A Dairy Of My 1st Building Project by edshaf: 10:30pm On Sep 09, 2012
This thread is to keep a record of the progress of my first building project.

4&5-Sep-12: I was told about a land in Ejigbo, Lagos. A single plot going for 5.5million in an area where land goes for nothing less than 7million. Sceptical, I went to sight the property.
It was a standard plot which existed as part of 2 plots and fenced as such. The owner is a business man that lives at Otta.
There is no title on the land and all the owner has is a receipt from the 'Omo-onile' and a survey plan of the two plots.
The survey has two stamps on it: "Plan falls within Govt. Acquisition/Revocation" and "Surveyed with the consent of the Surveyor General". The whole area, I later gathered suffer the same fate. However, upon checking at Alausa, I was made to understand that the land has not been committed and ratified.

I had no experience with respect to purchasing land. None at all! But my instinct says go ahead.

6-Sep-12: Contacted my lawyer and he asked the agent for the receipt on the land, the name of the family that sold the land, what motive is there for selling etc. He needed the info to draft the Deed of Assignment. Agent promised to get back in 2 days (working) with the necessary info. My intention is to perfect the documents on the land asap.
'Les I forget, the agent mentioned that I will have to pay homage to the 'King' of Ejigbo with @least N500k personally. So, effectively, the land cost 6m. smiley

8-Sep-12: Contacted my architect to check out the site in view of constructing a duplex with two 3 bedroom flats extension behind. The duplex will have 3 bedroom on the upper floor and a family living room too. On the lower floor, the main lounge, the reception, the dinning area, kitchen, maid room, study and the visitor's room. Awaiting the sketch. Awaiting the draft sketch.

To be continued...

5 Likes 3 Shares

Re: A Dairy Of My 1st Building Project by edshaf: 3:19pm On Jul 03, 2013
I am sorry for not updating this thread... It totally skipped my mind.
The land is acquired, red copy of survey ready and CofO is pretty much in progress, but kinda delayed due to some expected Lagos State bureaucracy!
I started with work on the land anyways... I needed to - though I know I will get fined for constructing before getting building approval sad

OK... I will have to rush through the progress so far... The pictures are not the best of qualities unfortunately but here we go...

Re: A Dairy Of My 1st Building Project by edshaf: 4:09pm On Jul 03, 2013
The foundation was a bit expensive. 3 layers of blocks from the foundation bedding to the surface then the casting. Another 3 layers of blocks from the surface plus another casting.
The foundation needed to be high because there is a potential for the road to be raised above the current level of the compound and the last thing we want is water flowing into the compound from the street! In truth, I was only going by the advice of my neighbors.

Well, the foundation was a bit above budget though, costing a whooping =N=4 million. Wait! Before you judge me, I need say that the foundation covers about 380 sq.meter. I have included the plan as well so you have an idea of what I am working on (not the actual archy plan though... thought this would be nicer grin).

1 Share

Re: A Dairy Of My 1st Building Project by edshaf: 4:18pm On Jul 03, 2013
And with that, the german floor was completed!
Step by step...

1 Share

Re: A Dairy Of My 1st Building Project by edshaf: 4:19pm On Jul 03, 2013
...by step by step ...

Re: A Dairy Of My 1st Building Project by edshaf: 4:26pm On Jul 03, 2013
The German floor was completed in March amidst a lot of rain. Anyhow, nothing was done in April and work resumed in June.
I wish I could state the reason for not doing anything in April was to strengthen the foundation, but that would be a lie.
I needed time to raise money to get the next phase started... raising up to Decking level... Estimated at 2.3million...

By the way, I need to do something about the grasses growing around the compound. I was advised to fill the compound now, but I am yet to construct the septic system and the security house... What to do, what to do!!!

3 Likes 1 Share

Re: A Dairy Of My 1st Building Project by edshaf: 4:49pm On Jul 03, 2013
These are the 3D perspectives I got from my Architect... My realistic target for completion is December 2015 (So help me God)...

