Bill Of Qantity For A 2- Unit 4 Bedroom Terrace by Monday5(m): 3:04pm On Jun 03, 2020 |
For those clients who would like to have an idea of what is going on on a building construction site. I tried as much as possible to touch up to 95 percent. Specifically Port-harcourt/Abia Location as case study, it will still be useful for those in other parts of the country. Strip/Pad Foundation adopted.
whatsapp - 07055500111
Cost of Building 2 Unit Semi-detached 4 BedROOM Terrace A. Cost of Foundation Stage - A1) Material Requirements for Setting-out with profiles Site clearance = NGN 20,000 Materials for setting out (pegs, nails and lines) = NGN 30,000 50 not 2X2 wood @ 220 = N110,000 Labour = 15,000 Estimated cost of setting-out = 175,000 A2) Material Requirements for Digging / Excavation Labour (Digging of Strip not less than 3 feet) = N71,300 Labour (Digging for 35 nos of footing) @ 500 = N17,500 Estimated cost of digging = N88,800 A3) Material Requirements for Blinding and Concrete Strip Foundation/Column Footing work 250 bags of cement @ NGN 2,650 each = N662,500 60 tonnes of sand @15,000 per 10 Tons = N90,000 45 tonnes of Granite = N360,000 Labour for casting work = N200,000 Estimated cost of Blinding and Concrete Strip Foundation/Column Footing work = N1,312,500 A4) Material Requirements for Concrete Columns in foundation 150 bags of cement @ NGN 2,650 each = N397,500 40 tonnes of sand = N60,000 30 tonnes of granite = N240,000 ½ Ton 12mm steel Reinforcements = N110,000 ½ Tons 10mm Steel Reinforcements = N110,000 1 Ton 16 my steel Reinforcements = N220,000 Binding wire (25kg/roll) – N10,000 Labour for casting concrete – N120,000 Labour for Iron benders = N70,000 Estimated cost for Concrete Columns in foundation = N1,337,500 A5) Material requirements for Foundation Columns/DPC Formworks 50 nos length – 1″ x 12” long plank @ N1,200 each = N60,000 30 nos length – 2″ x 3" for bracing @ N450 each = N13,500 3 inches Nail – 1 bag = N7,000 4 inches nail - 1 bag = N7,000 Labour for fixing Formworks support – N40,000 Estimated cost of Foundation Columns/DPC Formworks = N127,500 A6) Material Requirements for Laying Foundation Blocks 40 bags of cement @ N 2,650 each = N106,000 30 tonnes of sand = N45,000 2000 pcs of 9-inch blocks @ NGN 220 each = N440,000 Labour for blockwork @ 60= N120,000 The estimated cost of laying foundation blocks = N711,000 A7) Material Requirements for Backfilling/Filling 10 Trips of 10 tyre truck filling Sand @ N15,000 per trip = N150,000 Labour for Filling @ N5000 Per trip = NGN 50,000 Labour for Back filling (lump sum) = N15,000 Estimated cost for Backfilling/Filling = N215,000 A8) Material Requirements for Ground Floor Slab (DPC) 150 bags of Cement @ NGN 2,650 each = NGN 540,600 60 Tons of Sand = NGN 90,000 45 tons Granite = NGN 360,000 Labour for casting NGN 120,000 7 Roll BRC Mesh Ref 142 (15m x 2.1m) @ 20,000 per roll = NGN 140,000 Iron Bender Labour =NGN 25,000 Estimated cost of Ground Floor Slab (DPC) = NGN 1,395,600 B. Cost of Construction From D.P.C To Parapet B1) Material Requirements and Labour for Blockwork (Ground, First, and Second Floors) 18,000 pcs of 9-inch blocks @ NGN 220 = NGN 3,960,000 120 tons of sharp sand = NGN 180,000 300 bags of cement @ NGN 2,650 = NGN 495,000 Labour = NGN 1,080,000 Estimated cost of blockwork (Ground, First, and Second Floors) = N5,715,000. B2) Material Requirements for Columns and lintels (Ground Floor) 80 bags of Cement @ NGN 2,650 per bag = NGN 212,000 30 tons Granite = NGN 240,000 60 tons sand = NGN90,000 Labour for casting Concrete = NGN 64,000. 214 nos length 1″ x 12″ (Plank) @ NGN 1,200 = NGN 256,800 3 bags Nail @ NGN 7,000 per bag = NGN 21,000 Labour for Carpenter on formwork = NGN 115,500 1 Tons 10mm Reinforcement = NGN 220,000 1 Tons 12mm Reinforcement = NGN 220,000 2 Tons 16mm Reinforcement @ = NGN 440,000 2 rolls of Binding Wire (25kg / roll) = NGN 20,000 Labour for Iron benders on reinforcement = NGN 140,850 Estimated cost of concrete columns for all floors = NGN 2,040,150. B3) Cost of Decking/Stair Case Area (First Floor) 150 bags of Cement @ NGN 2,650 = NGN 397,500 60 tons Sharp sand @ = NGN 90,000 45 tons Granite = NGN 360,000 Labour for casting Concrete = NGN 52,000 250 nos length 1″ x 12″ (Plank) @ NGN 1,200 each = NGN 300,000 1000 nos length 2” x 