Bill Of Qantity For A 2- Unit 4 Bedroom Terrace by Monday5(m): 3:04pm On Jun 03, 2020
For those clients who would like to have an idea of what is going on on a building construction site. I tried as much as possible to touch up to 95 percent.
Specifically Port-harcourt/Abia Location as case study, it will still be useful for those in other parts of the country. Strip/Pad Foundation adopted.

whatsapp - 07055500111

Cost of Building 2 Unit Semi-detached 4 BedROOM Terrace
A. Cost of Foundation Stage -
A1) Material Requirements for Setting-out with profiles
Site clearance = NGN 20,000
Materials for setting out (pegs, nails and lines) = NGN 30,000
50 not 2X2 wood @ 220 = N110,000
Labour = 15,000
Estimated cost of setting-out = 175,000
A2) Material Requirements for Digging / Excavation
Labour (Digging of Strip not less than 3 feet) = N71,300
Labour (Digging for 35 nos of footing) @ 500 = N17,500
Estimated cost of digging = N88,800
A3) Material Requirements for Blinding and Concrete Strip Foundation/Column Footing work
250 bags of cement @ NGN 2,650 each = N662,500
60 tonnes of sand @15,000 per 10 Tons = N90,000
45 tonnes of Granite = N360,000
Labour for casting work = N200,000
Estimated cost of Blinding and Concrete Strip Foundation/Column Footing work = N1,312,500
A4) Material Requirements for Concrete Columns in foundation
150 bags of cement @ NGN 2,650 each = N397,500
40 tonnes of sand = N60,000
30 tonnes of granite = N240,000
½ Ton 12mm steel Reinforcements = N110,000
½ Tons 10mm Steel Reinforcements = N110,000
1 Ton 16 my steel Reinforcements = N220,000
Binding wire (25kg/roll) – N10,000
Labour for casting concrete – N120,000
Labour for Iron benders = N70,000
Estimated cost for Concrete Columns in foundation = N1,337,500
A5) Material requirements for Foundation Columns/DPC Formworks
50 nos length – 1″ x 12” long plank @ N1,200 each = N60,000
30 nos length – 2″ x 3" for bracing @ N450 each = N13,500
3 inches Nail – 1 bag = N7,000
4 inches nail - 1 bag = N7,000
Labour for fixing Formworks support – N40,000
Estimated cost of Foundation Columns/DPC Formworks = N127,500
A6) Material Requirements for Laying Foundation Blocks
40 bags of cement @ N 2,650 each = N106,000
30 tonnes of sand = N45,000
2000 pcs of 9-inch blocks @ NGN 220 each = N440,000
Labour for blockwork @ 60= N120,000
The estimated cost of laying foundation blocks = N711,000
A7) Material Requirements for Backfilling/Filling
10 Trips of 10 tyre truck filling Sand @ N15,000 per trip = N150,000
Labour for Filling @ N5000 Per trip = NGN 50,000
Labour for Back filling (lump sum) = N15,000
Estimated cost for Backfilling/Filling = N215,000
A8) Material Requirements for Ground Floor Slab (DPC)
150 bags of Cement @ NGN 2,650 each = NGN 540,600
60 Tons of Sand = NGN 90,000
45 tons Granite = NGN 360,000
Labour for casting NGN 120,000
7 Roll BRC Mesh Ref 142 (15m x 2.1m) @ 20,000 per roll = NGN 140,000
Iron Bender Labour =NGN 25,000
Estimated cost of Ground Floor Slab (DPC) = NGN 1,395,600
B. Cost of Construction From D.P.C To Parapet
B1) Material Requirements and Labour for Blockwork (Ground, First, and Second Floors)
18,000 pcs of 9-inch blocks @ NGN 220 = NGN 3,960,000
120 tons of sharp sand = NGN 180,000
300 bags of cement @ NGN 2,650 = NGN 495,000
Labour = NGN 1,080,000
Estimated cost of blockwork (Ground, First, and Second Floors) = N5,715,000.
B2) Material Requirements for Columns and lintels (Ground Floor)
80 bags of Cement @ NGN 2,650 per bag = NGN 212,000
30 tons Granite = NGN 240,000
60 tons sand = NGN90,000
Labour for casting Concrete = NGN 64,000.
214 nos length 1″ x 12″ (Plank) @ NGN 1,200 = NGN 256,800
3 bags Nail @ NGN 7,000 per bag = NGN 21,000
Labour for Carpenter on formwork = NGN 115,500
1 Tons 10mm Reinforcement = NGN 220,000
1 Tons 12mm Reinforcement = NGN 220,000
2 Tons 16mm Reinforcement @ = NGN 440,000
2 rolls of Binding Wire (25kg / roll) = NGN 20,000
Labour for Iron benders on reinforcement = NGN 140,850
Estimated cost of concrete columns for all floors = NGN 2,040,150.
B3) Cost of Decking/Stair Case Area (First Floor)
150 bags of Cement @ NGN 2,650 = NGN 397,500
60 tons Sharp sand @ = NGN 90,000
45 tons Granite = NGN 360,000
Labour for casting Concrete = NGN 52,000
250 nos length 1″ x 12″ (Plank) @ NGN 1,200 each = NGN 300,000
1000 nos length 2” x 3″@ NGN 450 each = NGN 450,000
400 nos length 2” x 2″@ NGN 350 each = NGN 140,000
200 pcs of Bamboo @ NGN 350 = NGN 70,000
3 bags Nail @ NGN 7,000 = NGN 21,000
Labour Carpenter on formwork = NGN 100,000
½ Tons 10mm Reinforcements = NGN 110,000
2 tons 12mm Reinforcements = NGN 480,000
½ Tons 16mm Reinforcementa = NGN 110,000
2 rolls Binding Wire (25kg / roll) @ NGN 10,000 each = NGN 20,000
Labour Iron benders on reinforcement = NGN 150,000
Estimated Cost for First Floor Decking/Stair Case Area = NGN 2,850,500
B4) Material Requirements for Columns and lintels (First Floor)
80 bags of Cement @ NGN 2,650 per bag = NGN 212,000
30 tons Granite = NGN 240,000
60 tons sand = NGN90,000
Labour for casting Concrete = NGN 64,000
214 nos length 1″ x 12″ (Plank) @ NGN 1,200 = NGN 256,800
3 bags Nail @ NGN 7,000 per bag = NGN 21,000
