Welcome, Guest: Register On Nairaland / LOGIN! / Trending / Recent / New
Stats: 3,205,580 members, 7,993,003 topics. Date: Sunday, 03 November 2024 at 11:13 PM

Estimates For Construction Of A 3 Bedroom Contemporary Bungalow In Rural Enugu - Properties (7) - Nairaland

Nairaland Forum / Nairaland / General / Properties / Estimates For Construction Of A 3 Bedroom Contemporary Bungalow In Rural Enugu (13307 Views)

6 Bedroom Contemporary Smart Duplex - Isheri North / Building A Fence On A Plot Of Land In Rural Enugu State: Costs And Challenges / KNOW THE COST OF YOUR BUILDING PROJECT TODAY-GET YOUR BOQ &BUILDING ESTIMATES (2) (3) (4)

(1) (2) (3) (4) (5) (6) (7) (8) (9) (Reply) (Go Down)

Re: Estimates For Construction Of A 3 Bedroom Contemporary Bungalow In Rural Enugu by spyder880(m): 12:21am On Apr 19, 2023
More roofing wood still waiting to be used...........

Re: Estimates For Construction Of A 3 Bedroom Contemporary Bungalow In Rural Enugu by spyder880(m): 9:07am On Apr 20, 2023
More works still going on here today.........
Re: Estimates For Construction Of A 3 Bedroom Contemporary Bungalow In Rural Enugu by spyder880(m): 10:52am On Apr 23, 2023
Roofing completed, ceiling nurgins also completed...........

Re: Estimates For Construction Of A 3 Bedroom Contemporary Bungalow In Rural Enugu by spyder880(m): 10:58am On Apr 23, 2023
More pictures.........

Re: Estimates For Construction Of A 3 Bedroom Contemporary Bungalow In Rural Enugu by spyder880(m): 11:06am On Apr 23, 2023
Outside..........

Re: Estimates For Construction Of A 3 Bedroom Contemporary Bungalow In Rural Enugu by 1x2x3: 8:38pm On Apr 23, 2023
spyder880:
Roofing completed, ceiling nurgins also completed...........


What would a house like this cost to complete in Asaba?
Re: Estimates For Construction Of A 3 Bedroom Contemporary Bungalow In Rural Enugu by spyder880(m): 8:41pm On Apr 23, 2023
1x2x3:



What would a house like this cost to complete in Asaba?

When you say completed, do you mean till roofing level or till painting level?

Thanks.
Re: Estimates For Construction Of A 3 Bedroom Contemporary Bungalow In Rural Enugu by 1x2x3: 8:42pm On Apr 23, 2023
spyder880:


When you say completed, do you mean till roofing level or till painting level?

Thanks.

Painting level Sir.
Re: Estimates For Construction Of A 3 Bedroom Contemporary Bungalow In Rural Enugu by spyder880(m): 9:11pm On Apr 23, 2023
1x2x3:


Painting level Sir.

How is the land, level, sloped or waterlogged?
Re: Estimates For Construction Of A 3 Bedroom Contemporary Bungalow In Rural Enugu by 1x2x3: 9:33pm On Apr 23, 2023
spyder880:


How is the land, level, sloped or waterlogged?

Level dry land.
Re: Estimates For Construction Of A 3 Bedroom Contemporary Bungalow In Rural Enugu by spyder880(m): 9:36pm On Apr 23, 2023
1x2x3:


Level dry land.

Budget N25m.
Re: Estimates For Construction Of A 3 Bedroom Contemporary Bungalow In Rural Enugu by 1x2x3: 9:40pm On Apr 23, 2023
spyder880:


Budget N25m.