3″@ NGN 450 each = NGN 450,000 400 nos length 2” x 2″@ NGN 350 each = NGN 140,000 200 pcs of Bamboo @ NGN 350 = NGN 70,000 3 bags Nail @ NGN 7,000 = NGN 21,000 Labour Carpenter on formwork = NGN 100,000 ½ Tons 10mm Reinforcements = NGN 110,000 2 tons 12mm Reinforcements = NGN 480,000 ½ Tons 16mm Reinforcementa = NGN 110,000 2 rolls Binding Wire (25kg / roll) @ NGN 10,000 each = NGN 20,000 Labour Iron benders on reinforcement = NGN 150,000 Estimated Cost for First Floor Decking/Stair Case Area = NGN 2,850,500 B4) Material Requirements for Columns and lintels (First Floor) 80 bags of Cement @ NGN 2,650 per bag = NGN 212,000 30 tons Granite = NGN 240,000 60 tons sand = NGN90,000 Labour for casting Concrete = NGN 64,000 214 nos length 1″ x 12″ (Plank) @ NGN 1,200 = NGN 256,800 3 bags Nail @ NGN 7,000 per bag = NGN 21,000 Labour for Carpenter on formwork = NGN 115,500 1 Tons 10mm Reinforcement = NGN 220,000 1 Tons 12mm Reinforcement = NGN 220,000 2 Tons 16mm Reinforcement @ = NGN 440,000 2 rolls of Binding Wire (25kg / roll) = NGN 20,000 Labour for Iron benders on reinforcement = NGN 140,850 Estimated cost of concrete columns for all floors = NGN 2,040,150. B5) Cost of Decking/Stair Case Area (Second Floor) 150 bags of Cement @ NGN 2,650 = NGN 397,500 60 tons Sharp sand @ = NGN 90,000 45 tons Granite = NGN 360,000 Labour for casting Concrete = NGN 52,000 250 nos length 1″ x 12″ (Plank) @ NGN 1,200 each = NGN 300,000 1000 nos length 2” x 3″@ NGN 450 each = NGN 450,000 400 nos length 2” x 2″@ NGN 350 each = NGN 140,000 200 pcs of Bamboo @ NGN 350 = NGN 70,000 3 bags Nail @ NGN 7,000 = NGN 21,000 Labour Carpenter on formwork = NGN 100,000 ½ Tons 10mm Reinforcements = NGN 110,000 2 tons 12mm Reinforcements = NGN 480,000 ½ Tons 16mm Reinforcementa = NGN 110,000 2 rolls Binding Wire (25kg / roll) @ NGN 10,000 each = NGN 20,000 Labour Iron benders on reinforcement = NGN 150,000 Estimated Cost for Second Floor Decking/Stair Case Area = NGN 2,850,500. B6) Material Requirements for Columns and lintels (Second Floor) 80 bags of Cement @ NGN 2,650 per bag = NGN 212,000 30 tons Granite = NGN 240,000 60 tons sand = NGN90,000 Labour for casting Concrete = NGN 64,000 214 nos length 1″ x 12″ (Plank) @ NGN 1,200 = NGN 256,800 3 bags Nail @ NGN 7,000 per bag = NGN 21,000 Labour for Carpenter on formwork = NGN 115,500 1 Tons 10mm Reinforcement = NGN 220,000 1 Tons 12mm Reinforcement = NGN 220,000 2 Tons 16mm Reinforcement @ = NGN 440,000 2 rolls of Binding Wire (25kg / roll) = NGN 20,000 Labour for Iron benders on reinforcement = NGN 140,850 Estimated cost of concrete columns for all floors = NGN 2,040,150 B7) Material requirements for Parapet 30 Tons of Granite = NGN 240,000 40 Tons of Sand = NGN 60,000 70 bags of cement @ NGN 2,650 = NGN 185,500 Casting Labour = NGN 70,000 1 Tons of 10mm Reinforcements = NGN 220,000 ½ Tons of 12mm Reinforcements = NGN 110,000 Iron Bender Labour = NGN 100,000 300 pcs of 1X12 planks @ 1200 = NGN 360,000 Cost of Sawing planks to Shape = NGN 150,000 40 Sheets of plywood @ 4,000 = 160,000 300 lengths of bamboo for scaffold @ 350 = NGN 105,000 6 bags of nail @7,000 = NGN 42,000 Carpenter Labour = NGN 100,000 Scaffolding Labour = NGN 70,000 Estimated cost for Parapet = N1,972,500 C) Cost of Roofing C1) Material Requirements for Roofing 800 length of 2 x 4 x 18 wood @ NGN 900= NGN 144,000 100 length of 4 x 4 x 12 @ NGN 850 = NGN 85,000 100 Lengths of 2 x 6 x 12 @ 850 = NGN 85,000 700 lengths of 2 x 2 x 12 for noggins @ 300 = N 210,000 8 bags of nails @ NGN 7,000= NGN 56,000 5 Gallons of wood treatment chemical @ 5,000 = NGN 25,000 60 liters of Kerosene @ 250 = NGN 15,000 Aluminium (0.45mm thick) roofing, transportation and Labour = NGN 1,000,000 Carpenter Labour = NGN 350,000 Total Estimated Cost for the roofing stage = NGN 1,970,000 D) Cost of Finishing Stage D1) Material Requirements for Floor Tiling works (All Floors, Skirting and Stircase Area ) 640 m² Floor and Skirting– 450 x450 floor tiles @ NGN 2,300/m² = NGN 1,472,000 200 m² Kitchen and Bathroom Wall — 450 X 300 wall tiles @ 1800 = NGN 360,000 300 bags of Cement for fixing tiles @ NGN 2,650 = NGN 795,000 80 Tons of Sand = NGN 120,000 Labour Tiling = NGN 672,000 Total Cost for Floor and Wall Tiles = NGN 3,419,000 D2) Material Requirements for Wall Plastering (All