Welcome, Guest: Register On Nairaland / LOGIN! / Trending / Recent / New
Stats: 3,208,587 members, 8,003,043 topics. Date: Friday, 15 November 2024 at 05:20 AM

Nigerian Government Pledges To Complete Construction Projects In Three Years - Properties - Nairaland

Nairaland Forum / Nairaland / General / Properties / Nigerian Government Pledges To Complete Construction Projects In Three Years (513 Views)

Abuja's Amazing Construction Projects / How Much Would It Cost Me To Complete This 3Bedroom Bungalow? (2) (3) (4)

(1) (Reply)

Nigerian Government Pledges To Complete Construction Projects In Three Years by OYELLOLO: 11:48pm On Jun 19, 2016
[color=#006600][/color]
The Minister of Power, Works and Housing, Babatunde Fashola, says the Federal Government is committed to finishing all ongoing projects within three years.
Mr. Fashola gave the assurance on Saturday evening after inspecting work at the Loko-Oweto Bridge over River Benue. The bridge connects Loko and Oweto communities in Nasarawa and Benue respectively.
He said the Federal Government would make funds available to pay contractors as soon as they delivered completed projects.
“The Federal Government of Nigeria and President Muhammadu Buhari have expressed very clear commitment to finish the ongoing and abandoned projects.
“We are focusing on completion of ongoing projects; this is one of the many ongoing projects.
“Lagos-Ibadan expressway is one of them; Kano-Maiduguri is one of them; Ilorin-Jebba is one of them and the Second Niger Bridge is one of them.
“All those projects now, the contractors are moving back to sites and work is beginning. Gradually over the next three years we would complete many of them,” the minister said.
Mr. Fashola expressed the confidence that the resumption of construction activities would stimulate expansion of infrastructure, create jobs and generate commercial opportunities for the people.
He said when completed, the Loko-Oweto Bridge would boost socio-economic activities in Nasarawa and Benue.
“You will see those who lost their jobs; they would come back to work. You would see increased merchandising and supply of building materials.
“When this project is completed, it would open up these communities; connect Nasarawa State and Benue; farmers would benefit from the movement and transportation of their farm produce.
“I am optimistic that we would get this project completed in 2018,” Mr. Fashola noted.
The News Agency of Nigeria reports that the Loko-Oweto Bridge contract was awarded to RCC Nig. Ltd. in November 2011 at N36. 1 billion with original completion date of Nov. 15, 2015.
The project was stalled in 2014 due to lack of funding and currently, at a revised contract sum of N51.6 billion, the project is scheduled for completion in 2018.
Re: Nigerian Government Pledges To Complete Construction Projects In Three Years by youngest85(m): 11:55pm On Jun 19, 2016
BRF has turned to broda Lai
Re: Nigerian Government Pledges To Complete Construction Projects In Three Years by SwtLynZy(f): 11:58pm On Jun 19, 2016
I pray oh

(1) (Reply)

515sqm For Sale At Lekki, 3 Round About:08032222501 / For Sale @ Magodo Phase 2 Shagisha (pictures) 4nos Of 4br D/H / POP, Wall Screeding And Window Art Work

(Go Up)

Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health
religion celebs tv-movies music-radio literature webmasters programming techmarket

Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 9
Disclaimer: Every Nairaland member is solely responsible for anything that he/she posts or uploads on Nairaland.