2 Likes

Re: A Dairy Of My 1st Building Project by fendorf(m): 5:58pm On Jul 03, 2013
Please call us for your GRANITE of any size.07064696356 fendorf2003@yahoo.com

1 Like

Re: A Dairy Of My 1st Building Project by Femonjay(m): 6:46pm On Jul 03, 2013
edshaf!:
These are the 3D perspectives I got from my Architect... My realistic target for completion is December 2015 (So help me God)...


Good job brooo. God will help you.

3 Likes

Re: A Dairy Of My 1st Building Project by edshaf: 7:20am On Jul 04, 2013
Femonjay:


Good job brooo. God will help you.

Thanks a lot and Amen.

1 Like

Re: A Dairy Of My 1st Building Project by edshaf: 12:12pm On Jul 16, 2013
Now, the lintel is all done... raising the next 2 block levels is already on the way.

Re: A Dairy Of My 1st Building Project by edshaf: 1:23pm On Apr 27, 2015
I had a 'realistic' target of December 2015 as completion date. That is no longer the case because the whole of 2014 was eventful with no work done on site.
Work however resumed in April, 2015 with the decking work.
Re: A Dairy Of My 1st Building Project by edshaf: 1:33pm On Apr 27, 2015
From my last update, I managed to complete the septic tank and soakaway. Did some filling (incomplete).

The whole of April was used in getting the decking done.

16mm used for the beams and secret beams while 12mm used for the mats. A total of 4.5 tons of 12mm + 1.5 tons of 16mm used.
267 bags of cements, 6 trailers (180 tons) of granite (less 10 tons) and 120 tons of sand used for the 6 inchs casting.
Re: A Dairy Of My 1st Building Project by edshaf: 1:37pm On Apr 27, 2015
Pix

Re: A Dairy Of My 1st Building Project by mufutau55(m): 2:30pm On Apr 27, 2015
edshaf:
I had a 'realistic' target of December 2015 as completion date. That is no longer the case because the whole of 2014 was eventful with no work done on site. Work however resumed in April, 2015 with the decking work.

Wow! All these years.. welcome back though. So what is the specifications of the buildings..
I can see 3 bedrooms flats on one side and don't know what others are. Please give details, so we can follow you thoroughly.
Thanks and welcome back.

Hajji M.

2 Likes

Re: A Dairy Of My 1st Building Project by edshaf: 5:29pm On Apr 27, 2015
mufutau55:


Wow! All these years.. welcome back though. So what is the specifications of the buildings..
I can see 3 bedrooms flats on one side and don't know what others are. Please give details, so we can follow you thoroughly.
Thanks and welcome back.

Hajji M.

My oga,
Thanks. Yes, it's been a while. Was involved in other 'critical projects' and had to sacrifice something for something.

A duplex, 1 storey building in front with guest lounge, ensuite guest room, visitor's toilet, dining room, living room, pantry and kitchen on the lower floor. A family living room, 1 ensuite master bedroom, 2 ensuite bedrooms and an office on the upper floor.

Adjoining the duplex is a 3 bedroom flat on both the ground floor and upper floor.

The design is with the intention of having a two 3 bedroom flats connected wall to wall to a 4 bedroom duplex.

I will have a plan uploaded when opportuned

4 Likes 2 Shares

Re: A Dairy Of My 1st Building Project by mufutau55(m): 6:20pm On Apr 27, 2015
edshaf:


My oga,
Thanks. Yes, it's been a while. Was involved in other 'critical projects' and had to sacrifice something for something.

A duplex, 1 storey building in front with guest lounge, ensuite guest room, visitor's toilet, dining room, living room, pantry and kitchen on the lower floor. A family living room, 1 ensuite master bedroom, 2 ensuite bedrooms and an office on the upper floor.

Adjoining the duplex is a 3 bedroom flat on both the ground floor and upper floor.

