of Education 1 Like |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by Mrkumareze(m): 1:54pm On Oct 23, 2017 |
toastedbread: The wall is quite high and from the foundation there is no chaining which works as a binder. therefore Cracking from the foundation can easily escalate to the last block but, if the lintel is allowed to go round the external blocks believe me it wouldn't be easy. And it's abnormal to have 10 coaches of blocks without chaining. 1 Like 1 Share |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by Mrkumareze(m): 1:57pm On Oct 23, 2017 |
haywire07: We 're saying almost the same thing. The structure is a down stair with shorter width so having intermediate columns at the foundation may be eliminated but lintel shouldn't. |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by sonety2k(m): 2:02pm On Oct 23, 2017 |
gbolex: Thanks and what's the annual rate per self contain 1 Like |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by toastedbread: 2:20pm On Oct 23, 2017 |
Mrkumareze: saydfact come in. no chaining which works as a binder and 10 coaches without a binder? |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by saydfact(m): 2:28pm On Oct 23, 2017 |
Daboomb: Firstly we didnt do conduit its all surface secondly pillars at the corners for what? - did u see the heavy rocks we dug out of that floor? even gravel sellers were asking me to see to them. lastly putting pillars where we have blocks on the terrace and beam - pls what function wld this serve? i just told you we didnt put any load on those blocks - THE COST SAVING I WAS REFERRING TO IS DROPPING THE UNNECESSARY AND FOCUSING ON THE NECESSARY.. If we didnt have any block on the terrace wld the building fall? NO - we only introduced it to separate the apartments - its has no other function, remove that singular function and its a waste of time and money. thanks for your sincere concern and advice.... maybe u shd check out my post on properties sections - I dont compromise quality 4 Likes |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by Mrjaz(m): 2:29pm On Oct 23, 2017 |
modelmike7: 8million naira for what na |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by Nobody: 2:30pm On Oct 23, 2017 |
Mrjaz:That question is for the Op I guess. |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by saydfact(m): 2:33pm On Oct 23, 2017 |
gbolex: @ Daboomb - Did u also notice the builder here also didnt introduce the beam you're talking about? experience on building shd tell one when and when not to introduce certain feature -ITS JUST A BUNGALOW, WHAT FUNCTION WLD THE BEAM BE SERVING? At Gbolex - i tell u, considering those pple cant pay much, i cant advice my client to do the secone phase ooh... 2 Likes |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by saydfact(m): 2:35pm On Oct 23, 2017 |
Daboomb: thanks and I LIKE YOUR SENSE OF HUMOR TOO... |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by saydfact(m): 2:37pm On Oct 23, 2017 |
shakol91: OMO - bricklayers are not office AC workers oh.. lol well, two bricklayers do the job and i dont pay for it..... and yes, its heave sha 1 Like |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by saydfact(m): 2:37pm On Oct 23, 2017 |
Pangolo123: Thanks sir, God bless u more 1 Like |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by Jamorezzi: 2:37pm On Oct 23, 2017 |
Seriously , I trip . Great job over there . 1 Like |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by saydfact(m): 2:40pm On Oct 23, 2017 |
Mrkumareze: SIR, THE SHOPRITE AT SANGOTEDO (after Ajah) WAS DONE BY THE COMPANY WHERE I'M EMPLOYED. ITS AS HIGH AS 30 COURSES OF BLOCK WITHOUT A BREAK (NO LINTEL - NO BEAM) I'll advice you read more on construction methods.... What if i decided to use wood or angle bars, you wld say the building done collapse already.. lol 2 Likes |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by saydfact(m): 2:42pm On Oct 23, 2017 |
toastedbread: see my reply above--- shoprite Sangotedo has about 30courses of blocks without lintel or beam between them.. ask me how we built it and it didnt collapse..but u wld pay for that info... lol lol lol |
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (Reply)
Sandra Duru's Landlord Throws Out Her Properties From Lagos Home (Photos) / Edo Landlord Burns Down His House Over Tenants’ Refusal To Pay Rent (Video) / The Port Harcourt Luxury Flats
(Go Up)
Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health religion celebs tv-movies music-radio literature webmasters programming techmarket Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 69 |