Welcome, Guest: Register On Nairaland / LOGIN! / Trending / Recent / NewStats: 3,218,454 members, 8,038,009 topics. Date: Friday, 27 December 2024 at 04:07 AM |
Nairaland Forum / Nairaland / General / Properties / 5 Bedroom Duplex - Ibadan Project (7705 Views)
Ibadan Project By ADEDWARD, Tower Aluminum Casement With 5mm Glass, / Construction Of A Twin 4bd/rm Duplex @IBADAN By Dioritestructures / Before And After Painting Of An Ibadan Project (2) (3) (4)
(1) (2) (3) (4) (5) (6) (7) (Reply) (Go Down)
Re: 5 Bedroom Duplex - Ibadan Project by Dennis3D(m): 8:51am On Sep 06, 2023 |
We have commenced block setting. Ground floor lay out done. And work commences 1 Like
|
Re: 5 Bedroom Duplex - Ibadan Project by Dennis3D(m): 8:54am On Sep 06, 2023 |
We are using stone Dust vibrated blocks. The best in the area though more expensive than the regular blocks.
|
Re: 5 Bedroom Duplex - Ibadan Project by Dennis3D(m): 1:55pm On Sep 06, 2023 |
Block works rising
|
Re: 5 Bedroom Duplex - Ibadan Project by Dennis3D(m): 2:52pm On Sep 06, 2023 |
We are making progress
|
Re: 5 Bedroom Duplex - Ibadan Project by Dennis3D(m): 11:55am On Sep 07, 2023 |
The blocks works are at Lintel in some areas now. We are doing the volume form work simultaneously
|
Re: 5 Bedroom Duplex - Ibadan Project by Dennis3D(m): 2:30pm On Sep 07, 2023 |
More site updates coming today |
Re: 5 Bedroom Duplex - Ibadan Project by ArcToyin(m): 7:39pm On Sep 07, 2023 |
Thumb up Engr. Kindly, inform us of the price of materials as the project progress. 1 Like |
Re: 5 Bedroom Duplex - Ibadan Project by Dennis3D(m): 4:44am On Sep 08, 2023 |
ArcToyin: Good morning Thanks for your comment Kindly let me know the particular materials you need their prices so I can write them for you. |
Re: 5 Bedroom Duplex - Ibadan Project by Dennis3D(m): 4:46am On Sep 08, 2023 |
More site Update. Prparijg for Lintel formwork and reinforcements.
|
Re: 5 Bedroom Duplex - Ibadan Project by Dennis3D(m): 4:47am On Sep 08, 2023 |
Colin's and beams form work.
|
Re: 5 Bedroom Duplex - Ibadan Project by ArcToyin(m): 7:12pm On Sep 08, 2023 |
Dennis3D: Reinforcement Bamboo. Whenever prices increase, you can update to create awareness. Thanks a bunch 1 Like |
Re: 5 Bedroom Duplex - Ibadan Project by Dennis3D(m): 11:30pm On Sep 08, 2023 |
ArcToyin: 16mm it's selling between 8800 - 9,500 between local and TMT 12mm between - 4700 - 5100 in similar fashion 10mm between 3,500 - 3,900 respectively. Bamboo is around 750 - 850 depending on the location and proximity to your site. |
Re: 5 Bedroom Duplex - Ibadan Project by Dennis3D(m): 11:32pm On Sep 08, 2023 |
Here is about today.