OK thanks, I will reach you on whatsapp

1 Like

Re: Estimates For Construction Of A 3 Bedroom Contemporary Bungalow In Rural Enugu by spyder880(m): 10:26pm On Apr 23, 2023
1x2x3:


OK thanks, I will reach you on whatsapp

Ok, thanks.
Re: Estimates For Construction Of A 3 Bedroom Contemporary Bungalow In Rural Enugu by eziokwunwoko(m): 11:31pm On Apr 23, 2023
Please what is the exact
1. quantity of sand used for filling the foundation.
2. quantity of Cement used for German floor.
Chechem:


Please bro, is this cost only for foundation to DPC
Re: Estimates For Construction Of A 3 Bedroom Contemporary Bungalow In Rural Enugu by eziokwunwoko(m): 11:35pm On Apr 23, 2023
Sir
What is the exact quantity of laterite sand used for filling foundation
What is the exact quantity of cement used for DCP/ German floor only.
What other materiala used for German floor only

quote author=spyder880 post=120682680]Haven seen the full picture of the costs of doing this foundation, as all the works are nearly completed, all costs paid for and every materials accounted for, I think I have the total costs of building this foundation till the cast of the DPC which is currently ongoing to completion. We have spent the following monies on both materials, workmanship and supervision of this stage of the project. Please feel free to ask me any questions about any of the materials, or lump sum which I allocated to some stages. Thanks.

1. Cost of removal of old house N10,000
2. Pegging materials/ wheel barrow N66,750
3. Cement (175) x 2543 = N445,025
4. 9" blocks (2275) 260 = N591,000
5. Trips of Sharp sand (14) 28,000 = N392,000
6. Chippings (2) 160,000 = N320,000
7. Local gravel (4) 53,000 = N212,000
8. Filling sand (32) 25,000 = N800,000
9. 16mm rods (18) 8500 = N153,000
10. 12mm rods (63) 4800 = N302,400
11. 8mm rods (35) 2500 = N87,500
12. Binding wire (1) N15,500
13. All transportation N109,600
14. Water supply N112,000
15. Wooden planks N64,000
16. Workmanship/Supervision N1,119,950

Total N4,801,225.00[/quote]
Re: Estimates For Construction Of A 3 Bedroom Contemporary Bungalow In Rural Enugu by spyder880(m): 7:33am On Apr 24, 2023
eziokwunwoko:
Sir
What is the exact quantity of laterite sand used for filling foundation
What is the exact quantity of cement used for DCP/ German floor only.
What other materiala used for German floor only

quote author=spyder880 post=120682680]Haven seen the full picture of the costs of doing this foundation, as all the works are nearly completed, all costs paid for and every materials accounted for, I think I have the total costs of building this foundation till the cast of the DPC which is currently ongoing to completion. We have spent the following monies on both materials, workmanship and supervision of this stage of the project. Please feel free to ask me any questions about any of the materials, or lump sum which I allocated to some stages. Thanks.

1. Cost of removal of old house N10,000
2. Pegging materials/ wheel barrow N66,750
3. Cement (175) x 2543 = N445,025
4. 9" blocks (2275) 260 = N591,000
5. Trips of Sharp sand (14) 28,000 = N392,000
6. Chippings (2) 160,000 = N320,000
7. Local gravel (4) 53,000 = N212,000
8. Filling sand (32) 25,000 = N800,000
9. 16mm rods (18) 8500 = N153,000
10. 12mm rods (63) 4800 = N302,400
11. 8mm rods (35) 2500 = N87,500
12. Binding wire (1) N15,500
13. All transportation N109,600
14. Water supply N112,000
15. Wooden planks N64,000
16. Workmanship/Supervision N1,119,950

Total N4,801,225.00

32 trips of sand for filling the foundation, about 80 bags of cement for DPC. Thanks.

1 Like

Re: Estimates For Construction Of A 3 Bedroom Contemporary Bungalow In Rural Enugu by billyG(m): 10:28am On Apr 24, 2023
~#4.8m for foundation?this bungalow is costing like duplex.... lesson buy flat land instead of slopy land unless you are a money bag.
Re: Estimates For Construction Of A 3 Bedroom Contemporary Bungalow In Rural Enugu by spyder880(m): 11:00am On Apr 24, 2023
billyG:
~#4.8m for foundation?this bungalow is costing like duplex.... lesson buy flat land instead of slopy land unless you are a money bag.