floors) 250 bags of Cement @ NGN 2,650 = NGN 662,500 80 tons of plaster sand @ NGN 15,000 per 10ton = NGN 120,000 80 tons of plaster gum sand @ NGN 15,000 per 10ton = NGN 120,000 Labour Scaffolding = NGN 70,000 Labour Plastering = NGN 750,000 Total Cost for wall Plastering work = NGN 1,722,500 D3) Material Requirements for Painting (All floors) 35 drums Dulux Emulsion/texcote paint (20Litres Drum) @ NGN 25,600= NGN 896,000 Labour for Painting = NGN 400,000 Total Cost for Painting Work = NGN 1,296,000 D4) Material Requirements for windows (Aluminium Casement) 12 nos 600 x 600 @ NGN 18,000 each = NGN 216,000 2 nos 1000x1000 @ NGN 25,000 each = NGN 50,000 27 nos 1500 x 1800 @ NGN 32,000 each = NGN 864,000 Total Cost for Window Work (Aluminium Casement) = NGN 1,130,000 D5) Materials Requirements for Doors 2 of 4ft Armoured Door (Exterior)- @N200,000 = N400,000 12 of 3ft Armoured Door (Exterior) - @ N160,000 = N1,920,000 16 of 3ft Stainless Steel Doors (Interior) - @ N100,000 = N1,600,000 12 of Bathroom PVC Doors @ N45,000 = N540,000 Total Cost for Doors and Installation = NGN 4,460,000 D6) Material Requirements for Plumbing work, Soak Away, and Labour (Lump sum) = NGN 2,500,000 D7) Material Requirements for Electrical work and Labour (Lump sum) = NGN 2,500,000 D8) Material Requirements for Ceiling POP Works (Lump sum) = NGN 2,000,000 E) Engineer's Supervision Fee = NGN 2,000,000 Bill Summary A. Cost of Foundation Stage - NGN 5,362,900 B. Cost of Construction From D.P.C To Parapet - NGN19,509,450 C) Cost of Roofing - NGN 1,970,000 D) Cost of Finishing Stage - NGN 19,027,500 E) Engineer's Supervision Fee NGN 2,000,000 Grand Total = NGN = 47,869,850 2 Likes |
Re: Bill Of Qantity For A 2- Unit 4 Bedroom Terrace by Monday5(m): 3:34pm On Jun 03, 2020 |
I didn't want to post the actual 3D building this bill is meant for, but this picture is close to it.
It called client's confidentiality.
I hope you find it useful. |
Re: Bill Of Qantity For A 2- Unit 4 Bedroom Terrace by Hum2020: 4:56pm On Jun 03, 2020 |
Op this is very interesting it give insight of what any builders should accept insider to achieve a good commercial home thanks for they time to put this here |
Re: Bill Of Qantity For A 2- Unit 4 Bedroom Terrace by Monday5(m): 4:57pm On Jun 03, 2020 |
Monday5: For those clients who would like to have an idea of what is going on on a building construction site. I tried as much as possible to touch up to 95 percent. Specifically Port-harcourt/Abia Location as case study, it will still be useful for those in other parts of the country. Strip/Pad Foundation adopted.
whatsapp - 07055500111
Cost of Building 2 Unit Semi-detached 4 BedROOM Terrace A. Cost of Foundation Stage - A1) Material Requirements for Setting-out with profiles Site clearance = NGN 20,000 Materials for setting out (pegs, nails and lines) = NGN 30,000 50 not 2X2 wood @ 220 = N110,000 Labour = 15,000 Estimated cost of setting-out = 175,000 A2) Material Requirements for Digging / Excavation Labour (Digging of Strip not less than 3 feet) = N71,300 Labour (Digging for 35 nos of footing) @ 500 = N17,500 Estimated cost of digging = N88,800 A3) Material Requirements for Blinding and Concrete Strip Foundation/Column Footing work 250 bags of cement @ NGN 2,650 each = N662,500 60 tonnes of sand @15,000 per 10 Tons = N90,000 45 tonnes of Granite = N360,000 Labour for casting work = N200,000 Estimated cost of Blinding and Concrete Strip Foundation/Column Footing work = N1,312,500 A4) Material Requirements for Concrete Columns in foundation 150 bags of cement @ NGN 2,650 each = N397,500 40 tonnes of sand = N60,000 30 tonnes of granite = N240,000 ½ Ton 12mm steel Reinforcements = N110,000 ½ Tons 10mm Steel Reinforcements = N110,000 1 Ton 16 my steel Reinforcements = N220,000 Binding wire (25kg/roll) – N10,000 Labour for casting concrete – N120,000 Labour for Iron benders = N70,000 Estimated cost for Concrete Columns in foundation = N1,337,500 A5) Material requirements for Foundation Columns/DPC Formworks 50 nos length – 1″ x 12” long plank @ N1,200 each = N60,000 30 nos length – 2″ x 3" for bracing @ N450 each = N13,500 3 inches Nail – 1 bag = N7,000 4 inches nail - 1 bag = N7,000 Labour for fixing Formworks support – N40,000 Estimated cost of Foundation Columns/DPC Formworks = N127,500 