|
Re: 5 Bedroom Duplex - Ibadan Project by Dennis3D(m): 5:41am On Sep 09, 2023 |
Keep following up with us always here |
Re: 5 Bedroom Duplex - Ibadan Project by Dennis3D(m): 5:28am On Sep 10, 2023 |
Plumbing materials arriving at site now... We and the installation ongoing simultaneously
|
Re: 5 Bedroom Duplex - Ibadan Project by Dennis3D(m): 5:29am On Sep 10, 2023 |
Concrete works on Lintel and columns. Our routine is usually Colum first and that's what we are doing below... Good properly mixed concrete mixture of sand, granite, cement and Water
|
Re: 5 Bedroom Duplex - Ibadan Project by ArcToyin(m): 4:12pm On Sep 10, 2023 |
Dennis3D: Wow. That's serious. Thanks for the info 1 Like |
Re: 5 Bedroom Duplex - Ibadan Project by Timtol(m): 5:49pm On Sep 10, 2023 |
Dennis3D:D for Dennis... Wish you God's speed bro... Keep winning.... #biglove #morecontract 1 Like |
Re: 5 Bedroom Duplex - Ibadan Project by kopell: 12:26am On Sep 11, 2023 |
Dennis3D:Trust you Dennis you never joke with quality of your project even with the speed that you deliver, you're bless to have a good crew that roll with your instructions. I remember my crazy ideas on my project, you stand firm to advise me professionally with your superior argument, another one I will never forget is when you told me to buy building before building. It helps a lot, meaning we bought 90% of every material needed before laying a single block. 1 Like |
Re: 5 Bedroom Duplex - Ibadan Project by Dennis3D(m): 4:56pm On Sep 12, 2023 |
Timtol: Thanks brother 1 Like |
Re: 5 Bedroom Duplex - Ibadan Project by Dennis3D(m): 4:58pm On Sep 12, 2023 |
kopell: Absolutely correct sir. From day one of this project. We bought reinforcement for the project from foundation to Decking. We would have done same for cement if not for the estate rule that states that big trailer of 30 Tons and above can't come in to the estate. Buying matetisis down helps wage against inflation and it's importance can't be overemphasized especially as Nigerian market is fluctuating up and up. Not even up and down. With respect to quality. We don't joke with that. It's the bedrock to our project success while at the speed to which we carry out our task. We pay attention to the core areas of the projects which are the concrete works. Also for projects such as this, we estimated blocks for 420 per one. Upon getting to the location we discovered that their normal blocks were sold for 450 naira per one. Which is even above our budget. But guess what, they had another blocks. Made of stone Dust, and it's sold for 500 naira per one. In a bit to ensure quality, that's what my team and I went for at no additional cost to the client because we want to achieve quality. However, we have contigency plan provided that we are working with in this regard. Alot more I would be staring as the project proceeds. |
Re: 5 Bedroom Duplex - Ibadan Project by Dennis3D(m): 5:00pm On Sep 12, 2023 |
We are done with Lintel works and now leveling the building on preparation for Decking works. Pictures speaks below.
|
Re: 5 Bedroom Duplex - Ibadan Project by Dennis3D(m): 5:06pm On Sep 12, 2023 |
More pictures from the building leveling and Lintel concrete works. We normally do concrete works on Colum a day ahead before we do Lintel. This is to ensure good workability of the concrete on the columns we are doing at a time.
|
Re: 5 Bedroom Duplex - Ibadan Project by Dennis3D(m): 8:58am On Sep 13, 2023 |
Final blocks leveling before Decking. We have a height of 3.15m before Decking beam.
|
Re: 5 Bedroom Duplex - Ibadan Project by Dennis3D(m): 6:50pm On Sep 13, 2023 |
Arrival of bamboo for Decking purposes. We are at Day 25 Now since we started works on this site. Because of the height of the building. We have about 450 bamboo here. Long ones at that. One good thing I would say I got here better than Lagos.
|
Re: 5 Bedroom Duplex - Ibadan Project by Dennis3D(m): 12:43pm On Sep 14, 2023 |
We have procured planks and wood for the decking works as well. Planks here are sold 2,300 and we got about 480 pcs of it in total including for staircase and beams as well as Decking floor. We also bought 2x3x12 Woods for props preparation
|
Re: 5 Bedroom Duplex - Ibadan Project by Dennis3D(m): 12:47pm On Sep 14, 2023 |
And today, Decking works has began. Carpentry works is gonna go on for about 3 - 5 Days of which the welders are on stand by to start up their own work with Decking beam reinforcements once the decking floor is prepared by the Carpenters. 1 Like
|
Re: 5 Bedroom Duplex - Ibadan Project by Dennis3D(m): 3:31am On Sep 15, 2023 |
We are making progress. Keep following up with us.
|
Re: 5 Bedroom Duplex - Ibadan Project by Dennis3D(m): 1:11pm On Sep 15, 2023 |
Our work progress today is impressive.
|
Re: 5 Bedroom Duplex - Ibadan Project by Dennis3D(m): 6:05am On Sep 16, 2023 |
More pictures of the decking formation.
|
Re: 5 Bedroom Duplex - Ibadan Project by Dennis3D(m): 12:03pm On Sep 16, 2023 |
Keep following up with us. We are working back to back. Sitting room and Dinning area Decking formation ongoing now.
|
Re: 5 Bedroom Duplex - Ibadan Project by Dennis3D(m): 3:39pm On Sep 16, 2023 |
We are making progress. Decking floor about - 85% Completed. Would be finally completed 100% by tomorrow. Then staircase and the temporary step for concrete works will be done ASAP. Meanwhile, our welders have started preparing the decking beams accordingly. Our style of execution and precision.
|
(1) (2) (3) (4) (5) (6) (7) (Reply)
Building Soakaway Pit With 5" Blocks / Building The Lagos Warehouse (temporary Structure)/budget Project / Painting And Decorating Of Nairalander's Master's Bedroom& Sitting Room at Lekki
(Go Up)
Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health religion celebs tv-movies music-radio literature webmasters programming techmarket Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 31 |