Labour for Carpenter on formwork = NGN 115,500
1 Tons 10mm Reinforcement = NGN 220,000
1 Tons 12mm Reinforcement = NGN 220,000
2 Tons 16mm Reinforcement @ = NGN 440,000
2 rolls of Binding Wire (25kg / roll) = NGN 20,000
Labour for Iron benders on reinforcement = NGN 140,850
Estimated cost of concrete columns for all floors = NGN 2,040,150.
B5) Cost of Decking/Stair Case Area (Second Floor)
150 bags of Cement @ NGN 2,650 = NGN 397,500
60 tons Sharp sand @ = NGN 90,000
45 tons Granite = NGN 360,000
Labour for casting Concrete = NGN 52,000
250 nos length 1″ x 12″ (Plank) @ NGN 1,200 each = NGN 300,000
1000 nos length 2” x 3″@ NGN 450 each = NGN 450,000
400 nos length 2” x 2″@ NGN 350 each = NGN 140,000
200 pcs of Bamboo @ NGN 350 = NGN 70,000
3 bags Nail @ NGN 7,000 = NGN 21,000
Labour Carpenter on formwork = NGN 100,000
½ Tons 10mm Reinforcements = NGN 110,000
2 tons 12mm Reinforcements = NGN 480,000
½ Tons 16mm Reinforcementa = NGN 110,000
2 rolls Binding Wire (25kg / roll) @ NGN 10,000 each = NGN 20,000
Labour Iron benders on reinforcement = NGN 150,000
Estimated Cost for Second Floor Decking/Stair Case Area = NGN 2,850,500.
B6) Material Requirements for Columns and lintels (Second Floor)
80 bags of Cement @ NGN 2,650 per bag = NGN 212,000
30 tons Granite = NGN 240,000
60 tons sand = NGN90,000
Labour for casting Concrete = NGN 64,000
214 nos length 1″ x 12″ (Plank) @ NGN 1,200 = NGN 256,800
3 bags Nail @ NGN 7,000 per bag = NGN 21,000
Labour for Carpenter on formwork = NGN 115,500
1 Tons 10mm Reinforcement = NGN 220,000
1 Tons 12mm Reinforcement = NGN 220,000
2 Tons 16mm Reinforcement @ = NGN 440,000
2 rolls of Binding Wire (25kg / roll) = NGN 20,000
Labour for Iron benders on reinforcement = NGN 140,850
Estimated cost of concrete columns for all floors = NGN 2,040,150
B7) Material requirements for Parapet
30 Tons of Granite = NGN 240,000
40 Tons of Sand = NGN 60,000
70 bags of cement @ NGN 2,650 = NGN 185,500
Casting Labour = NGN 70,000
1 Tons of 10mm Reinforcements = NGN 220,000
½ Tons of 12mm Reinforcements = NGN 110,000
Iron Bender Labour = NGN 100,000
300 pcs of 1X12 planks @ 1200 = NGN 360,000
Cost of Sawing planks to Shape = NGN 150,000
40 Sheets of plywood @ 4,000 = 160,000
300 lengths of bamboo for scaffold @ 350 = NGN 105,000
6 bags of nail @7,000 = NGN 42,000
Carpenter Labour = NGN 100,000
Scaffolding Labour = NGN 70,000
Estimated cost for Parapet = N1,972,500
C) Cost of Roofing
C1) Material Requirements for Roofing
800 length of 2 x 4 x 18 wood @ NGN 900= NGN 144,000
100 length of 4 x 4 x 12 @ NGN 850 = NGN 85,000
100 Lengths of 2 x 6 x 12 @ 850 = NGN 85,000
700 lengths of 2 x 2 x 12 for noggins @ 300 = N 210,000
8 bags of nails @ NGN 7,000= NGN 56,000
5 Gallons of wood treatment chemical @ 5,000 = NGN 25,000
60 liters of Kerosene @ 250 = NGN 15,000
Aluminium (0.45mm thick) roofing, transportation and Labour = NGN 1,000,000
Carpenter Labour = NGN 350,000
Total Estimated Cost for the roofing stage = NGN 1,970,000
D) Cost of Finishing Stage
D1) Material Requirements for Floor Tiling works (All Floors, Skirting and Stircase Area )
640 m² Floor and Skirting– 450 x450 floor tiles @ NGN 2,300/m² = NGN 1,472,000
200 m² Kitchen and Bathroom Wall — 450 X 300 wall tiles @ 1800 = NGN 360,000
300 bags of Cement for fixing tiles @ NGN 2,650 = NGN 795,000
80 Tons of Sand = NGN 120,000
Labour Tiling = NGN 672,000
Total Cost for Floor and Wall Tiles = NGN 3,419,000
D2) Material Requirements for Wall Plastering (All floors)
250 bags of Cement @ NGN 2,650 = NGN 662,500
80 tons of plaster sand @ NGN 15,000 per 10ton = NGN 120,000
80 tons of plaster gum sand @ NGN 15,000 per 10ton = NGN 120,000
Labour Scaffolding = NGN 70,000
Labour Plastering = NGN 750,000
Total Cost for wall Plastering work = NGN 1,722,500
D3) Material Requirements for Painting (All floors)
35 drums Dulux Emulsion/texcote paint (20Litres Drum) @ NGN 25,600= NGN 896,000
Labour for Painting = NGN 400,000
Total Cost for Painting Work = NGN 1,296,000
D4) Material Requirements for windows (Aluminium Casement)
12 nos 600 x 600 @ NGN 18,000 each = NGN 216,000
2 nos 1000x1000 @ NGN 25,000 each = NGN 50,000
27 nos 1500 x 1800 @ NGN 32,000 each = NGN 864,000
Total Cost for Window Work (Aluminium Casement) = NGN 1,130,000
D5) Materials Requirements for Doors
2 of 4ft Armoured Door (Exterior)- @N200,000 = N400,000
12 of 3ft Armoured Door (Exterior) - @ N160,000 = N1,920,000
16 of 3ft Stainless Steel Doors (Interior) - @ N100,000 = N1,600,000
12 of Bathroom PVC Doors @ N45,000 = N540,000
Total Cost for Doors and Installation = NGN 4,460,000
D6) Material Requirements for Plumbing work, Soak Away, and Labour (Lump sum)
= NGN 2,500,000
D7) Material Requirements for Electrical work and Labour (Lump sum)
= NGN 2,500,000
D8) Material Requirements for Ceiling POP Works (Lump sum)
= NGN 2,000,000
E) Engineer's Supervision Fee = NGN 2,000,000
Bill Summary
A. Cost of Foundation Stage - NGN 5,362,900
B. Cost of Construction From D.P.C To Parapet - NGN19,509,450
C) Cost of Roofing - NGN 1,970,000
D) Cost of Finishing Stage - NGN 19,027,500
E) Engineer's Supervision Fee NGN 2,000,000
Grand Total = NGN = 47,869,850