A6) Material Requirements for Laying Foundation Blocks 40 bags of cement @ N 2,650 each = N106,000 30 tonnes of sand = N45,000 2000 pcs of 9-inch blocks @ NGN 220 each = N440,000 Labour for blockwork @ 60= N120,000 The estimated cost of laying foundation blocks = N711,000 A7) Material Requirements for Backfilling/Filling 10 Trips of 10 tyre truck filling Sand @ N15,000 per trip = N150,000 Labour for Filling @ N5000 Per trip = NGN 50,000 Labour for Back filling (lump sum) = N15,000 Estimated cost for Backfilling/Filling = N215,000 A8) Material Requirements for Ground Floor Slab (DPC) 150 bags of Cement @ NGN 2,650 each = NGN 540,600 60 Tons of Sand = NGN 90,000 45 tons Granite = NGN 360,000 Labour for casting NGN 120,000 7 Roll BRC Mesh Ref 142 (15m x 2.1m) @ 20,000 per roll = NGN 140,000 Iron Bender Labour =NGN 25,000 Estimated cost of Ground Floor Slab (DPC) = NGN 1,395,600 B. Cost of Construction From D.P.C To Parapet B1) Material Requirements and Labour for Blockwork (Ground, First, and Second Floors) 18,000 pcs of 9-inch blocks @ NGN 220 = NGN 3,960,000 120 tons of sharp sand = NGN 180,000 300 bags of cement @ NGN 2,650 = NGN 495,000 Labour = NGN 1,080,000 Estimated cost of blockwork (Ground, First, and Second Floors) = N5,715,000. B2) Material Requirements for Columns and lintels (Ground Floor) 80 bags of Cement @ NGN 2,650 per bag = NGN 212,000 30 tons Granite = NGN 240,000 60 tons sand = NGN90,000 Labour for casting Concrete = NGN 64,000. 214 nos length 1″ x 12″ (Plank) @ NGN 1,200 = NGN 256,800 3 bags Nail @ NGN 7,000 per bag = NGN 21,000 Labour for Carpenter on formwork = NGN 115,500 1 Tons 10mm Reinforcement = NGN 220,000 1 Tons 12mm Reinforcement = NGN 220,000 2 Tons 16mm Reinforcement @ = NGN 440,000 2 rolls of Binding Wire (25kg / roll) = NGN 20,000 Labour for Iron benders on reinforcement = NGN 140,850 Estimated cost of concrete columns for all floors = NGN 2,040,150. B3) Cost of Decking/Stair Case Area (First Floor) 150 bags of Cement @ NGN 2,650 = NGN 397,500 60 tons Sharp sand @ = NGN 90,000 45 tons Granite = NGN 360,000 Labour for casting Concrete = NGN 52,000 250 nos length 1″ x 12″ (Plank) @ NGN 1,200 each = NGN 300,000 1000 nos length 2” x 3″@ NGN 450 each = NGN 450,000 400 nos length 2” x 2″@ NGN 350 each = NGN 140,000 200 pcs of Bamboo @ NGN 350 = NGN 70,000 3 bags Nail @ NGN 7,000 = NGN 21,000 Labour Carpenter on formwork = NGN 100,000 ½ Tons 10mm Reinforcements = NGN 110,000 2 tons 12mm Reinforcements = NGN 480,000 ½ Tons 16mm Reinforcementa = NGN 110,000 2 rolls Binding Wire (25kg / roll) @ NGN 10,000 each = NGN 20,000 Labour Iron benders on reinforcement = NGN 150,000 Estimated Cost for First Floor Decking/Stair Case Area = NGN 2,850,500 B4) Material Requirements for Columns and lintels (First Floor) 80 bags of Cement @ NGN 2,650 per bag = NGN 212,000 30 tons Granite = NGN 240,000 60 tons sand = NGN90,000 Labour for casting Concrete = NGN 64,000 214 nos length 1″ x 12″ (Plank) @ NGN 1,200 = NGN 256,800 3 bags Nail @ NGN 7,000 per bag = NGN 21,000 Labour for Carpenter on formwork = NGN 115,500 1 Tons 10mm Reinforcement = NGN 220,000 1 Tons 12mm Reinforcement = NGN 220,000 2 Tons 16mm Reinforcement @ = NGN 440,000 2 rolls of Binding Wire (25kg / roll) = NGN 20,000 Labour for Iron benders on reinforcement = NGN 140,850 Estimated cost of concrete columns for all floors = NGN 2,040,150. B5) Cost of Decking/Stair Case Area (Second Floor) 150 bags of Cement @ NGN 2,650 = NGN 397,500 60 tons Sharp sand @ = NGN 90,000 45 tons Granite = NGN 360,000 Labour for casting Concrete = NGN 52,000 250 nos length 1″ x 12″ (Plank) @ NGN 1,200 each = NGN 300,000 1000 nos length 2” x 3″@ NGN 450 each = NGN 450,000 400 nos length 2” x 2″@ NGN 350 each = NGN 140,000 200 pcs of Bamboo @ NGN 350 = NGN 70,000 3 bags Nail @ NGN 7,000 = NGN 21,000 Labour Carpenter on formwork = NGN 100,000 ½ Tons 10mm Reinforcements = NGN 110,000 2 tons 12mm Reinforcements = NGN 480,000 ½ Tons 16mm Reinforcementa = NGN 110,000 2 rolls Binding Wire (25kg / roll) @ NGN 10,000 each = NGN 20,000 Labour Iron benders on reinforcement = NGN 150,000 Estimated Cost for Second Floor Decking/Stair Case Area = NGN 2,850,500. B6) Material Requirements for Columns and lintels (Second Floor) 80 bags of Cement @ NGN 2,650 per bag = NGN 212,000 30 tons