Help With Costing Of 4 Bedroom Bungalow by grafixdon: 1:35pm On Mar 04, 2020 |
Hello Nairalanders,
Please I need your assistance with costing of 4 bedroom bungalow somewhere at Agbara.
See attached pictures.
So far I've spent 600k plus for 3 coaches level which I think is very expensive compare to what I'd read on this site. Now the engineer is asking for another 810k for German floor.
Kindly help me do the costing so I won't be ripoff.
Thank you. |
Re: Help With Costing Of 4 Bedroom Bungalow by grafixdon: 1:39pm On Mar 04, 2020 |
Spent 600k plus to this level |
Re: Help With Costing Of 4 Bedroom Bungalow by grafixdon: 1:43pm On Mar 04, 2020 |
Na Wa o. No one is willing to help |
Re: Help With Costing Of 4 Bedroom Bungalow by grafixdon: 4:52pm On Mar 04, 2020 |
Help a brother o |
Re: Help With Costing Of 4 Bedroom Bungalow by charlesELIKIBA: 5:33pm On Mar 04, 2020 |
grafixdon: Help a brother o thats a huge bungalow bro ...so far its realistic the prices. |
Re: Help With Costing Of 4 Bedroom Bungalow by grafixdon: 7:30pm On Mar 04, 2020 |
charlesELIKIBA:
thats a huge bungalow bro
...so far its realistic the prices.
OH you mean the quotation is justifiable? |
Re: Help With Costing Of 4 Bedroom Bungalow by Godisgreatest1: 10:41pm On Mar 04, 2020 |
The number of cement in bags is tooooooo much. 100 bags?! Wonderful!. |
Re: Help With Costing Of 4 Bedroom Bungalow by grafixdon: 3:25pm On Mar 05, 2020 |
Godisgreatest1: The number of cement in bags is tooooooo much. 100 bags?! Wonderful!. Thank you, this's what I'm saying. The quotation is too high . I need an expert to help costing this |
Re: Help With Costing Of 4 Bedroom Bungalow by lightofjoy(m): 4:05pm On Mar 05, 2020 |
The quote is high. Talk to me if you need a BOQ that will assist you in your cost planning. Thanks |
Re: Help With Costing Of 4 Bedroom Bungalow by Godisgreatest1: 8:22pm On Mar 05, 2020 |
grafixdon:
Thank you, this what I'm saying. The quotation is too high . I need an expert to help costing this Don't talk to anyone for any BOQ, I managed mine by 'playing to the script'. Don't buy those materials in bulk the way it is listed, do it gradually, you won't buy up to that quantity. What you should negotiate is the 'workmanship'. 4 Likes |
Re: Help With Costing Of 4 Bedroom Bungalow by grafixdon: 9:45pm On Mar 05, 2020 |
Godisgreatest1:
Don't talk to anyone for any BOQ, I managed mine by 'playing to the script'. Don't buy those materials in bulk the way it is listed, do it gradually, you won't buy up to that quantity. What you should negotiate is the 'workmanship'. Thank you bro |
Re: Help With Costing Of 4 Bedroom Bungalow by charlesELIKIBA: 3:39pm On Mar 06, 2020 |
grafixdon:
OH you mean the quotation is justifiable? yes |
Re: Help With Costing Of 4 Bedroom Bungalow by Smartwave: 5:22pm On Mar 06, 2020 |
Too high. |
Re: Help With Costing Of 4 Bedroom Bungalow by dandy2222: 9:04pm On Mar 06, 2020 |
300-400k could do dt thing am seeing there. D quotation is high. 30-40 bags of cement, 2 trips of sand , 1 trip of gravel, 8lengths of 12mm rod, 1,500 blocks at most and 30-50k labour cost can comfortably achieve dt. So u can check d cost of dis materials urself . 2 Likes |
Re: Help With Costing Of 4 Bedroom Bungalow by grafixdon: 12:36pm On Mar 07, 2020 |