2 Likes

Re: Bill Of Qantity For A 2- Unit 4 Bedroom Terrace by Monday5(m): 3:34pm On Jun 03, 2020
I didn't want to post the actual 3D building this bill is meant for, but this picture is close to it.

It called client's confidentiality.

I hope you find it useful.
Re: Bill Of Qantity For A 2- Unit 4 Bedroom Terrace by Hum2020: 4:56pm On Jun 03, 2020
Op this is very interesting it give insight of what any builders should accept insider to achieve a good commercial home thanks for they time to put this here
Re: Bill Of Qantity For A 2- Unit 4 Bedroom Terrace by Monday5(m): 4:57pm On Jun 03, 2020
Monday5:
For those clients who would like to have an idea of what is going on on a building construction site. I tried as much as possible to touch up to 95 percent.
Specifically Port-harcourt/Abia Location as case study, it will still be useful for those in other parts of the country. Strip/Pad Foundation adopted.

whatsapp - 07055500111

Cost of Building 2 Unit Semi-detached 4 BedROOM Terrace
A. Cost of Foundation Stage -
A1) Material Requirements for Setting-out with profiles
Site clearance = NGN 20,000
Materials for setting out (pegs, nails and lines) = NGN 30,000
50 not 2X2 wood @ 220 = N110,000
Labour = 15,000
Estimated cost of setting-out = 175,000
A2) Material Requirements for Digging / Excavation
Labour (Digging of Strip not less than 3 feet) = N71,300
Labour (Digging for 35 nos of footing) @ 500 = N17,500
Estimated cost of digging = N88,800
A3) Material Requirements for Blinding and Concrete Strip Foundation/Column Footing work
250 bags of cement @ NGN 2,650 each = N662,500
60 tonnes of sand @15,000 per 10 Tons = N90,000
45 tonnes of Granite = N360,000
Labour for casting work = N200,000
Estimated cost of Blinding and Concrete Strip Foundation/Column Footing work = N1,312,500
A4) Material Requirements for Concrete Columns in foundation
150 bags of cement @ NGN 2,650 each = N397,500
40 tonnes of sand = N60,000
30 tonnes of granite = N240,000
½ Ton 12mm steel Reinforcements = N110,000
½ Tons 10mm Steel Reinforcements = N110,000
1 Ton 16 my steel Reinforcements = N220,000
Binding wire (25kg/roll) – N10,000
Labour for casting concrete – N120,000
Labour for Iron benders = N70,000
Estimated cost for Concrete Columns in foundation = N1,337,500
A5) Material requirements for Foundation Columns/DPC Formworks
50 nos length – 1″ x 12” long plank @ N1,200 each = N60,000
30 nos length – 2″ x 3" for bracing @ N450 each = N13,500
3 inches Nail – 1 bag = N7,000
4 inches nail - 1 bag = N7,000
Labour for fixing Formworks support – N40,000
Estimated cost of Foundation Columns/DPC Formworks = N127,500
A6) Material Requirements for Laying Foundation Blocks
40 bags of cement @ N 2,650 each = N106,000
30 tonnes of sand = N45,000
2000 pcs of 9-inch blocks @ NGN 220 each = N440,000
Labour for blockwork @ 60= N120,000
The estimated cost of laying foundation blocks = N711,000
A7) Material Requirements for Backfilling/Filling
10 Trips of 10 tyre truck filling Sand @ N15,000 per trip = N150,000
Labour for Filling @ N5000 Per trip = NGN 50,000
Labour for Back filling (lump sum) = N15,000
Estimated cost for Backfilling/Filling = N215,000
A8) Material Requirements for Ground Floor Slab (DPC)
150 bags of Cement @ NGN 2,650 each = NGN 540,600
60 Tons of Sand = NGN 90,000
45 tons Granite = NGN 360,000
Labour for casting NGN 120,000
7 Roll BRC Mesh Ref 142 (15m x 2.1m) @ 20,000 per roll = NGN 140,000
Iron Bender Labour =NGN 25,000
Estimated cost of Ground Floor Slab (DPC) = NGN 1,395,600
B. Cost of Construction From D.P.C To Parapet