Granite = NGN 240,000 60 tons sand = NGN90,000 Labour for casting Concrete = NGN 64,000 214 nos length 1″ x 12″ (Plank) @ NGN 1,200 = NGN 256,800 3 bags Nail @ NGN 7,000 per bag = NGN 21,000 Labour for Carpenter on formwork = NGN 115,500 1 Tons 10mm Reinforcement = NGN 220,000 1 Tons 12mm Reinforcement = NGN 220,000 2 Tons 16mm Reinforcement @ = NGN 440,000 2 rolls of Binding Wire (25kg / roll) = NGN 20,000 Labour for Iron benders on reinforcement = NGN 140,850 Estimated cost of concrete columns for all floors = NGN 2,040,150 B7) Material requirements for Parapet 30 Tons of Granite = NGN 240,000 40 Tons of Sand = NGN 60,000 70 bags of cement @ NGN 2,650 = NGN 185,500 Casting Labour = NGN 70,000 1 Tons of 10mm Reinforcements = NGN 220,000 ½ Tons of 12mm Reinforcements = NGN 110,000 Iron Bender Labour = NGN 100,000 300 pcs of 1X12 planks @ 1200 = NGN 360,000 Cost of Sawing planks to Shape = NGN 150,000 40 Sheets of plywood @ 4,000 = 160,000 300 lengths of bamboo for scaffold @ 350 = NGN 105,000 6 bags of nail @7,000 = NGN 42,000 Carpenter Labour = NGN 100,000 Scaffolding Labour = NGN 70,000 Estimated cost for Parapet = N1,972,500 C) Cost of Roofing C1) Material Requirements for Roofing 800 length of 2 x 4 x 18 wood @ NGN 900= NGN 144,000 100 length of 4 x 4 x 12 @ NGN 850 = NGN 85,000 100 Lengths of 2 x 6 x 12 @ 850 = NGN 85,000 700 lengths of 2 x 2 x 12 for noggins @ 300 = N 210,000 8 bags of nails @ NGN 7,000= NGN 56,000 5 Gallons of wood treatment chemical @ 5,000 = NGN 25,000 60 liters of Kerosene @ 250 = NGN 15,000 Aluminium (0.45mm thick) roofing, transportation and Labour = NGN 1,000,000 Carpenter Labour = NGN 350,000 Total Estimated Cost for the roofing stage = NGN 1,970,000 D) Cost of Finishing Stage D1) Material Requirements for Floor Tiling works (All Floors, Skirting and Stircase Area ) 640 m² Floor and Skirting– 450 x450 floor tiles @ NGN 2,300/m² = NGN 1,472,000 200 m² Kitchen and Bathroom Wall — 450 X 300 wall tiles @ 1800 = NGN 360,000 300 bags of Cement for fixing tiles @ NGN 2,650 = NGN 795,000 80 Tons of Sand = NGN 120,000 Labour Tiling = NGN 672,000 Total Cost for Floor and Wall Tiles = NGN 3,419,000 D2) Material Requirements for Wall Plastering (All floors) 250 bags of Cement @ NGN 2,650 = NGN 662,500 80 tons of plaster sand @ NGN 15,000 per 10ton = NGN 120,000 80 tons of plaster gum sand @ NGN 15,000 per 10ton = NGN 120,000 Labour Scaffolding = NGN 70,000 Labour Plastering = NGN 750,000 Total Cost for wall Plastering work = NGN 1,722,500 D3) Material Requirements for Painting (All floors) 35 drums Dulux Emulsion/texcote paint (20Litres Drum) @ NGN 25,600= NGN 896,000 Labour for Painting = NGN 400,000 Total Cost for Painting Work = NGN 1,296,000 D4) Material Requirements for windows (Aluminium Casement) 12 nos 600 x 600 @ NGN 18,000 each = NGN 216,000 2 nos 1000x1000 @ NGN 25,000 each = NGN 50,000 27 nos 1500 x 1800 @ NGN 32,000 each = NGN 864,000 Total Cost for Window Work (Aluminium Casement) = NGN 1,130,000 D5) Materials Requirements for Doors 2 of 4ft Armoured Door (Exterior)- @N200,000 = N400,000 12 of 3ft Armoured Door (Exterior) - @ N160,000 = N1,920,000 16 of 3ft Stainless Steel Doors (Interior) - @ N100,000 = N1,600,000 12 of Bathroom PVC Doors @ N45,000 = N540,000 Total Cost for Doors and Installation = NGN 4,460,000 D6) Material Requirements for Plumbing work, Soak Away, and Labour (Lump sum) = NGN 2,500,000 D7) Material Requirements for Electrical work and Labour (Lump sum) = NGN 2,500,000 D8) Material Requirements for Ceiling POP Works (Lump sum) = NGN 2,000,000 E) Engineer's Supervision Fee = NGN 2,000,000 Bill Summary A. Cost of Foundation Stage - NGN 5,362,900 B. Cost of Construction From D.P.C To Parapet - NGN19,509,450 C) Cost of Roofing - NGN 1,970,000 D) Cost of Finishing Stage - NGN 19,027,500 E) Engineer's Supervision Fee NGN 2,000,000 Grand Total = NGN = 47,869,850 1 Like |
Re: Bill Of Qantity For A 2- Unit 4 Bedroom Terrace by Gabrokpara001(m): 8:51pm On Jun 03, 2020 |
Monday5: For those clients who would like to have an idea of what is going on on a building construction site. I tried as much as possible to touch up to 95 percent. Specifically Port-harcourt/Abia Location as case study, it will still be useful for those in other parts of the country. Strip/Pad Foundation adopted.
