Diary Of Our Remodelling And Finishing Works On This Luxury 6 Bedroom Duplex. by Procontractor(m): 10:37am On Jul 24, 2020 |
Welcome! We are Gozok Engineering Services Ltd. A company dedicated to providing professional and innovative services in the construction industry. Stay tuned as we provide you with construction updates on the reconstruction and finishing works for this project. Scope of the project: 1) Reconstruction works 2) General finishing works 3) swimming pool 4) Lanscaping The picture below is how we met it.
|
Re: Diary Of Our Remodelling And Finishing Works On This Luxury 6 Bedroom Duplex. by Procontractor(m): 10:53am On Jul 24, 2020 |
As always when we are called in for finishing jobs on a carcass, is our culture to check the walls and edges for straightness, especially already plastered walls. Most clients make mistake of thinking that finishing works starts from screeding and POP. The answer is no, it actually starts from plastering cos that is the pivot on which most finishing operation revolves. |
Re: Diary Of Our Remodelling And Finishing Works On This Luxury 6 Bedroom Duplex. by Procontractor(m): 10:57am On Jul 24, 2020 |
Checking already plastered walls, as expected walls are skewed and iregular
|
Re: Diary Of Our Remodelling And Finishing Works On This Luxury 6 Bedroom Duplex. by Procontractor(m): 11:05am On Jul 24, 2020 |
Still on wall testing...
|
Re: Diary Of Our Remodelling And Finishing Works On This Luxury 6 Bedroom Duplex. by Procontractor(m): 11:13am On Jul 24, 2020 |
Replastering
|
Re: Diary Of Our Remodelling And Finishing Works On This Luxury 6 Bedroom Duplex. by Procontractor(m): 1:15pm On Jul 24, 2020 |
Breaking and reinstatement of door lintels to required height.
|
Re: Diary Of Our Remodelling And Finishing Works On This Luxury 6 Bedroom Duplex. by Procontractor(m): 6:43pm On Jul 24, 2020 |
Observe the new height for the door spaces. When these doors are fixed, I promise you they will stand tall and look elegant.
|
Re: Diary Of Our Remodelling And Finishing Works On This Luxury 6 Bedroom Duplex. by soonest(f): 8:54pm On Jul 24, 2020 |
Following |
Re: Diary Of Our Remodelling And Finishing Works On This Luxury 6 Bedroom Duplex. by Procontractor(m): 6:34am On Jul 25, 2020 |
soonest: All right kindly stay tuned. |
Re: Diary Of Our Remodelling And Finishing Works On This Luxury 6 Bedroom Duplex. by Procontractor(m): 10:40am On Jul 25, 2020 |
Still on reconstruction works. Moulds are already forming on plaster, cos they did a shady job on the water collector.We will be removing all installed rain collectors and reinstall later.
|
Re: Diary Of Our Remodelling And Finishing Works On This Luxury 6 Bedroom Duplex. by Procontractor(m): 11:59am On Jul 25, 2020 |
Replastering of wrongly plastered portions...
|
Re: Diary Of Our Remodelling And Finishing Works On This Luxury 6 Bedroom Duplex. by Procontractor(m): 4:06pm On Jul 25, 2020 |
Still on it, no room for bad walls.
|
Re: Diary Of Our Remodelling And Finishing Works On This Luxury 6 Bedroom Duplex. by Procontractor(m): 7:33pm On Jul 25, 2020 |
Correction of affected edges
|
Re: Diary Of Our Remodelling And Finishing Works On This Luxury 6 Bedroom Duplex. by Procontractor(m): 9:02pm On Jul 25, 2020 |
Demolition of attached building at the rear, this structure has taken all the available space. There is no reason for it to be there hence the demolition with approval from the client.
|
Re: Diary Of Our Remodelling And Finishing Works On This Luxury 6 Bedroom Duplex. by Procontractor(m): 9:19am On Jul 27, 2020 |
Replastering of bent walls, this operation will continue round the building till all iregularities are corrected. 1 Like
|
Re: Diary Of Our Remodelling And Finishing Works On This Luxury 6 Bedroom Duplex. by TheNigerianPers: 2:28pm On Jul 27, 2020 |
Well Done. I like to see people bring a new dimension to how things are done. But you need to do better by providing protective equipment for your workers. Boots, gloves and helmets will go a long way. 2 Likes |
Re: Diary Of Our Remodelling And Finishing Works On This Luxury 6 Bedroom Duplex. by Procontractor(m): 3:35pm On Jul 27, 2020 |
TheNigerianPers: Thanks boss, well noted we are working on it already. 2 Likes |
Re: Diary Of Our Remodelling And Finishing Works On This Luxury 6 Bedroom Duplex. by Procontractor(m): 4:12pm On Jul 27, 2020 |
New look so far. The concrete facia is being corrected. Concrete pillars have been properly dressed, we are getting there! 1 Like
|
Re: Diary Of Our Remodelling And Finishing Works On This Luxury 6 Bedroom Duplex. by Procontractor(m): 10:21am On Jul 28, 2020 |
Talorin cement on walls preparatory for replastering.