B1) Material Requirements and Labour for Blockwork (Ground, First, and Second Floors)
18,000 pcs of 9-inch blocks @ NGN 220 = NGN 3,960,000
120 tons of sharp sand = NGN 180,000
300 bags of cement @ NGN 2,650 = NGN 495,000
Labour = NGN 1,080,000
Estimated cost of blockwork (Ground, First, and Second Floors) = N5,715,000.
B2) Material Requirements for Columns and lintels (Ground Floor)
80 bags of Cement @ NGN 2,650 per bag = NGN 212,000
30 tons Granite = NGN 240,000
60 tons sand = NGN90,000
Labour for casting Concrete = NGN 64,000.
214 nos length 1″ x 12″ (Plank) @ NGN 1,200 = NGN 256,800
3 bags Nail @ NGN 7,000 per bag = NGN 21,000
Labour for Carpenter on formwork = NGN 115,500
1 Tons 10mm Reinforcement = NGN 220,000
1 Tons 12mm Reinforcement = NGN 220,000
2 Tons 16mm Reinforcement @ = NGN 440,000
2 rolls of Binding Wire (25kg / roll) = NGN 20,000
Labour for Iron benders on reinforcement = NGN 140,850
Estimated cost of concrete columns for all floors = NGN 2,040,150.
B3) Cost of Decking/Stair Case Area (First Floor)
150 bags of Cement @ NGN 2,650 = NGN 397,500
60 tons Sharp sand @ = NGN 90,000
45 tons Granite = NGN 360,000
Labour for casting Concrete = NGN 52,000
250 nos length 1″ x 12″ (Plank) @ NGN 1,200 each = NGN 300,000
1000 nos length 2” x 3″@ NGN 450 each = NGN 450,000
400 nos length 2” x 2″@ NGN 350 each = NGN 140,000
200 pcs of Bamboo @ NGN 350 = NGN 70,000
3 bags Nail @ NGN 7,000 = NGN 21,000
Labour Carpenter on formwork = NGN 100,000
½ Tons 10mm Reinforcements = NGN 110,000
2 tons 12mm Reinforcements = NGN 480,000
½ Tons 16mm Reinforcementa = NGN 110,000
2 rolls Binding Wire (25kg / roll) @ NGN 10,000 each = NGN 20,000
Labour Iron benders on reinforcement = NGN 150,000
Estimated Cost for First Floor Decking/Stair Case Area = NGN 2,850,500
B4) Material Requirements for Columns and lintels (First Floor)
80 bags of Cement @ NGN 2,650 per bag = NGN 212,000
30 tons Granite = NGN 240,000
60 tons sand = NGN90,000
Labour for casting Concrete = NGN 64,000
214 nos length 1″ x 12″ (Plank) @ NGN 1,200 = NGN 256,800
3 bags Nail @ NGN 7,000 per bag = NGN 21,000
Labour for Carpenter on formwork = NGN 115,500
1 Tons 10mm Reinforcement = NGN 220,000
1 Tons 12mm Reinforcement = NGN 220,000
2 Tons 16mm Reinforcement @ = NGN 440,000
2 rolls of Binding Wire (25kg / roll) = NGN 20,000
Labour for Iron benders on reinforcement = NGN 140,850
Estimated cost of concrete columns for all floors = NGN 2,040,150.
B5) Cost of Decking/Stair Case Area (Second Floor)
150 bags of Cement @ NGN 2,650 = NGN 397,500
60 tons Sharp sand @ = NGN 90,000
45 tons Granite = NGN 360,000
Labour for casting Concrete = NGN 52,000
250 nos length 1″ x 12″ (Plank) @ NGN 1,200 each = NGN 300,000
1000 nos length 2” x 3″@ NGN 450 each = NGN 450,000
400 nos length 2” x 2″@ NGN 350 each = NGN 140,000
200 pcs of Bamboo @ NGN 350 = NGN 70,000
3 bags Nail @ NGN 7,000 = NGN 21,000
Labour Carpenter on formwork = NGN 100,000
½ Tons 10mm Reinforcements = NGN 110,000
2 tons 12mm Reinforcements = NGN 480,000
½ Tons 16mm Reinforcementa = NGN 110,000
2 rolls Binding Wire (25kg / roll) @ NGN 10,000 each = NGN 20,000
Labour Iron benders on reinforcement = NGN 150,000
Estimated Cost for Second Floor Decking/Stair Case Area = NGN 2,850,500.
B6) Material Requirements for Columns and lintels (Second Floor)
80 bags of Cement @ NGN 2,650 per bag = NGN 212,000
30 tons Granite = NGN 240,000
60 tons sand = NGN90,000
Labour for casting Concrete = NGN 64,000
214 nos length 1″ x 12″ (Plank) @ NGN 1,200 = NGN 256,800
3 bags Nail @ NGN 7,000 per bag = NGN 21,000
Labour for Carpenter on formwork = NGN 115,500
1 Tons 10mm Reinforcement = NGN 220,000