dandy2222: 300-400k could do dt thing am seeing there. D quotation is high. 30-40 bags of cement, 2 trips of sand , 1 trip of gravel, 8lengths of 12mm rod, 1,500 blocks at most and 30-50k labour cost can comfortably achieve dt. So u can check d cost of dis materials urself . I really appreciate this. Maybe I need to change engineer |
Re: Help With Costing Of 4 Bedroom Bungalow by Valentine87: 7:21am On Mar 18, 2020 |
Bro search for this thread on properties section and post your request on it ........ General Topic Thread-To Discuss Anything And Everything in Building Construction |
Re: Help With Costing Of 4 Bedroom Bungalow by Perfecttouchade: 7:23am On Mar 18, 2020 |
grafixdon: Na Wa o. No one is willing to help cc: saydfact |
Re: Help With Costing Of 4 Bedroom Bungalow by Perfecttouchade: 7:25am On Mar 18, 2020 |
|
Re: Help With Costing Of 4 Bedroom Bungalow by Valentine87: 7:41am On Mar 18, 2020 |
this what some else spent in finishing all his bock work of a bungalow that is even bigger This what I have spent to this stage. Labour Cost for Foundation Excavation, Blinding and Block setting to Lintel = 180000 Blinding Cement - 30 bags @ 2500 = 75,000 Sharp Sand - 20 tonnes = 32,000 Granite - 25 tonnes = 105,000 Total = 212,000 Foundation Block Setting & Sock away Pit Blocks = 1400 @ 150 = 210,000 Cement - 30 bags @ 2400 = 72,000 Sharp Sand =15 tonnes = 24,000 Labour for Soak away = 62,000 Extra Labour Expenses = 20,000 Total = 388,000 Foundation Filling Labour = 92,000 Laterite = 326,000 Total = 418000 DPC - Half DPM Nylon = 11,500 Granite= 10 tonnes = 45,000 Tara = 10 tonnes =13,000 Sharp sand = 10 tonnes = 15,500 Planks - 25 pieces & nails = 25000 Iron 16mm - 4 lengths @4400 = 17600 8mm - 3 lengths @ 1250 = 3750 Binding wire =2500 Transport = 2500 Workmanship Labourer = 40000 Welder and carpenter = 13000 Cement = 28 bags @ 2500= 70000 Wire Mesh = 10500 Total = 273,000 Above Foundation Block setting + 2 soak away pits Blocks 4100 @ 150 = 615000 Water = 3000 Sharp sand = 36000 Joining sand = 18000 Cement @2500 =162500 labour = 56000 Total = 891000 Lintel and Pillars Casting 16mm - 8 lengths @ 3630 = 29040 8mm - 31 lengths @ 1030 = 31930 12mm - 34 lengths @ 2050 = 69700 1 binding wire = 4000 Transport & logistics = 4000 Wood and planks ➕ TP = 51000 Granite = Used remains Sharp sand = 15000 Cement = 30 bags @ 2500 = 75000 Workmanship Labour 40000 Carpenter 22000 Iron bender 17000 Total =360000 Parapet and soak away Casting Iron plus 12mm - 30 lengths @ 1970 = 59100 8mm - 51 lengths @ 1420 = 72420 Big Binding wire @ 7000 Extra iron = 9000 Quarter rod - 15 lengths @ 200 = 3000 Transport = 3500 Workmanship = 25000 Wood and cutting = 175000 Nail = 11100 Transport = 4000 Workmanship = 40000 Granite = 20 tonnes = 100000 Sharp sand = 15 tonnes = 21000 Cement 50 bags @ = 130000 Labour = 50000 Total = 710,000 Electrical 20mm pipe = 2 bundles @2100 25mm pipe = 1 bundle @ 3200 Electrical materials = 14000 Workmanship =9000 Plumbing Internal plumbing Cost of pipes and accessories = 47,000 Labour = 18,000 Perfecttouchade: the link to the thread: https://www.nairaland.com/2550211/general-topic-thread-to-discuss-anything/1345 1 Like |
Re: Help With Costing Of 4 Bedroom Bungalow by grafixdon: 6:56pm On Mar 18, 2020 |
Valentine87: this what some else spent in finishing all his bock work of a bungalow that is even bigger
This what I have spent to this stage.