The design is with the intention of having a two 3 bedroom flats connected wall to wall to a 4 bedroom duplex.

I will have a plan uploaded when opportuned

Thank you for the details.. and welcome back. We will be on the lookout for the designs. Thank you.

Hajji M.

1 Like

Re: A Dairy Of My 1st Building Project by edshaf: 3:09am On Apr 28, 2015
Pix

Re: A Dairy Of My 1st Building Project by edshaf: 3:34am On Apr 28, 2015
Plan

2 Likes 1 Share

Re: A Dairy Of My 1st Building Project by rydeorsail(m): 4:50am On Apr 28, 2015
is your C of O out yet?
Re: A Dairy Of My 1st Building Project by edshaf: 6:51am On Apr 28, 2015
rydeorsail:
is your C of O out yet?

Not yet bro. I had to pause the process in 2012 because of the electronic C of O. I have not been available since 2013 to resume the process until a week ago.
Re: A Dairy Of My 1st Building Project by Nobody: 7:56am On Apr 28, 2015
Goodspeed on your project!
Re: A Dairy Of My 1st Building Project by rydeorsail(m): 8:18pm On Apr 30, 2015
edshaf:


Not yet bro. I had to pause the process in 2012 because of the electronic C of O. I have not been available since 2013 to resume the process until a week ago.

Good luck bro..and i can only imagine..i av been on my governor consent since 2013...
Re: A Dairy Of My 1st Building Project by nameoh: 9:51pm On Apr 30, 2015
pls how much did the decking cost you.
Re: A Dairy Of My 1st Building Project by edshaf: 4:10pm On May 03, 2015
nameoh:
pls how much did the decking cost you.

Based on the structural drawing, below is the list of materials used:

1.5 tons of 16mm iron rods
3.0 tons of 12mm iron rods + extra 12 pieces
1.5 tons of 10mm iron rods
6 trailers (10 tyres) of sharp sand
4 trailers (10 tyres) of granite (true 30 tons)
265 bags of cements

In total, I spent #2,782,250

Off course, I didn't include #400,000 omo onile's money and #40,000 cost of feeding the decking labourers...

1 Like 1 Share

Re: A Dairy Of My 1st Building Project by mufutau55(m): 5:08pm On May 03, 2015
What is the dimensions of the building in Length and Width. Thanks.

Hajji M.
Re: A Dairy Of My 1st Building Project by edshaf: 3:33pm On May 04, 2015
mufutau55:
What is the dimensions of the building in Length and Width. Thanks.

Hajji M.


12.6m x 26m
Re: A Dairy Of My 1st Building Project by FADEO: 3:46pm On May 04, 2015
Is the building still on or it is completed already?
am also starting a project before the end of the month. so I might need your input as things unfolds.

1 Like 1 Share

Re: A Dairy Of My 1st Building Project by FADEO: 3:49pm On May 04, 2015
the building is like a duplex in front and 3 bedroom behind? am I right
Re: A Dairy Of My 1st Building Project by edshaf: 8:23pm On May 04, 2015
FADEO:
the building is like a duplex in front and 3 bedroom behind? am I right

Correct.
Re: A Dairy Of My 1st Building Project by edshaf: 9:40pm On May 04, 2015
FADEO:
Is the building still on or it is completed already?
am also starting a project before the end of the month. so I might need your input as things unfolds.

It is still very much a work in progress. I will glad to share knowledge and wish you the very best on your pending project.

1 Like 1 Share

(1) (2) (3) (4) (5) (Reply)

LASBCA Seals The Biggest Building In Bariga (Photos) / Prices Of Land In Lekki Increase By 500% In Just Five Years / Building Collapse At Agege, Lagos, Five People Killed

(Go Up)

Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health
religion celebs tv-movies music-radio literature webmasters programming techmarket

Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 45
Disclaimer: Every Nairaland member is solely responsible for anything that he/she posts or uploads on Nairaland.