1 Tons 12mm Reinforcement = NGN 220,000
2 Tons 16mm Reinforcement @ = NGN 440,000
2 rolls of Binding Wire (25kg / roll) = NGN 20,000
Labour for Iron benders on reinforcement = NGN 140,850
Estimated cost of concrete columns for all floors = NGN 2,040,150
B7) Material requirements for Parapet
30 Tons of Granite = NGN 240,000
40 Tons of Sand = NGN 60,000
70 bags of cement @ NGN 2,650 = NGN 185,500
Casting Labour = NGN 70,000
1 Tons of 10mm Reinforcements = NGN 220,000
½ Tons of 12mm Reinforcements = NGN 110,000
Iron Bender Labour = NGN 100,000
300 pcs of 1X12 planks @ 1200 = NGN 360,000
Cost of Sawing planks to Shape = NGN 150,000
40 Sheets of plywood @ 4,000 = 160,000
300 lengths of bamboo for scaffold @ 350 = NGN 105,000
6 bags of nail @7,000 = NGN 42,000
Carpenter Labour = NGN 100,000
Scaffolding Labour = NGN 70,000
Estimated cost for Parapet = N1,972,500
C) Cost of Roofing
C1) Material Requirements for Roofing
800 length of 2 x 4 x 18 wood @ NGN 900= NGN 144,000
100 length of 4 x 4 x 12 @ NGN 850 = NGN 85,000
100 Lengths of 2 x 6 x 12 @ 850 = NGN 85,000
700 lengths of 2 x 2 x 12 for noggins @ 300 = N 210,000
8 bags of nails @ NGN 7,000= NGN 56,000
5 Gallons of wood treatment chemical @ 5,000 = NGN 25,000
60 liters of Kerosene @ 250 = NGN 15,000
Aluminium (0.45mm thick) roofing, transportation and Labour = NGN 1,000,000
Carpenter Labour = NGN 350,000
Total Estimated Cost for the roofing stage = NGN 1,970,000
D) Cost of Finishing Stage
D1) Material Requirements for Floor Tiling works (All Floors, Skirting and Stircase Area )
640 m² Floor and Skirting– 450 x450 floor tiles @ NGN 2,300/m² = NGN 1,472,000
200 m² Kitchen and Bathroom Wall — 450 X 300 wall tiles @ 1800 = NGN 360,000
300 bags of Cement for fixing tiles @ NGN 2,650 = NGN 795,000
80 Tons of Sand = NGN 120,000
Labour Tiling = NGN 672,000
Total Cost for Floor and Wall Tiles = NGN 3,419,000
D2) Material Requirements for Wall Plastering (All floors)
250 bags of Cement @ NGN 2,650 = NGN 662,500
80 tons of plaster sand @ NGN 15,000 per 10ton = NGN 120,000
80 tons of plaster gum sand @ NGN 15,000 per 10ton = NGN 120,000
Labour Scaffolding = NGN 70,000
Labour Plastering = NGN 750,000
Total Cost for wall Plastering work = NGN 1,722,500
D3) Material Requirements for Painting (All floors)
35 drums Dulux Emulsion/texcote paint (20Litres Drum) @ NGN 25,600= NGN 896,000
Labour for Painting = NGN 400,000
Total Cost for Painting Work = NGN 1,296,000
D4) Material Requirements for windows (Aluminium Casement)
12 nos 600 x 600 @ NGN 18,000 each = NGN 216,000
2 nos 1000x1000 @ NGN 25,000 each = NGN 50,000
27 nos 1500 x 1800 @ NGN 32,000 each = NGN 864,000
Total Cost for Window Work (Aluminium Casement) = NGN 1,130,000
D5) Materials Requirements for Doors
2 of 4ft Armoured Door (Exterior)- @N200,000 = N400,000
12 of 3ft Armoured Door (Exterior) - @ N160,000 = N1,920,000
16 of 3ft Stainless Steel Doors (Interior) - @ N100,000 = N1,600,000
12 of Bathroom PVC Doors @ N45,000 = N540,000
Total Cost for Doors and Installation = NGN 4,460,000
D6) Material Requirements for Plumbing work, Soak Away, and Labour (Lump sum)
= NGN 2,500,000
D7) Material Requirements for Electrical work and Labour (Lump sum)
= NGN 2,500,000
D8) Material Requirements for Ceiling POP Works (Lump sum)
= NGN 2,000,000
E) Engineer's Supervision Fee = NGN 2,000,000
Bill Summary
A. Cost of Foundation Stage - NGN 5,362,900
B. Cost of Construction From D.P.C To Parapet - NGN19,509,450
C) Cost of Roofing - NGN 1,970,000
D) Cost of Finishing Stage - NGN 19,027,500
E) Engineer's Supervision Fee NGN 2,000,000
Grand Total = NGN = 47,869,850