Labour Cost for Foundation Excavation, Blinding and Block setting to Lintel = 180000
Blinding Cement - 30 bags @ 2500 = 75,000 Sharp Sand - 20 tonnes = 32,000 Granite - 25 tonnes = 105,000 Total = 212,000
Foundation Block Setting & Sock away Pit Blocks = 1400 @ 150 = 210,000 Cement - 30 bags @ 2400 = 72,000 Sharp Sand =15 tonnes = 24,000 Labour for Soak away = 62,000 Extra Labour Expenses = 20,000 Total = 388,000
Foundation Filling Labour = 92,000 Laterite = 326,000 Total = 418000
DPC - Half DPM Nylon = 11,500 Granite= 10 tonnes = 45,000 Tara = 10 tonnes =13,000 Sharp sand = 10 tonnes = 15,500 Planks - 25 pieces & nails = 25000 Iron 16mm - 4 lengths @4400 = 17600 8mm - 3 lengths @ 1250 = 3750 Binding wire =2500 Transport = 2500 Workmanship Labourer = 40000 Welder and carpenter = 13000 Cement = 28 bags @ 2500= 70000 Wire Mesh = 10500 Total = 273,000
Above Foundation Block setting + 2 soak away pits Blocks 4100 @ 150 = 615000 Water = 3000 Sharp sand = 36000 Joining sand = 18000 Cement @2500 =162500 labour = 56000 Total = 891000
Lintel and Pillars Casting 16mm - 8 lengths @ 3630 = 29040 8mm - 31 lengths @ 1030 = 31930 12mm - 34 lengths @ 2050 = 69700 1 binding wire = 4000 Transport & logistics = 4000 Wood and planks ➕ TP = 51000 Granite = Used remains Sharp sand = 15000 Cement = 30 bags @ 2500 = 75000 Workmanship Labour 40000 Carpenter 22000 Iron bender 17000 Total =360000
Parapet and soak away Casting Iron plus 12mm - 30 lengths @ 1970 = 59100 8mm - 51 lengths @ 1420 = 72420 Big Binding wire @ 7000 Extra iron = 9000 Quarter rod - 15 lengths @ 200 = 3000 Transport = 3500 Workmanship = 25000 Wood and cutting = 175000 Nail = 11100 Transport = 4000 Workmanship = 40000 Granite = 20 tonnes = 100000 Sharp sand = 15 tonnes = 21000 Cement 50 bags @ = 130000 Labour = 50000 Total = 710,000
Electrical 20mm pipe = 2 bundles @2100 25mm pipe = 1 bundle @ 3200 Electrical materials = 14000 Workmanship =9000
Plumbing Internal plumbing Cost of pipes and accessories = 47,000 Labour = 18,000
Valentine87: this what some else spent in finishing all his bock work of a bungalow that is even bigger
This what I have spent to this stage.
Labour Cost for Foundation Excavation, Blinding and Block setting to Lintel = 180000
Blinding Cement - 30 bags @ 2500 = 75,000 Sharp Sand - 20 tonnes = 32,000 Granite - 25 tonnes = 105,000 Total = 212,000
Foundation Block Setting & Sock away Pit Blocks = 1400 @ 150 = 210,000 Cement - 30 bags @ 2400 = 72,000 Sharp Sand =15 tonnes = 24,000 Labour for Soak away = 62,000 Extra Labour Expenses = 20,000 Total = 388,000
Foundation Filling Labour = 92,000 Laterite = 326,000 Total = 418000
DPC - Half DPM Nylon = 11,500 Granite= 10 tonnes = 45,000 Tara = 10 tonnes =13,000 Sharp sand = 10 tonnes = 15,500 Planks - 25 pieces & nails = 25000 Iron 16mm - 4 lengths @4400 = 17600 8mm - 3 lengths @ 1250 = 3750 Binding wire =2500 Transport = 2500 Workmanship Labourer = 40000 Welder and carpenter = 13000 Cement = 28 bags @ 2500= 70000 Wire Mesh = 10500 Total = 273,000
Above Foundation Block setting + 2 soak away pits Blocks 4100 @ 150 = 615000 Water = 3000 Sharp sand = 36000 Joining sand = 18000 Cement @2500 =162500 labour = 56000 Total = 891000
Lintel and Pillars Casting 16mm - 8 lengths @ 3630 = 29040 8mm - 31 lengths @ 1030 = 31930 12mm - 34 lengths @ 2050 = 69700 1 binding wire = 4000 Transport & logistics = 4000 Wood and planks ➕ TP = 51000 Granite = Used remains Sharp sand = 15000 Cement = 30 bags @ 2500 = 75000 Workmanship Labour 40000 Carpenter 22000 Iron bender 17000 Total =360000
