The Making Of The "7 Bedrooms High Ceiling Bungalow" In Anambra - Properties (30) - Nairaland

Nairaland Forum / Nairaland / General / Properties / The Making Of The "7 Bedrooms High Ceiling Bungalow" In Anambra (80443 Views)

The Making Of The "Owerri Royal Manor" / The Making Of The "Akure 5 Bedroom Duplex" / The Making Of The Enugu 6 Bedroom Duplex (2) (3) (4)

(1) (2) (3) ... (27) (28) (29) (30) (31) (32) (33) ... (46) (Reply) (Go Down)

Re: The Making Of The "7 Bedrooms High Ceiling Bungalow" In Anambra by sonnie10: 7:24pm On Nov 22, 2021
spyder880:


Which city Sir?
Ihiala.
Re: The Making Of The "7 Bedrooms High Ceiling Bungalow" In Anambra by spyder880(m): 7:28pm On Nov 22, 2021
sonnie10:
Ihiala.

Ihiala is nearer to Onitsha than most other cities where stone coated roofing dealers are. Wichtech is very costly now, almost 70 % more costly than others, so I will suggest Swisstech tiles based in Awka. I will look for their contacts and post later.

1 Like

Re: The Making Of The "7 Bedrooms High Ceiling Bungalow" In Anambra by sonnie10: 7:33pm On Nov 22, 2021
spyder880:


Ihiala is nearer to Onitsha than most other cities where stone coated roofing dealers are. Wichtech is very costly now, almost 70 % more costly than others, so I will suggest Swisstech tiles based in Awka. I will look for their contacts and post later.
Thank you. I am waiting.

1 Like

Re: The Making Of The "7 Bedrooms High Ceiling Bungalow" In Anambra by spyder880(m): 7:40pm On Nov 22, 2021
We are done with every finish touches on tiles in this house.

3 Likes

Re: The Making Of The "7 Bedrooms High Ceiling Bungalow" In Anambra by michlins(m): 8:15pm On Nov 22, 2021
donforeign:


I will snap and show you tomorrow
measure the available space and if it's about 7ft by 7ft, you are safe
Re: The Making Of The "7 Bedrooms High Ceiling Bungalow" In Anambra by dongc(m): 10:28pm On Nov 22, 2021
sonnie10:
Thank you. I am waiting.

If I am not mistaken this guys below?

https://swissmetrotiles.com/

Spyder880?

Re: The Making Of The "7 Bedrooms High Ceiling Bungalow" In Anambra by spyder880(m): 10:41pm On Nov 22, 2021
dongc:


If I am not mistaken this guys below?

https://swissmetrotiles.com/

Spyder880?

Yes, that's them. I've been in that their Awka express office many times.

1 Like

Re: The Making Of The "7 Bedrooms High Ceiling Bungalow" In Anambra by sonnie10: 8:34am On Nov 23, 2021
dongc:


If I am not mistaken this guys below?

https://swissmetrotiles.com/

Spyder880?
Thanks.,I will give them a call.
Re: The Making Of The "7 Bedrooms High Ceiling Bungalow" In Anambra by Godisgreatest1: 10:22am On Nov 23, 2021
spyder880:
We are dome with every finish touches on tiles in this house.

Please what type of floor tile did you use for the bathroom. And also, are there cracks between the WC and floor tiles as common with Nigerian tilers? Thank you.
Re: The Making Of The "7 Bedrooms High Ceiling Bungalow" In Anambra by spyder880(m): 6:04pm On Nov 23, 2021
Godisgreatest1:


Please what type of floor tile did you use for the bathroom. And also, are there cracks between the WC and floor tiles as common with Nigerian tilers? Thank you.

We used high quality Nigerian made Royal tiles brand. My tilers did a great work with it.

2 Likes 1 Share

Re: The Making Of The "7 Bedrooms High Ceiling Bungalow" In Anambra by spyder880(m): 9:52pm On Nov 24, 2021
Our work at the swimming pool is still ongoing today.......

1 Like

Re: The Making Of The "7 Bedrooms High Ceiling Bungalow" In Anambra by spyder880(m): 9:57pm On Nov 24, 2021
Work is ongoing with our inspection chambers all around the house, the work should be completed by today......

2 Likes

Re: The Making Of The "7 Bedrooms High Ceiling Bungalow" In Anambra by spyder880(m): 10:32pm On Nov 24, 2021
More

1 Like

Re: The Making Of The "7 Bedrooms High Ceiling Bungalow" In Anambra by spyder880(m): 10:35pm On Nov 24, 2021
Drilling the borehole for water continues.........

1 Like 1 Share

Re: The Making Of The "7 Bedrooms High Ceiling Bungalow" In Anambra by spyder880(m): 8:04am On Nov 25, 2021
All hands on deck this morning. Race against time.

1 Like

Re: The Making Of The "7 Bedrooms High Ceiling Bungalow" In Anambra by IjebuWarrior: 11:20am On Nov 25, 2021
spyder880:
All hands on deck this morning. Race against time.