whatsapp - 07055500111
Cost of Building 2 Unit Semi-detached 4 BedROOM Terrace A. Cost of Foundation Stage - A1) Material Requirements for Setting-out with profiles Site clearance = NGN 20,000 Materials for setting out (pegs, nails and lines) = NGN 30,000 50 not 2X2 wood @ 220 = N110,000 Labour = 15,000 Estimated cost of setting-out = 175,000 A2) Material Requirements for Digging / Excavation Labour (Digging of Strip not less than 3 feet) = N71,300 Labour (Digging for 35 nos of footing) @ 500 = N17,500 Estimated cost of digging = N88,800 A3) Material Requirements for Blinding and Concrete Strip Foundation/Column Footing work 250 bags of cement @ NGN 2,650 each = N662,500 60 tonnes of sand @15,000 per 10 Tons = N90,000 45 tonnes of Granite = N360,000 Labour for casting work = N200,000 Estimated cost of Blinding and Concrete Strip Foundation/Column Footing work = N1,312,500 A4) Material Requirements for Concrete Columns in foundation 150 bags of cement @ NGN 2,650 each = N397,500 40 tonnes of sand = N60,000 30 tonnes of granite = N240,000 ½ Ton 12mm steel Reinforcements = N110,000 ½ Tons 10mm Steel Reinforcements = N110,000 1 Ton 16 my steel Reinforcements = N220,000 Binding wire (25kg/roll) – N10,000 Labour for casting concrete – N120,000 Labour for Iron benders = N70,000 Estimated cost for Concrete Columns in foundation = N1,337,500 A5) Material requirements for Foundation Columns/DPC Formworks 50 nos length – 1″ x 12” long plank @ N1,200 each = N60,000 30 nos length – 2″ x 3" for bracing @ N450 each = N13,500 3 inches Nail – 1 bag = N7,000 4 inches nail - 1 bag = N7,000 Labour for fixing Formworks support – N40,000 Estimated cost of Foundation Columns/DPC Formworks = N127,500 A6) Material Requirements for Laying Foundation Blocks 40 bags of cement @ N 2,650 each = N106,000 30 tonnes of sand = N45,000 2000 pcs of 9-inch blocks @ NGN 220 each = N440,000 Labour for blockwork @ 60= N120,000 The estimated cost of laying foundation blocks = N711,000 A7) Material Requirements for Backfilling/Filling 10 Trips of 10 tyre truck filling Sand @ N15,000 per trip = N150,000 Labour for Filling @ N5000 Per trip = NGN 50,000 Labour for Back filling (lump sum) = N15,000 Estimated cost for Backfilling/Filling = N215,000 A8) Material Requirements for Ground Floor Slab (DPC) 150 bags of Cement @ NGN 2,650 each = NGN 540,600 60 Tons of Sand = NGN 90,000 45 tons Granite = NGN 360,000 Labour for casting NGN 120,000 7 Roll BRC Mesh Ref 142 (15m x 2.1m) @ 20,000 per roll = NGN 140,000 Iron Bender Labour =NGN 25,000 Estimated cost of Ground Floor Slab (DPC) = NGN 1,395,600 B. Cost of Construction From D.P.C To Parapet B1) Material Requirements and Labour for Blockwork (Ground, First, and Second Floors) 18,000 pcs of 9-inch blocks @ NGN 220 = NGN 3,960,000 120 tons of sharp sand = NGN 180,000 300 bags of cement @ NGN 2,650 = NGN 495,000 Labour = NGN 1,080,000 Estimated cost of blockwork (Ground, First, and Second Floors) = N5,715,000. B2) Material Requirements for Columns and lintels (Ground Floor) 80 bags of Cement @ NGN 2,650 per bag = NGN 212,000 30 tons Granite = NGN 240,000 60 tons sand = NGN90,000 Labour for casting Concrete = NGN 64,000. 214 nos length 1″ x 12″ (Plank) @ NGN 1,200 = NGN 256,800 3 bags Nail @ NGN 7,000 per bag = NGN 21,000 Labour for Carpenter on formwork = NGN 115,500 1 Tons 10mm Reinforcement = NGN 220,000 1 Tons 12mm Reinforcement = NGN 220,000 2 Tons 16mm Reinforcement @ = NGN 440,000 2 rolls of Binding Wire (25kg / roll) = NGN 20,000 Labour for Iron benders on reinforcement = NGN 140,850 Estimated cost of concrete columns for all floors = NGN 2,040,150. B3) Cost of Decking/Stair Case Area (First Floor) 150 bags of Cement @ NGN 2,650 = NGN 397,500 60 tons Sharp sand @ = NGN 90,000 45 tons Granite = NGN 360,000 Labour for casting Concrete = NGN 52,000 250 nos length 1″ x 12″ (Plank) @ NGN 1,200 each = NGN 300,000 1000 nos length 2” x 3″@ NGN 450 each = NGN 