It's actually N5m. We later corrected something in the cement cost. Sloping land costs a lot to work on.
Re: Estimates For Construction Of A 3 Bedroom Contemporary Bungalow In Rural Enugu by spyder880(m): 8:20am On Apr 29, 2023
More updates from this site later today...........
Re: Estimates For Construction Of A 3 Bedroom Contemporary Bungalow In Rural Enugu by spyder880(m): 11:52am On Apr 30, 2023
Bringing in some more materials for the plastering of this house, and for the scaffolding works around the house............

Re: Estimates For Construction Of A 3 Bedroom Contemporary Bungalow In Rural Enugu by spyder880(m): 11:55am On Apr 30, 2023
Around the house yesterday...........

Re: Estimates For Construction Of A 3 Bedroom Contemporary Bungalow In Rural Enugu by spyder880(m): 11:59am On Apr 30, 2023
We are casting the concrete top of the parapet wall................

Re: Estimates For Construction Of A 3 Bedroom Contemporary Bungalow In Rural Enugu by spyder880(m): 12:03pm On Apr 30, 2023
The look from the top of the roof...........

Re: Estimates For Construction Of A 3 Bedroom Contemporary Bungalow In Rural Enugu by spyder880(m): 12:06pm On Apr 30, 2023
More............

Re: Estimates For Construction Of A 3 Bedroom Contemporary Bungalow In Rural Enugu by spyder880(m): 7:17pm On May 04, 2023
We have done the scaffolding of this house in readiness for the plastering works that is about to commence.............

Re: Estimates For Construction Of A 3 Bedroom Contemporary Bungalow In Rural Enugu by spyder880(m): 7:22pm On May 04, 2023
More.......

Re: Estimates For Construction Of A 3 Bedroom Contemporary Bungalow In Rural Enugu by spyder880(m): 9:26pm On May 09, 2023
Electrical piping works ongoing at this site............

Dressing works at the top of the parapet wall......

Re: Estimates For Construction Of A 3 Bedroom Contemporary Bungalow In Rural Enugu by spyder880(m): 9:34pm On May 09, 2023
Works going on around the house...........

Re: Estimates For Construction Of A 3 Bedroom Contemporary Bungalow In Rural Enugu by 1x2x3: 3:19am On May 10, 2023
spyder880:
The look from the top of the roof...........

Well done sir, what are the pros and cons of this type of roofing?
What's the importance of the casting you did at the top edges?
Re: Estimates For Construction Of A 3 Bedroom Contemporary Bungalow In Rural Enugu by spyder880(m): 5:21am On May 10, 2023
Our roofing sheets for this site arrives..........

Re: Estimates For Construction Of A 3 Bedroom Contemporary Bungalow In Rural Enugu by spyder880(m): 5:25am On May 10, 2023
1x2x3:


Well done sir, what are the pros and cons of this type of roofing?
What's the importance of the casting you did at the top edges?

1. Cost effectiveness, this type of roof is cheaper to do, but some says the beauty of the roof is now hidden from public view.

The coping on the top of the parapet wall is for effects, a design that adds to the beauty, plus a way to shift the water dropping line away from the side of the wall.

Thanks.

1 Like

Re: Estimates For Construction Of A 3 Bedroom Contemporary Bungalow In Rural Enugu by michlins(m): 6:42am On May 10, 2023
spyder880:
Our roofing sheets for this site arrives..........
please sir, what are the pros and cons of doing this flat roof and why are most carpenters against it

(1) (2) (3) (4) (5) (6) (7) (8) (9) (Reply)

Opic, Isheri North 10 acres land (Along Lagos-ibadan Expressway) / NIL / Goodnews To RCCG Members..pics Attached

(Go Up)

Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health
religion celebs tv-movies music-radio literature webmasters programming techmarket

Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 29
Disclaimer: Every Nairaland member is solely responsible for anything that he/she posts or uploads on Nairaland.