Parapet and soak away Casting Iron plus 12mm - 30 lengths @ 1970 = 59100 8mm - 51 lengths @ 1420 = 72420 Big Binding wire @ 7000 Extra iron = 9000 Quarter rod - 15 lengths @ 200 = 3000 Transport = 3500 Workmanship = 25000 Wood and cutting = 175000 Nail = 11100 Transport = 4000 Workmanship = 40000 Granite = 20 tonnes = 100000 Sharp sand = 15 tonnes = 21000 Cement 50 bags @ = 130000 Labour = 50000 Total = 710,000
Electrical 20mm pipe = 2 bundles @2100 25mm pipe = 1 bundle @ 3200 Electrical materials = 14000 Workmanship =9000
Plumbing Internal plumbing Cost of pipes and accessories = 47,000 Labour = 18,000
Thank you for this 1 Like |
Re: Help With Costing Of 4 Bedroom Bungalow by Godisgreatest1: 7:41pm On Mar 18, 2020 |
Valentine87: this what some else spent in finishing all his bock work of a bungalow that is even bigger
This what I have spent to this stage.
Labour Cost for Foundation Excavation, Blinding and Block setting to Lintel = 180000
Blinding Cement - 30 bags @ 2500 = 75,000 Sharp Sand - 20 tonnes = 32,000 Granite - 25 tonnes = 105,000 Total = 212,000
Foundation Block Setting & Sock away Pit Blocks = 1400 @ 150 = 210,000 Cement - 30 bags @ 2400 = 72,000 Sharp Sand =15 tonnes = 24,000 Labour for Soak away = 62,000 Extra Labour Expenses = 20,000 Total = 388,000
Foundation Filling Labour = 92,000 Laterite = 326,000 Total = 418000
DPC - Half DPM Nylon = 11,500 Granite= 10 tonnes = 45,000 Tara = 10 tonnes =13,000 Sharp sand = 10 tonnes = 15,500 Planks - 25 pieces & nails = 25000 Iron 16mm - 4 lengths @4400 = 17600 8mm - 3 lengths @ 1250 = 3750 Binding wire =2500 Transport = 2500 Workmanship Labourer = 40000 Welder and carpenter = 13000 Cement = 28 bags @ 2500= 70000 Wire Mesh = 10500 Total = 273,000
Above Foundation Block setting + 2 soak away pits Blocks 4100 @ 150 = 615000 Water = 3000 Sharp sand = 36000 Joining sand = 18000 Cement @2500 =162500 labour = 56000 Total = 891000
Lintel and Pillars Casting 16mm - 8 lengths @ 3630 = 29040 8mm - 31 lengths @ 1030 = 31930 12mm - 34 lengths @ 2050 = 69700 1 binding wire = 4000 Transport & logistics = 4000 Wood and planks ➕ TP = 51000 Granite = Used remains Sharp sand = 15000 Cement = 30 bags @ 2500 = 75000 Workmanship Labour 40000 Carpenter 22000 Iron bender 17000 Total =360000
Parapet and soak away Casting Iron plus 12mm - 30 lengths @ 1970 = 59100 8mm - 51 lengths @ 1420 = 72420 Big Binding wire @ 7000 Extra iron = 9000 Quarter rod - 15 lengths @ 200 = 3000 Transport = 3500 Workmanship = 25000 Wood and cutting = 175000 Nail = 11100 Transport = 4000 Workmanship = 40000 Granite = 20 tonnes = 100000 Sharp sand = 15 tonnes = 21000 Cement 50 bags @ = 130000 Labour = 50000 Total = 710,000
Electrical 20mm pipe = 2 bundles @2100 25mm pipe = 1 bundle @ 3200 Electrical materials = 14000 Workmanship =9000
Plumbing Internal plumbing Cost of pipes and accessories = 47,000 Labour = 18,000
Well detailed and clear, thank you and best regards. |
Re: Help With Costing Of 4 Bedroom Bungalow by grafixdon: 7:53pm On Mar 18, 2020 |
|
Re: Help With Costing Of 4 Bedroom Bungalow by Amastermovic(m): 7:55pm On Mar 18, 2020 |
I will post tomorrow the quantity of the materials needed to the last block excluding roofing.. After that stage I might help u with d quantity of tiles needed also ..mind you u will fix d price to each material urself will just tell u d quantity..