450,000 400 nos length 2” x 2″@ NGN 350 each = NGN 140,000 200 pcs of Bamboo @ NGN 350 = NGN 70,000 3 bags Nail @ NGN 7,000 = NGN 21,000 Labour Carpenter on formwork = NGN 100,000 ½ Tons 10mm Reinforcements = NGN 110,000 2 tons 12mm Reinforcements = NGN 480,000 ½ Tons 16mm Reinforcementa = NGN 110,000 2 rolls Binding Wire (25kg / roll) @ NGN 10,000 each = NGN 20,000 Labour Iron benders on reinforcement = NGN 150,000 Estimated Cost for First Floor Decking/Stair Case Area = NGN 2,850,500 B4) Material Requirements for Columns and lintels (First Floor) 80 bags of Cement @ NGN 2,650 per bag = NGN 212,000 30 tons Granite = NGN 240,000 60 tons sand = NGN90,000 Labour for casting Concrete = NGN 64,000 214 nos length 1″ x 12″ (Plank) @ NGN 1,200 = NGN 256,800 3 bags Nail @ NGN 7,000 per bag = NGN 21,000 Labour for Carpenter on formwork = NGN 115,500 1 Tons 10mm Reinforcement = NGN 220,000 1 Tons 12mm Reinforcement = NGN 220,000 2 Tons 16mm Reinforcement @ = NGN 440,000 2 rolls of Binding Wire (25kg / roll) = NGN 20,000 Labour for Iron benders on reinforcement = NGN 140,850 Estimated cost of concrete columns for all floors = NGN 2,040,150. B5) Cost of Decking/Stair Case Area (Second Floor) 150 bags of Cement @ NGN 2,650 = NGN 397,500 60 tons Sharp sand @ = NGN 90,000 45 tons Granite = NGN 360,000 Labour for casting Concrete = NGN 52,000 250 nos length 1″ x 12″ (Plank) @ NGN 1,200 each = NGN 300,000 1000 nos length 2” x 3″@ NGN 450 each = NGN 450,000 400 nos length 2” x 2″@ NGN 350 each = NGN 140,000 200 pcs of Bamboo @ NGN 350 = NGN 70,000 3 bags Nail @ NGN 7,000 = NGN 21,000 Labour Carpenter on formwork = NGN 100,000 ½ Tons 10mm Reinforcements = NGN 110,000 2 tons 12mm Reinforcements = NGN 480,000 ½ Tons 16mm Reinforcementa = NGN 110,000 2 rolls Binding Wire (25kg / roll) @ NGN 10,000 each = NGN 20,000 Labour Iron benders on reinforcement = NGN 150,000 Estimated Cost for Second Floor Decking/Stair Case Area = NGN 2,850,500. B6) Material Requirements for Columns and lintels (Second Floor) 80 bags of Cement @ NGN 2,650 per bag = NGN 212,000 30 tons Granite = NGN 240,000 60 tons sand = NGN90,000 Labour for casting Concrete = NGN 64,000 214 nos length 1″ x 12″ (Plank) @ NGN 1,200 = NGN 256,800 3 bags Nail @ NGN 7,000 per bag = NGN 21,000 Labour for Carpenter on formwork = NGN 115,500 1 Tons 10mm Reinforcement = NGN 220,000 1 Tons 12mm Reinforcement = NGN 220,000 2 Tons 16mm Reinforcement @ = NGN 440,000 2 rolls of Binding Wire (25kg / roll) = NGN 20,000 Labour for Iron benders on reinforcement = NGN 140,850 Estimated cost of concrete columns for all floors = NGN 2,040,150 B7) Material requirements for Parapet 30 Tons of Granite = NGN 240,000 40 Tons of Sand = NGN 60,000 70 bags of cement @ NGN 2,650 = NGN 185,500 Casting Labour = NGN 70,000 1 Tons of 10mm Reinforcements = NGN 220,000 ½ Tons of 12mm Reinforcements = NGN 110,000 Iron Bender Labour = NGN 100,000 300 pcs of 1X12 planks @ 1200 = NGN 360,000 Cost of Sawing planks to Shape = NGN 150,000 40 Sheets of plywood @ 4,000 = 160,000 300 lengths of bamboo for scaffold @ 350 = NGN 105,000 6 bags of nail @7,000 = NGN 42,000 Carpenter Labour = NGN 100,000 Scaffolding Labour = NGN 70,000 Estimated cost for Parapet = N1,972,500 C) Cost of Roofing C1) Material Requirements for Roofing 800 length of 2 x 4 x 18 wood @ NGN 900= NGN 144,000 100 length of 4 x 4 x 12 @ NGN 850 = NGN 85,000 100 Lengths of 2 x 6 x 12 @ 850 = NGN 85,000 700 lengths of 2 x 2 x 12 for noggins @ 300 = N 210,000 8 bags of nails @ NGN 7,000= NGN 56,000 5 Gallons of wood treatment chemical @ 5,000 = NGN 25,000 60 liters of Kerosene @ 250 = NGN 15,000 Aluminium (0.45mm thick) roofing, transportation and Labour = NGN 1,000,000 Carpenter Labour = NGN 350,000 Total Estimated Cost for the roofing stage = NGN 1,970,000 D) Cost of Finishing Stage D1) Material Requirements for Floor Tiling works (All Floors, Skirting and Stircase Area ) 640 m² Floor and Skirting– 