1 Like

Re: Bill Of Qantity For A 2- Unit 4 Bedroom Terrace by Gabrokpara001(m): 8:51pm On Jun 03, 2020
Monday5:
For those clients who would like to have an idea of what is going on on a building construction site. I tried as much as possible to touch up to 95 percent.
Specifically Port-harcourt/Abia Location as case study, it will still be useful for those in other parts of the country. Strip/Pad Foundation adopted.

whatsapp - 07055500111

Cost of Building 2 Unit Semi-detached 4 BedROOM Terrace
A. Cost of Foundation Stage -
A1) Material Requirements for Setting-out with profiles
Site clearance = NGN 20,000
Materials for setting out (pegs, nails and lines) = NGN 30,000
50 not 2X2 wood @ 220 = N110,000
Labour = 15,000
Estimated cost of setting-out = 175,000
A2) Material Requirements for Digging / Excavation
Labour (Digging of Strip not less than 3 feet) = N71,300
Labour (Digging for 35 nos of footing) @ 500 = N17,500
Estimated cost of digging = N88,800
A3) Material Requirements for Blinding and Concrete Strip Foundation/Column Footing work
250 bags of cement @ NGN 2,650 each = N662,500
60 tonnes of sand @15,000 per 10 Tons = N90,000
45 tonnes of Granite = N360,000
Labour for casting work = N200,000
Estimated cost of Blinding and Concrete Strip Foundation/Column Footing work = N1,312,500
A4) Material Requirements for Concrete Columns in foundation
150 bags of cement @ NGN 2,650 each = N397,500
40 tonnes of sand = N60,000
30 tonnes of granite = N240,000
½ Ton 12mm steel Reinforcements = N110,000
½ Tons 10mm Steel Reinforcements = N110,000
1 Ton 16 my steel Reinforcements = N220,000
Binding wire (25kg/roll) – N10,000
Labour for casting concrete – N120,000
Labour for Iron benders = N70,000
Estimated cost for Concrete Columns in foundation = N1,337,500
A5) Material requirements for Foundation Columns/DPC Formworks
50 nos length – 1″ x 12” long plank @ N1,200 each = N60,000
30 nos length – 2″ x 3" for bracing @ N450 each = N13,500
3 inches Nail – 1 bag = N7,000
4 inches nail - 1 bag = N7,000
Labour for fixing Formworks support – N40,000
Estimated cost of Foundation Columns/DPC Formworks = N127,500
A6) Material Requirements for Laying Foundation Blocks
40 bags of cement @ N 2,650 each = N106,000
30 tonnes of sand = N45,000
2000 pcs of 9-inch blocks @ NGN 220 each = N440,000
Labour for blockwork @ 60= N120,000
The estimated cost of laying foundation blocks = N711,000
A7) Material Requirements for Backfilling/Filling
10 Trips of 10 tyre truck filling Sand @ N15,000 per trip = N150,000
Labour for Filling @ N5000 Per trip = NGN 50,000
Labour for Back filling (lump sum) = N15,000
Estimated cost for Backfilling/Filling = N215,000
A8) Material Requirements for Ground Floor Slab (DPC)
150 bags of Cement @ NGN 2,650 each = NGN 540,600
60 Tons of Sand = NGN 90,000
45 tons Granite = NGN 360,000
Labour for casting NGN 120,000
7 Roll BRC Mesh Ref 142 (15m x 2.1m) @ 20,000 per roll = NGN 140,000
Iron Bender Labour =NGN 25,000
Estimated cost of Ground Floor Slab (DPC) = NGN 1,395,600
B. Cost of Construction From D.P.C To Parapet
B1) Material Requirements and Labour for Blockwork (Ground, First, and Second Floors)
18,000 pcs of 9-inch blocks @ NGN 220 = NGN 3,960,000
120 tons of sharp sand = NGN 180,000
300 bags of cement @ NGN 2,650 = NGN 495,000
Labour = NGN 1,080,000
Estimated cost of blockwork (Ground, First, and Second Floors) = N5,715,000.
B2) Material Requirements for Columns and lintels (Ground Floor)
80 bags of Cement @ NGN 2,650 per bag = NGN 212,000
30 tons Granite = NGN 240,000
60 tons sand = NGN90,000
Labour for casting Concrete = NGN 64,000.
214 nos length 1″ x 12″ (Plank) @ NGN 1,200 = NGN 256,800
3 bags Nail @ NGN 7,000 per bag = NGN 21,000
Labour for Carpenter on formwork = NGN 115,500
1 Tons 10mm Reinforcement = NGN 220,000
1 Tons 12mm Reinforcement = NGN 220,000
2 Tons 16mm Reinforcement @ = NGN 440,000
2 rolls of Binding Wire (25kg / roll) = NGN 20,000
Labour for Iron benders on reinforcement = NGN 140,850
Estimated cost of concrete columns for all floors = NGN 2,040,150.
B3) Cost of Decking/Stair Case Area (First Floor)
150 bags of Cement @ NGN 2,650 = NGN 397,500
60 tons Sharp sand @ = NGN 90,000
45 tons Granite = NGN 360,000
Labour for casting Concrete = NGN 52,000
250 nos length 1″ x 12″ (Plank) @ NGN 1,200 each = NGN 300,000
1000 nos length 2” x 3″@ NGN 450 each = NGN 450,000
400 nos length 2” x 2″@ NGN 350 each = NGN 140,000
200 pcs of Bamboo @ NGN 350 = NGN 70,000
3 bags Nail @ NGN 7,000 = NGN 21,000
Labour Carpenter on formwork = NGN 100,000
½ Tons 10mm Reinforcements = NGN 110,000
2 tons 12mm Reinforcements = NGN 480,000
½ Tons 16mm Reinforcementa = NGN 110,000
2 rolls Binding Wire (25kg / roll) @ NGN 10,000 each = NGN 20,000
Labour Iron benders on reinforcement = NGN 150,000
Estimated Cost for First Floor Decking/Stair Case Area = NGN 2,850,500
B4) Material Requirements for Columns and lintels (First Floor)
80 bags of Cement @ NGN 2,650 per bag = NGN 212,000
30 tons Granite = NGN 240,000
60 tons sand = NGN90,000
Labour for casting Concrete = NGN 64,000
214 nos length 1″ x 12″ (Plank) @ NGN 1,200 = NGN 256,800
3 bags Nail @ NGN 7,000 per bag = NGN 21,000