[color=#006600][/color] |
Re: Help With Costing Of 4 Bedroom Bungalow by Perfecttouchade: 9:42pm On Mar 18, 2020 |
|
Re: Help With Costing Of 4 Bedroom Bungalow by grafixdon: 3:11pm On Mar 19, 2020 |
Amastermovic: I will post tomorrow the quantity of the materials needed to the last block excluding roofing.. After that stage I might help u with d quantity of tiles needed also ..mind you u will fix d price to each material urself will just tell u d quantity..
[color=#006600][/color] Thanks boss |
Re: Help With Costing Of 4 Bedroom Bungalow by saydfact(m): 11:25pm On Mar 19, 2020 |
Perfecttouchade: cc: saydfact Plus send a WhatsApp message pls. I can't promise full estimate but Ian help with major.breakdown.. Been busy and unavailable. Thanks |
Re: Help With Costing Of 4 Bedroom Bungalow by yak(m): 11:40pm On Apr 02, 2020 |
Valentine87: this what some else spent in finishing all his bock work of a bungalow that is even bigger
This what I have spent to this stage.
Labour Cost for Foundation Excavation, Blinding and Block setting to Lintel = 180000
Blinding Cement - 30 bags @ 2500 = 75,000 Sharp Sand - 20 tonnes = 32,000 Granite - 25 tonnes = 105,000 Total = 212,000
Foundation Block Setting & Sock away Pit Blocks = 1400 @ 150 = 210,000 Cement - 30 bags @ 2400 = 72,000 Sharp Sand =15 tonnes = 24,000 Labour for Soak away = 62,000 Extra Labour Expenses = 20,000 Total = 388,000
Foundation Filling Labour = 92,000 Laterite = 326,000 Total = 418000
DPC - Half DPM Nylon = 11,500 Granite= 10 tonnes = 45,000 Tara = 10 tonnes =13,000 Sharp sand = 10 tonnes = 15,500 Planks - 25 pieces & nails = 25000 Iron 16mm - 4 lengths @4400 = 17600 8mm - 3 lengths @ 1250 = 3750 Binding wire =2500 Transport = 2500 Workmanship Labourer = 40000 Welder and carpenter = 13000 Cement = 28 bags @ 2500= 70000 Wire Mesh = 10500 Total = 273,000
Above Foundation Block setting + 2 soak away pits Blocks 4100 @ 150 = 615000 Water = 3000 Sharp sand = 36000 Joining sand = 18000 Cement @2500 =162500 labour = 56000 Total = 891000
Lintel and Pillars Casting 16mm - 8 lengths @ 3630 = 29040 8mm - 31 lengths @ 1030 = 31930 12mm - 34 lengths @ 2050 = 69700 1 binding wire = 4000 Transport & logistics = 4000 Wood and planks ➕ TP = 51000 Granite = Used remains Sharp sand = 15000 Cement = 30 bags @ 2500 = 75000 Workmanship Labour 40000 Carpenter 22000 Iron bender 17000 Total =360000
Parapet and soak away Casting Iron plus 12mm - 30 lengths @ 1970 = 59100 8mm - 51 lengths @ 1420 = 72420 Big Binding wire @ 7000 Extra iron = 9000 Quarter rod - 15 lengths @ 200 = 3000 Transport = 3500 Workmanship = 25000 Wood and cutting = 175000 Nail = 11100 Transport = 4000 Workmanship = 40000 Granite = 20 tonnes = 100000 Sharp sand = 15 tonnes = 21000 Cement 50 bags @ = 130000 Labour = 50000 Total = 710,000
Electrical 20mm pipe = 2 bundles @2100 25mm pipe = 1 bundle @ 3200 Electrical materials = 14000 Workmanship =9000
Plumbing Internal plumbing Cost of pipes and accessories = 47,000 Labour = 18,000
what's the size of this property sir? because I have a small 3bed bungalow that got to bungalow today. can't continue because of the govt lockdown order |