450 x450 floor tiles @ NGN 2,300/m² = NGN 1,472,000 200 m² Kitchen and Bathroom Wall — 450 X 300 wall tiles @ 1800 = NGN 360,000 300 bags of Cement for fixing tiles @ NGN 2,650 = NGN 795,000 80 Tons of Sand = NGN 120,000 Labour Tiling = NGN 672,000 Total Cost for Floor and Wall Tiles = NGN 3,419,000 D2) Material Requirements for Wall Plastering (All floors) 250 bags of Cement @ NGN 2,650 = NGN 662,500 80 tons of plaster sand @ NGN 15,000 per 10ton = NGN 120,000 80 tons of plaster gum sand @ NGN 15,000 per 10ton = NGN 120,000 Labour Scaffolding = NGN 70,000 Labour Plastering = NGN 750,000 Total Cost for wall Plastering work = NGN 1,722,500 D3) Material Requirements for Painting (All floors) 35 drums Dulux Emulsion/texcote paint (20Litres Drum) @ NGN 25,600= NGN 896,000 Labour for Painting = NGN 400,000 Total Cost for Painting Work = NGN 1,296,000 D4) Material Requirements for windows (Aluminium Casement) 12 nos 600 x 600 @ NGN 18,000 each = NGN 216,000 2 nos 1000x1000 @ NGN 25,000 each = NGN 50,000 27 nos 1500 x 1800 @ NGN 32,000 each = NGN 864,000 Total Cost for Window Work (Aluminium Casement) = NGN 1,130,000 D5) Materials Requirements for Doors 2 of 4ft Armoured Door (Exterior)- @N200,000 = N400,000 12 of 3ft Armoured Door (Exterior) - @ N160,000 = N1,920,000 16 of 3ft Stainless Steel Doors (Interior) - @ N100,000 = N1,600,000 12 of Bathroom PVC Doors @ N45,000 = N540,000 Total Cost for Doors and Installation = NGN 4,460,000 D6) Material Requirements for Plumbing work, Soak Away, and Labour (Lump sum) = NGN 2,500,000 D7) Material Requirements for Electrical work and Labour (Lump sum) = NGN 2,500,000 D8) Material Requirements for Ceiling POP Works (Lump sum) = NGN 2,000,000 E) Engineer's Supervision Fee = NGN 2,000,000 Bill Summary A. Cost of Foundation Stage - NGN 5,362,900 B. Cost of Construction From D.P.C To Parapet - NGN19,509,450 C) Cost of Roofing - NGN 1,970,000 D) Cost of Finishing Stage - NGN 19,027,500 E) Engineer's Supervision Fee NGN 2,000,000 Grand Total = NGN = 47,869,850 Lovely breakdown of cost... but please this is not a BILL OF QUANTITIES so please don't call it one, it may not mean much to you but you re belittling the professional work of a Quantity surveyor by calling a normal quotation a Bill of Quantities. Again nice work 2 Likes 1 Share |
Re: Bill Of Qantity For A 2- Unit 4 Bedroom Terrace by Monday5(m): 9:28pm On Jun 03, 2020 |
Gabrokpara001:
Lovely breakdown of cost... but please this is not a BILL OF QUANTITIES so please don't call it one, it may not mean much to you but you re belittling the professional work of a Quantity surveyor by calling a normal quotation a Bill of Quantities. Again nice work It's meant for people outside the field bro. I sent professional one like that to a client sometimes ago, my man no understand that one oo.. |
Re: Bill Of Qantity For A 2- Unit 4 Bedroom Terrace by Gabrokpara001(m): 9:34pm On Jun 03, 2020 |
Monday5:
It's meant for people outside the field bro. I sent professional one like that to a client sometimes ago, my man no understand that one oo..
Chief please whether its for people in the field or not dont call a quotation a bill of quantity, you are unintentionally doing a great harm to the quantity surveying profession that is lack of respect to the profession...there exist a clear difference between both it is now left to you as the pro to explain to your client. Lets learn to respect other professionals in the built industry |
Re: Bill Of Qantity For A 2- Unit 4 Bedroom Terrace by Badgers14: 6:08am On Jul 08, 2020 |
[quote author=Monday5 post=90273570][/quote]
Good breakdown.. |
Re: Bill Of Qantity For A 2- Unit 4 Bedroom Terrace by RealBadBoy: 4:51pm On Aug 30, 2020 |
Monday5: For those clients who would like to have an idea of what is going on on a building construction site. I tried as much as possible to touch up to 95 percent.
Please can I know the prices for pvc and upvc pipes? |