Sir, what's the total cost of your roofing sheets (labor installation inclusive)?

Thanks
Re: The Making Of The "7 Bedrooms High Ceiling Bungalow" In Anambra by spyder880(m): 11:24am On Nov 25, 2021
IjebuWarrior:


Sir, what's the total cost of your roofing sheets (labor installation inclusive)?

Thanks

About N3.2m

2 Likes

Re: The Making Of The "7 Bedrooms High Ceiling Bungalow" In Anambra by IjebuWarrior: 11:30am On Nov 25, 2021
spyder880:


About N3.2m

I appreciate the swift response, sir!

2 Likes

Re: The Making Of The "7 Bedrooms High Ceiling Bungalow" In Anambra by AlphamaleTech1(m): 6:38pm On Nov 25, 2021
spyder880:


Bio digester is a technology that hasn't gained much popularity in my side of the country, the south east. I haven't done a bio digested before, and I must add that I have never seen anyone who has done one in the whole houses I have visited in the south east or south south.

I might not be the best person to compare the two, because of my limited knowledge about bio digester. Thank you.



Bio Digester is the best, it was developed to counter the disadvantages of our local smelling soak away..... It doesn't smell or allows rodent, it doesn't get filled because of the degradable materials used during installation, it can work for both dry and water side area, very affordable, users friendly, it doesn't collapse or sink unlike the old soak away...am an expert in this field,av worked in different part of east but based in lagos....we work nation wide... U can contact me on 08165641857 for more info

1 Like

Re: The Making Of The "7 Bedrooms High Ceiling Bungalow" In Anambra by donforeign: 10:04am On Nov 26, 2021
Oga Spyder I want to wrap my pillars, I am confused on what to use .. should I use the tiles below or South Africa burnt bricks ?

Re: The Making Of The "7 Bedrooms High Ceiling Bungalow" In Anambra by spyder880(m): 11:34am On Nov 26, 2021
donforeign:
Oga Spyder I want to wrap my pillars, I am confused on what to use .. should I use the tiles below or South Africa burnt bricks ?

These look very good, and they are new in the market too.

1 Like

Re: The Making Of The "7 Bedrooms High Ceiling Bungalow" In Anambra by donforeign: 1:06pm On Nov 26, 2021
spyder880:


These look very good, and they are new in the market too.
which will you advice me to use?
Re: The Making Of The "7 Bedrooms High Ceiling Bungalow" In Anambra by sonnie10: 5:14pm On Nov 26, 2021
donforeign:
Oga Spyder I want to wrap my pillars, I am confused on what to use .. should I use the tiles below or South Africa burnt bricks ?
I will actually prefer this tile for lower part of my building to prevent water splashes. What is the price?

1 Like

Re: The Making Of The "7 Bedrooms High Ceiling Bungalow" In Anambra by spyder880(m): 7:09pm On Nov 26, 2021
donforeign:
which will you advice me to use?

This tiles. They look nice and will not change colour easily.

1 Like

Re: The Making Of The "7 Bedrooms High Ceiling Bungalow" In Anambra by spyder880(m): 7:10pm On Nov 26, 2021
Still working on the swimming pool this evening. Mounting the skimmer.

1 Like

Re: The Making Of The "7 Bedrooms High Ceiling Bungalow" In Anambra by spyder880(m): 7:17pm On Nov 26, 2021
Compound floor works in progress.........

1 Like

Re: The Making Of The "7 Bedrooms High Ceiling Bungalow" In Anambra by spyder880(m): 7:21pm On Nov 26, 2021
Everyone is busy.........

1 Like

Re: The Making Of The "7 Bedrooms High Ceiling Bungalow" In Anambra by spyder880(m): 7:31pm On Nov 26, 2021
And we have started working on our giant elephant statue, this is not Rochas house oooo grin

3 Likes

Re: The Making Of The "7 Bedrooms High Ceiling Bungalow" In Anambra by sonnie10: 8:40pm On Nov 26, 2021
dongc:


If I am not mistaken this guys below?

https://swissmetrotiles.com/

Spyder880?

None of these numbers are working. I still need their contact.
Re: The Making Of The "7 Bedrooms High Ceiling Bungalow" In Anambra by michlins(m): 8:52pm On Nov 26, 2021
spyder880:
Everyone is busy.........
the welder that did that job is good and I respect him

1 Like

Re: The Making Of The "7 Bedrooms High Ceiling Bungalow" In Anambra by spyder880(m): 9:33pm On Nov 26, 2021
michlins:
the welder that did that job is good and I respect him

Thank you bro.

(1) (2) (3) ... (27) (28) (29) (30) (31) (32) (33) ... (46) (Reply)

I Cried When I Entered The Houses Of Billionaires In Lekki / These Houses In Ebute Metta Are Too Close To Each Other (pictures) / Lagos Family Houses (Pictures)

Viewing this topic: 3 guest(s)

(Go Up)

Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health
religion celebs tv-movies music-radio literature webmasters programming techmarket

Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 28
Disclaimer: Every Nairaland member is solely responsible for anything that he/she posts or uploads on Nairaland.