|
Re: Diary Of Our Remodelling And Finishing Works On This Luxury 6 Bedroom Duplex. by omanzo02: 10:47am On Jul 28, 2020 |
Procontractor: Talorin cement? What type of cement is that and what its function are? Mould formation on already completed and painted building is very rampant, I always wonder if atmospheric humidity is the cause or quality of paint used? Anyway that reconstruction seem like a total makeover. Thanks |
Re: Diary Of Our Remodelling And Finishing Works On This Luxury 6 Bedroom Duplex. by Johntemmy(m): 10:59am On Jul 28, 2020 |
contact me for your painting and wood work for your roofing.call or Whatsapp on 07060795767 |
Re: Diary Of Our Remodelling And Finishing Works On This Luxury 6 Bedroom Duplex. by Procontractor(m): 11:46am On Jul 28, 2020 |
omanzo02: Thank you for stoping by. Tailorin as it sounds is a 'pseudo' name giving to a mixture of cement, sand and water in disproportionate ratio. Is usually applied on already plastered surfaces to roughen the wall to receive fresh plaster. This is used where you don't intend to break off the existing plaster. Whether we are doing reconstruction or make over, I believe its reconstruction cos we have to a large extent done a lot of remodelling on this structure. On mould formation, observe that this structure is at carcass stage, not painted nor finished and this moulds are already ravaging the structure, this is solely a problem of bad workmanship on the rain collector causing it to leak and soak all the walls. Kindly stay tuned sir. Hope I answered your questions? |
Re: Diary Of Our Remodelling And Finishing Works On This Luxury 6 Bedroom Duplex. by Procontractor(m): 12:31pm On Jul 28, 2020 |
Still on it...
|
Re: Diary Of Our Remodelling And Finishing Works On This Luxury 6 Bedroom Duplex. by Procontractor(m): 10:25am On Jul 29, 2020 |
Progress.. observe the gradual transformation.
|
Re: Diary Of Our Remodelling And Finishing Works On This Luxury 6 Bedroom Duplex. by Procontractor(m): 5:07pm On Jul 29, 2020 |
Still on reconstruction...
|
Re: Diary Of Our Remodelling And Finishing Works On This Luxury 6 Bedroom Duplex. by Procontractor(m): 8:09am On Jul 30, 2020 |
More updates coming, we will soon get into the main business. |
Re: Diary Of Our Remodelling And Finishing Works On This Luxury 6 Bedroom Duplex. by Procontractor(m): 2:46pm On Jul 30, 2020 |
Correction works on the concrete fascia, we are leaving no stone unturned.
|
Re: Diary Of Our Remodelling And Finishing Works On This Luxury 6 Bedroom Duplex. by Procontractor(m): 10:43am On Jul 31, 2020 |
Work in progress, the shape of the structure is coming out already.
|
Re: Diary Of Our Remodelling And Finishing Works On This Luxury 6 Bedroom Duplex. by Procontractor(m): 12:40pm On Aug 03, 2020 |
Good day every one, work continues today. Still on reconstruction work. We had to creat alternative access to the walk in closet for the master bedroom, it must not be accessed only through the bathroom!
|
Re: Diary Of Our Remodelling And Finishing Works On This Luxury 6 Bedroom Duplex. by Procontractor(m): 9:29am On Aug 04, 2020 |
What do you think about this so far?
|
Re: Diary Of Our Remodelling And Finishing Works On This Luxury 6 Bedroom Duplex. by Procontractor(m): 12:44pm On Aug 04, 2020 |
External screeding and correction works going on simultaneously.
|
Re: Diary Of Our Remodelling And Finishing Works On This Luxury 6 Bedroom Duplex. by Procontractor(m): 3:02pm On Aug 04, 2020 |
More updates coming... |
I Buy Faulty Property House Hold Items / New Generator For Sale / Construction Of A 5 Bedroom @ Lekki, Lagos
(Go Up)
Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health religion celebs tv-movies music-radio literature webmasters programming techmarket Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) Nairaland - Copyright © 2005 - 2025 Oluwaseun Osewa. All rights reserved. See How To Advertise. 21 |