Labour for Carpenter on formwork = NGN 115,500
1 Tons 10mm Reinforcement = NGN 220,000
1 Tons 12mm Reinforcement = NGN 220,000
2 Tons 16mm Reinforcement @ = NGN 440,000
2 rolls of Binding Wire (25kg / roll) = NGN 20,000
Labour for Iron benders on reinforcement = NGN 140,850
Estimated cost of concrete columns for all floors = NGN 2,040,150.
B5) Cost of Decking/Stair Case Area (Second Floor)
150 bags of Cement @ NGN 2,650 = NGN 397,500
60 tons Sharp sand @ = NGN 90,000
45 tons Granite = NGN 360,000
Labour for casting Concrete = NGN 52,000
250 nos length 1″ x 12″ (Plank) @ NGN 1,200 each = NGN 300,000
1000 nos length 2” x 3″@ NGN 450 each = NGN 450,000
400 nos length 2” x 2″@ NGN 350 each = NGN 140,000
200 pcs of Bamboo @ NGN 350 = NGN 70,000
3 bags Nail @ NGN 7,000 = NGN 21,000
Labour Carpenter on formwork = NGN 100,000
½ Tons 10mm Reinforcements = NGN 110,000
2 tons 12mm Reinforcements = NGN 480,000
½ Tons 16mm Reinforcementa = NGN 110,000
2 rolls Binding Wire (25kg / roll) @ NGN 10,000 each = NGN 20,000
Labour Iron benders on reinforcement = NGN 150,000
Estimated Cost for Second Floor Decking/Stair Case Area = NGN 2,850,500.
B6) Material Requirements for Columns and lintels (Second Floor)
80 bags of Cement @ NGN 2,650 per bag = NGN 212,000
30 tons Granite = NGN 240,000
60 tons sand = NGN90,000
Labour for casting Concrete = NGN 64,000
214 nos length 1″ x 12″ (Plank) @ NGN 1,200 = NGN 256,800
3 bags Nail @ NGN 7,000 per bag = NGN 21,000
Labour for Carpenter on formwork = NGN 115,500
1 Tons 10mm Reinforcement = NGN 220,000
1 Tons 12mm Reinforcement = NGN 220,000
2 Tons 16mm Reinforcement @ = NGN 440,000
2 rolls of Binding Wire (25kg / roll) = NGN 20,000
Labour for Iron benders on reinforcement = NGN 140,850
Estimated cost of concrete columns for all floors = NGN 2,040,150
B7) Material requirements for Parapet
30 Tons of Granite = NGN 240,000
40 Tons of Sand = NGN 60,000
70 bags of cement @ NGN 2,650 = NGN 185,500
Casting Labour = NGN 70,000
1 Tons of 10mm Reinforcements = NGN 220,000
½ Tons of 12mm Reinforcements = NGN 110,000
Iron Bender Labour = NGN 100,000
300 pcs of 1X12 planks @ 1200 = NGN 360,000
Cost of Sawing planks to Shape = NGN 150,000
40 Sheets of plywood @ 4,000 = 160,000
300 lengths of bamboo for scaffold @ 350 = NGN 105,000
6 bags of nail @7,000 = NGN 42,000
Carpenter Labour = NGN 100,000
Scaffolding Labour = NGN 70,000
Estimated cost for Parapet = N1,972,500
C) Cost of Roofing
C1) Material Requirements for Roofing
800 length of 2 x 4 x 18 wood @ NGN 900= NGN 144,000
100 length of 4 x 4 x 12 @ NGN 850 = NGN 85,000
100 Lengths of 2 x 6 x 12 @ 850 = NGN 85,000
700 lengths of 2 x 2 x 12 for noggins @ 300 = N 210,000
8 bags of nails @ NGN 7,000= NGN 56,000
5 Gallons of wood treatment chemical @ 5,000 = NGN 25,000
60 liters of Kerosene @ 250 = NGN 15,000
Aluminium (0.45mm thick) roofing, transportation and Labour = NGN 1,000,000
Carpenter Labour = NGN 350,000
Total Estimated Cost for the roofing stage = NGN 1,970,000
D) Cost of Finishing Stage
D1) Material Requirements for Floor Tiling works (All Floors, Skirting and Stircase Area )
640 m² Floor and Skirting– 450 x450 floor tiles @ NGN 2,300/m² = NGN 1,472,000
200 m² Kitchen and Bathroom Wall — 450 X 300 wall tiles @ 1800 = NGN 360,000
300 bags of Cement for fixing tiles @ NGN 2,650 = NGN 795,000
80 Tons of Sand = NGN 120,000
Labour Tiling = NGN 672,000
Total Cost for Floor and Wall Tiles = NGN 3,419,000
D2) Material Requirements for Wall Plastering (All floors)
250 bags of Cement @ NGN 2,650 = NGN 662,500
80 tons of plaster sand @ NGN 15,000 per 10ton = NGN 120,000
80 tons of plaster gum sand @ NGN 15,000 per 10ton = NGN 120,000
Labour Scaffolding = NGN 70,000
Labour Plastering = NGN 750,000
Total Cost for wall Plastering work = NGN 1,722,500
D3) Material Requirements for Painting (All floors)
35 drums Dulux Emulsion/texcote paint (20Litres Drum) @ NGN 25,600= NGN 896,000
Labour for Painting = NGN 400,000
Total Cost for Painting Work = NGN 1,296,000
D4) Material Requirements for windows (Aluminium Casement)
12 nos 600 x 600 @ NGN 18,000 each = NGN 216,000
2 nos 1000x1000 @ NGN 25,000 each = NGN 50,000
27 nos 1500 x 1800 @ NGN 32,000 each = NGN 864,000
Total Cost for Window Work (Aluminium Casement) = NGN 1,130,000
D5) Materials Requirements for Doors
2 of 4ft Armoured Door (Exterior)- @N200,000 = N400,000
12 of 3ft Armoured Door (Exterior) - @ N160,000 = N1,920,000
16 of 3ft Stainless Steel Doors (Interior) - @ N100,000 = N1,600,000
12 of Bathroom PVC Doors @ N45,000 = N540,000
Total Cost for Doors and Installation = NGN 4,460,000
D6) Material Requirements for Plumbing work, Soak Away, and Labour (Lump sum)
= NGN 2,500,000
D7) Material Requirements for Electrical work and Labour (Lump sum)
= NGN 2,500,000
D8) Material Requirements for Ceiling POP Works (Lump sum)
= NGN 2,000,000
E) Engineer's Supervision Fee = NGN 2,000,000
Bill Summary
A. Cost of Foundation Stage - NGN 5,362,900
B. Cost of Construction From D.P.C To Parapet - NGN19,509,450
C) Cost of Roofing - NGN 1,970,000
D) Cost of Finishing Stage - NGN 19,027,500
E) Engineer's Supervision Fee NGN 2,000,000
Grand Total = NGN = 47,869,850


