Nairaland Forum / Nairaland / General / Properties / Roofing And Finish Works For A New Bungalow In Nsukka (8514 Views)
Roofing And Finish Works For A New Bungalow In Oji River / NEW BUNGALOW DESIGN:: 6 Bedroom Bungalow Design With 2 Master's Bedroom. / Old Widow Gets A New Bungalow As Gift In Abia (Photos) (2) (3) (4)
(1) (2) (3) (4) (Reply) (Go Down)
Re: Roofing And Finish Works For A New Bungalow In Nsukka by spyder880(m): 7:11am On Aug 24, 2019 |
Sand filling thus compound. ........ 1 Like
|
Re: Roofing And Finish Works For A New Bungalow In Nsukka by spyder880(m): 7:16am On Aug 24, 2019 |
Let's fill the compound with more sand........... 2 Likes
|
Re: Roofing And Finish Works For A New Bungalow In Nsukka by spyder880(m): 7:13am On Aug 29, 2019 |
Foundation for a kitchen and toilet inside the compound. ...... 1 Like
|
Re: Roofing And Finish Works For A New Bungalow In Nsukka by spyder880(m): 7:19am On Aug 29, 2019 |
Raising the walls..... 1 Like
|
Re: Roofing And Finish Works For A New Bungalow In Nsukka by spyder880(m): 8:10am On Aug 29, 2019 |
Tiles work on the front columns....... 1 Like
|
Re: Roofing And Finish Works For A New Bungalow In Nsukka by spyder880(m): 8:14am On Aug 29, 2019 |
Some part of the back of this house, showing the new additions. ...... 1 Like
|
Re: Roofing And Finish Works For A New Bungalow In Nsukka by spyder880(m): 8:16am On Aug 29, 2019 |
More of the new house. .... 1 Like
|
Re: Roofing And Finish Works For A New Bungalow In Nsukka by spyder880(m): 8:18am On Aug 29, 2019 |
Approach to the house. ........ 3 Likes
|
Re: Roofing And Finish Works For A New Bungalow In Nsukka by spyder880(m): 8:21am On Aug 29, 2019 |
More pictures from the front. ...... 1 Like
|
Re: Roofing And Finish Works For A New Bungalow In Nsukka by spyder880(m): 8:24am On Aug 29, 2019 |
Work continues today as we roof the small addition and ceil it, while doing some other works...... 2 Likes
|
Re: Roofing And Finish Works For A New Bungalow In Nsukka by spyder880(m): 8:08am On Sep 02, 2019 |
Plumbing and electrical works for the fence in progress today........ 1 Like |
Re: Roofing And Finish Works For A New Bungalow In Nsukka by anochuks08(m): 1:28pm On Sep 02, 2019 |
spyder880:Please what is the importance of the sandfill? Regards |
Re: Roofing And Finish Works For A New Bungalow In Nsukka by spyder880(m): 7:04am On Sep 03, 2019 |
anochuks08: The sand filling was done to raise the level of the compound. The inside of the compound is very low and we had to fill in with sharp sand. This is a preparation to other compound works like a concrete floor which will come soon. 2 Likes |
Re: Roofing And Finish Works For A New Bungalow In Nsukka by anochuks08(m): 10:34am On Sep 03, 2019 |
spyder880:Noted. Thanks for the explanation boss. 1 Like |
Re: Roofing And Finish Works For A New Bungalow In Nsukka by spyder880(m): 7:11am On Sep 04, 2019 |
anochuks08: Thanks Bro. |
Re: Roofing And Finish Works For A New Bungalow In Nsukka by spyder880(m): 7:13am On Sep 04, 2019 |
We have roofed the kitchen, plastering and ceiling done. Work is still going on. 2 Likes
|
Become a landlord at Maya ikorodu in a fully developed area for 1.2m / Fcta Warning! Develop Your Plots In Karshi Or Have Them Revoked-min / *SILVERTON GARDENS 1 AREPO* 10mins Drive From Alausa. #6m Per Plot
(Go Up)
Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health religion celebs tv-movies music-radio literature webmasters programming techmarket Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 15 |