Lovely breakdown of cost... but please this is not a BILL OF QUANTITIES so please don't call it one, it may not mean much to you but you re belittling the professional work of a Quantity surveyor by calling a normal quotation a Bill of Quantities. Again nice work

2 Likes 1 Share

Re: Bill Of Qantity For A 2- Unit 4 Bedroom Terrace by Monday5(m): 9:28pm On Jun 03, 2020
Gabrokpara001:



Lovely breakdown of cost... but please this is not a BILL OF QUANTITIES so please don't call it one, it may not mean much to you but you re belittling the professional work of a Quantity surveyor by calling a normal quotation a Bill of Quantities. Again nice work

It's meant for people outside the field bro. I sent professional one like that to a client sometimes ago, my man no understand that one oo..
Re: Bill Of Qantity For A 2- Unit 4 Bedroom Terrace by Gabrokpara001(m): 9:34pm On Jun 03, 2020
Monday5:


It's meant for people outside the field bro. I sent professional one like that to a client sometimes ago, my man no understand that one oo..


Chief please whether its for people in the field or not dont call a quotation a bill of quantity, you are unintentionally doing a great harm to the quantity surveying profession that is lack of respect to the profession...there exist a clear difference between both it is now left to you as the pro to explain to your client.
Lets learn to respect other professionals in the built industry
Re: Bill Of Qantity For A 2- Unit 4 Bedroom Terrace by Badgers14: 6:08am On Jul 08, 2020
[quote author=Monday5 post=90273570][/quote]

Good breakdown..
Re: Bill Of Qantity For A 2- Unit 4 Bedroom Terrace by RealBadBoy: 4:51pm On Aug 30, 2020
Monday5:
For those clients who would like to have an idea of what is going on on a building construction site. I tried as much as possible to touch up to 95 percent.

Please can I know the prices for pvc and upvc pipes?

(1) (Reply)

No More Excuses!!!! GRACIAS PEARL ESTATE ,ise Town,ibeju-lekki / Solar 4G CCTV PTZ Solar Camera For Cheaper Price.. / Estate Agents In Limehouse: How To Find A Good Real Estate Agent?

(Go Up)

Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health
religion celebs tv-movies music-radio literature webmasters programming techmarket

Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 92
Disclaimer: Every Nairaland member is solely responsible for anything that he/she posts or uploads on Nairaland.